ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Sadguru Residence

Registration lapsed No litigation declared Residential / Group Housing project

Sadguru Residence

By Manoj Mandhare & Associates

RG-MH-11621 · RERA P52100010778 · Last updated on MahaRERA portal: 22 Jun 2021

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 37 months past the filed date
  • 5 complaints at MahaRERA
  • Completion date moved by 62 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 completed earlier projects delivered on promise

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2023Possession promised37 months past this date
4 of 11Construction stages donefurthest along: Internal walls, 80%
5Complaints at MahaRERAon this registration
Jump to the 29 documents Report an error

Sadguru Residence is a Residential / Group Housing project by Manoj Mandhare & Associates in Pune, Maharashtra, registered with MahaRERA as P52100010778 on 31 Aug 2017. Possession was promised by 30 Sep 2023 and is now 37 months past that date. The completion date has moved by 62 months from the original filing. 5 complaints are on record with the regulator.

At a glance

Project

  • NameSadguru Residence
  • TypeResidential / Group Housing
  • Location
    • Yerawada
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411006
  • Pincode411006
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100010778
  • ReraGenie IDRG-MH-11621

Builder

  • NameManoj Mandhare & Associates
  • Entity typeOthers
  • Named personAkshay Mandhare
  • Other registrations2 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

37 months past promisethis monthRegisteredAug 2017First promiseJul 2018Revised toSep 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Aug 2017
  • Promised completion30 Sep 2023
  • Revised completionRevised to 30 Sep 2023 (originally 31 Jul 2018)
  • Buildings1 building record
  • Documents filed29 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sadguru ResidenceNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Jun 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 80%.

Sadguru Residence: 56% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 22 Jun 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area522 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI753.47
Proposed, not sanctioned753 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch1206/34 Opp Hotel Pathik, Shivaji nagar, Pune 411004

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAakruti architects and designer
EngineerMr Santosh Patil
PartnerRole in project
Manoj Mandhare & Associates-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100009909Jul 2018 → Mar 2023

Reason as filed by the promoterThe project is 90% completed and Flats are allotted to land owners but there is no amount received from booking due to market issues. Major finances are invested by us in the project, But due to pandemic situation, we are facing problem for completing the project in time as committed earlier. Request you to please accept the request for extension of the project.

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC005000000085275Mr. Surendra Dnyaneshwar KambleM/s. Manoj Mandhare and AssociatesThrough its Proprietor Mr. Manoj P. Mandhare26/02/2021
CC005000000085303Mr. Sunil Tukaram KambleM/s. Manoj Mandhare and AssociatesThrough its Proprietor Mr. Manoj P. Mandhare06/03/2021
CC005000000085325Mr. Rajendra Tukaram KambleM/s. Manoj Mandhare and Associates Through its Proprietor Mr. Manoj P. Mandhare17/03/2021
CC005000000085430Mr. Fayyaz Gayasuddin ShaikhM/S. MANOJ MANDHARE AND ASSOCIATES Through its Proprietor Mr. Manoj P. Mandhare08/04/2021
CC005000000085609Mr. Ravindra Namdeo KambleM/s. Manoj Mandhare and Associates Through its Proprietor Mr. Manoj P. Mandhare31/05/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed29

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A Engineer's Certificate.pdf22 Jun 2021
Disclosure of sold/ booked inventoryFile: SOLD CIRCULAR 29(1).pdf22 Jun 2021
Certificates of CA (Form 3)File: Form 3_FY 2017-18_Q2.pdf24 May 2021
Certificates of CA (Form 3)File: Form 3_FY 2017-18_Q3.pdf24 May 2021
Certificates of CA (Form 3)File: Form 3_FY 2017-18_Q4.pdf24 May 2021
Certificates of CA (Form 3)File: Form 3_FY 18-19_Q1.pdf24 May 2021
Certificates of CA (Form 3)File: Form 3_FY 18-19_Q2.pdf24 May 2021
Certificates of CA (Form 3)File: Form 3_FY 18-19_Q3.pdf24 May 2021
Certificates of CA (Form 3)File: Form 3_FY 18-19_Q4.pdf24 May 2021
Certificates of CA (Form 3)File: Form 3_FY 19-20_Q1.pdf24 May 2021
Certificates of CA (Form 3)File: Form 3_FY 19-20_Q2.pdf24 May 2021
Certificates of CA (Form 3)File: Form 3_FY 19-20_Q3.pdf24 May 2021
Certificates of CA (Form 3)File: Form 3_FY 19-20_Q4.pdf24 May 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5_FY 17-18.pdf24 May 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5_FY 18-19.pdf24 May 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5_FY 19-20.pdf24 May 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf23 Mar 2018
Building plan approvalFile: PLAN.pdf1 Aug 2017
Layout approvalFile: PLAN.pdf1 Aug 2017
PAN CardFile: PAN.pdf1 Aug 2017
Copy of the legal title reportFile: Search And Title.pdf1 Aug 2017
Details of encumbrancesFile: Details Of Encumbrances.PDF1 Aug 2017
Copy of Layout Approval (in case of layout)File: PLAN.pdf1 Aug 2017
Building Plan Approval (IOD)File: PLAN.pdf1 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Certificate.pdf1 Aug 2017
Certificates of CA (Form 3)File: CA Certificate appilcation.PDF1 Aug 2017
Declaration in FORM BFile: Form B.PDF29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect certificate.PDF29 Jul 2017
Proforma of Allotment letterFile: Yerawada Flat Agreement draft.pdf29 Jul 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Torna MoharP52100015727Behind Bhartiya vidhyapeeth, Pune123Mar 2018OngoingDec 2028Registered original: Dec 2024Not due yet
Torana PranganS.no.51 Khandoba Paduka Chowk Dhayri Pune 41104156-CompletedOct 2016Oct 2016

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 62 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sadguru Residence on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Yerawada13,700+ in Pune

2 kmSadguru ResidenceCompleted 9Lapsed / revoked 5Other 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 15 registered projects within 2 km.

Builder: Manoj Mandhare & Associates

Manoj Mandhare & Associates has 3 registrations on MahaRERA, including Sadguru Residence and Torna Mohar. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Sadguru Residence shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Sadguru Residence is delayed beyond 30 Sep 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sadguru Residence?

The registered promoter entity is Manoj Mandhare & Associates, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sadguru Residence?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Sadguru Residence?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Sadguru Residence?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sadguru Residence?

The professionals named in the filing: Architect: Aakruti architects and designer; Engineer: Mr Santosh Patil. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sadguru Residence?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sadguru Residence. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sadguru Residence to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.