Home / Browse projects / Mumbai Suburban, Maharashtra / SAFAL GANGA SMRUTI

Registered No litigation declared Residential / Group Housing project

SAFAL GANGA SMRUTI

By VARUN HOMES PVT LTD

RG-MH-27946 · RERA P51800024417 · Last updated on MahaRERA portal: 24 Apr 2026

Source: official MahaRERA filing

Red flags

  • 3 complaints at MahaRERA
  • Completion date moved by 32 months
  • 4 extensions taken
  • Rs 24.00 crore secured on the land, in favour of STATE BANK OF INDIA

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Nov 2026Possession promisedmoved 32 months from the original
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 61%
28 of 63Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 98 documents Report an error

SAFAL GANGA SMRUTI is a Residential / Group Housing project by VARUN HOMES PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800024417 on 12 Feb 2020. Possession is promised by 30 Nov 2026. The completion date has moved by 32 months from the original filing. 35 of the 63 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameSAFAL GANGA SMRUTI
  • TypeResidential / Group Housing
  • Location
    • R.C.MARG VILLAGE MARAVALI
    • GHATKOPER MAHUL ROAD MUMBAI
    • Kurla
    • Mumbai Suburban
    • 400074
  • Pincode400074
  • RERA no.P51800024417
  • ReraGenie IDRG-MH-27946

Builder

  • NameVARUN HOMES PVT LTD
  • Entity typeCompany
  • DirectorsVARUN VINOD ASRANI, SANJAY VINOD ASRANI
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredFeb 2020First promiseMar 2024Revised toNov 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on12 Feb 2020
  • Promised completion30 Nov 2026
  • Revised completionRevised to 30 Nov 2026 (originally 30 Mar 2024)
  • Buildings1 building record
  • Documents filed98 files

Current status

56%35 of 63 units booked
66.6%Work done, per cost certificate

Figures as on 24 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAFAL GANGA SMRUTINA191763063

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 61%.

SAFAL GANGA SMRUTI: 52% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure61%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises8%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks61%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.6%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed66

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots66
Closed/Covered66

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,278 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofSTATE BANK OF INDIA
Secured amountRs 24.00 crore
CERSAI search filedYes
Declared on16 Sep 2024

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI3448.04
Proposed, not sanctioned2,549 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchB G AGARWAL MARKET SHYAMKAMAL TRADE CENTRE VILE PARLE EAST MUMBAI 400057
Estimated costRs 19.44 cr
Cost incurredRs 12.95 cr
Work done66.61%
BuildingWingEstimatedIncurred
SAFAL GANGA SMRUTINARs 15.44 crRs 12.95 cr
-NARs 4.00 cr-

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerVIJAY NARANG
Chartered AccountantP.C. DHOLAKIA & CO
Chartered AccountantBANWAT & CO
PartnerRole in project
VARUN HOMES PVT LTD-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800017542Mar 2024 → Sep 2024

Reason as filed by the promoterDUE TO SHORTAGE OF TDR IN MARKET , WE ARE UNABLE TO BUY THE SAME. SO 6 MONTHS EXTENSION IS REQUIRED FOR PURCHASE OF TDR AND CONSTRUCTION OF ADDITIONAL 9 FLOOR OF THE BUILDING.

EXT51800024141Mar 2024 → Mar 2025

Reason as filed by the promoterBuilding work is completed up to 12 th floor and internal work is in progress, earlier developer had taken extension up to September 2024, extension was received in November 2023, Developer took TDR upto 17th floor and taken approval from commissioner which took 8 months. Now Developer is waiting for fund allocation from Bank, as Developer have taken construction finance. Therefore, developer require additional 6 months i.e. by 31 st March 2025 to complete the construction of project.

EXT51800028049Mar 2024 → Mar 2026

Reason as filed by the promoterDue to financial constraints faced ,construction work of the building are not yet completed. Therefore, the we Require additional time i.e. extension upto 31st March 2026 to complete the construction of project. We request you to do the needful.

EA24042620729Mar 2024 → Nov 2026

Reason as filed by the promoterDue to financial issue progress was slow , now all the financial issues have been fully resolved, and construction work has recommenced in full swing with adequate manpower, machinery, and materials deployed at site. Considering the present progress and the revised construction schedule, we requires an additional 8 months (up to November 2026) to complete the project in all respects.

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC12602144Jyoti Hanumant GaikwadVARUN HOMES PVT LTD11/04/2026
CC12603468SHAKIL JALIL KHANVARUN HOMES PVT LTD05/06/2026
CC12603592SHAKIL JALIL KHANVARUN HOMES PVT LTD10/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Feb 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Feb 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Apr 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Apr 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Nov 2026

Documents filed98

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 98 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement certificateFile: GANGA SMRUTI FULL CC.pdf24 Apr 2026
Building plan approvalFile: APPROVED PLAN LETTER may 2025.pdf24 Apr 2026
Building plan approvalFile: GS APPROVAL MAY 2025.pdf24 Apr 2026
Withdrawal Update Form 1File: GS FORM 1 JUNE 2025.pdf24 Apr 2026
Withdrawal Update Form 1File: GS FORM 1 SEPT 2025.pdf24 Apr 2026
Withdrawal Update Form 1File: GS FROM 1 DEC 2025.pdf24 Apr 2026
Withdrawal Update Form 1File: GS FORM 1 MAR 2026.pdf24 Apr 2026
Withdrawal Update Form 2File: FORM 2 GS JUNE 2025.pdf24 Apr 2026
Withdrawal Update Form 2File: FORM 2 GANGA SMRUTI SEPT 2025.pdf24 Apr 2026
Withdrawal Update Form 2File: FORM 2 GANGA SMRUTI DEC 2025.pdf24 Apr 2026
Withdrawal Update Form 2File: FORM 2 GS MAR 2026.pdf24 Apr 2026
Withdrawal Update Form 3File: FROM 3 30TH JUNE 2025.pdf24 Apr 2026
Withdrawal Update Form 3File: FROM 3 30TH SEPTEMBER 2025.pdf24 Apr 2026
Withdrawal Update Form 3File: FROM 3 31ST DECEMBER 2025.pdf24 Apr 2026
Withdrawal Update Form 3File: form 3 gs mar 2026.pdf24 Apr 2026
Form 2A (FY 2024-2025)File: CGS Form 2A MAR 2026.pdf24 Apr 2026
Form 2A (FY 2025-2026)File: CGS Form 2A MAR 2026.pdf24 Apr 2026
Form 5 (FY 2025-2026)File: FORM 5 MAR 2026 GS.pdf24 Apr 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 MAR 2025.pdf17 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: GANGA SMRUTI FORM 3 MARCH 2025.pdf17 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: from 2 march 2025.pdf17 Apr 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF INVENTORY MAR 2025.pdf17 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2a 24- 25.pdf17 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 GANGA SMRUTI 2024 2025.pdf17 Apr 2025
Declaration in FORM BFile: FORM B GANGA SMRUTI.pdf2 Apr 2025
Disclosure of sold/ booked inventoryFile: Ganga Smruti DISCLOSURE OF INVENTORY.pdf2 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INETREST GS.pdf29 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: CGS Form 2A.pdf29 Mar 2025
Declaration in FORM BFile: GANGA SMRUTI FORM B UPDATED.pdf28 Mar 2025
CERSAI detailsFile: CERSAI GANGA SMRUTI (1).pdf28 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GANGA SMRUTI FORM 1 DEC 2024.pdf1 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 GANGA SMRUTI dec 2024.pdf1 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GANGA SMRUTI FORM 2 DEC 2024.pdf1 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SEPT 2024 GANGA SMRUTI.pdf9 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 GANAG SMRUTI SEPT 2024.pdf9 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GANGA SMRUTI FORM 2 SEPT 2024.pdf9 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT A DESIGNATED BANK GANGA SMRUTI.pdf28 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 GANGA SMRUTI 2023 24.pdf28 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 JUNE 2024.pdf7 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 JUNE 2024 GS.pdf7 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 JUNE 2024.pdf7 Oct 2024
Declaration about Commencement CertificateFile: FORM D GS.pdf3 Jul 2024
Disclosure of sold/ booked inventoryFile: INVENTORY UPDATE GS MARCH 2024.pdf3 Jul 2024
Building plan approvalFile: APPROVED PLAN LETTER GS.pdf2 Jul 2024
Building plan approvalFile: APPROVED PLAN GS.pdf2 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: APPROVED PLAN LETTER GS.pdf2 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: APPROVED PLAN GS.pdf2 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: CC GANGA SMRUTI.pdf2 Jul 2024
Declaration in FORM BFile: FORM B MARCH 25.pdf26 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 GANGA SMRUTI MARCH 2024.pdf12 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 GANGA SMRUTI MARCH 2024.pdf12 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 GANGA SMRUTI MAR 2024.pdf12 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SAFAL GANGA SMRUTI FROM 1 SEPT 2023.pdf27 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SAFAL GANGA SMRUTI FROM1 DEC 2023.pdf27 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SAFAL GANGA SMRUTI FROM 2 SEPT 2023.pdf27 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SAFAL GANGA SMRUTI FROM 2 DEC 2023.pdf27 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SAFAL GANGA SMRUTI FORM 3 SEPT 2023.pdf27 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA ACCOUNT CERTIFICATE FORM 3.pdf27 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SAFAL GANGA SMRUTI FROM 3 DEC 2023.pdf27 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 APRIL 2021 TO MAR 2022.pdf30 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 APRIL 2022 TO MAR 2023.pdf30 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A- ENGNEERING'S CERTIFICATE-19-20.pdf21 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A- ENGNEERING'S CERTIFICATE-20-21.pdf21 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A- ENGNEERING'S CERTIFICATE-21-22.pdf21 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A- ENGNEERING'S CERTIFICATE-22-23.pdf21 Sep 2023
Disclosure of sold/ booked inventoryFile: INVENTORY LIST JUNE 2023.pdf21 Sep 2023
Commencement Certificates / NA Order for plotted developmentFile: SAFAL GANGA SMRUTI REENDORSE CC .pdf21 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SMRUTI FORM 2 ENGINEER CERTIFICATE JANUARY 2023.pdf21 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SMRUTI FORM 3 CA CERTIFICATE JANUARY 2023.pdf21 Aug 2023
Details of encumbrancesFile: SBI GANGA SMRUTI EMCUMBRANCE CERTIFICATE.pdf3 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: GANGA SMRUTI FORM 5 2020.pdf22 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: GANGA SMRUTI FORM 5 2021.pdf22 Sep 2022
Building plan approvalFile: SAFAL GANGA SMRUTI IOD WITH PLAN.pdf6 Sep 2022
Building Plan Approval / NA Order for plotted developmentFile: SAFAL GANGA SMRUTI IOD WITH PLAN.pdf6 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SAFAL GANGA SMRUTI LS CERTICATE.pdf6 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SAFAL GANGA SMRUTI FORM 2 ANNEXURE B.pdf6 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SAFAL GANGA SMRUTI FORM 2A.pdf6 Sep 2022
Disclosure of sold/ booked inventoryFile: SAFAL GANGA SMRUTI DISCLOSURE OF INVENTORY .pdf6 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SAFAL GANGA SMRUTI CA CERTIFICATE.pdf6 Sep 2022
Proforma of Allotment letterFile: GANGA SMRUTI DRAFT AGREEMENT.pdf5 Sep 2022

How this compares with Mumbai Suburban

56%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 32 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAFAL GANGA SMRUTI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GHATKOPER MAHUL ROAD MUMBAI6,700+ in Mumbai Suburban

Builder: VARUN HOMES PVT LTD

VARUN HOMES PVT LTD has 2 registrations on MahaRERA, including SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD and SAFAL GANGA SMRUTI. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SAFAL GANGA SMRUTI is delayed beyond 30 Nov 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAFAL GANGA SMRUTI?

The registered promoter entity is VARUN HOMES PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAFAL GANGA SMRUTI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SAFAL GANGA SMRUTI?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SAFAL GANGA SMRUTI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAFAL GANGA SMRUTI?

The professionals named in the filing: Engineer: VIJAY NARANG; Chartered Accountant: P.C. DHOLAKIA & CO; Chartered Accountant: BANWAT & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAFAL GANGA SMRUTI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAFAL GANGA SMRUTI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAFAL GANGA SMRUTI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.