Home / Browse projects / Dakshina Kannada, Karnataka / S Cube Nest

Registration approved Mixed Development project

S Cube Nest

By VINU G NAIR

RG-KA-03033 · RERA PRM/KA/RERA/1257/334/PR/210928/004308 · Last updated on RERA Karnataka portal: 10 Sep 2021

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Jun 2023Possession promisedmoved 6 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 106 documents Report an error

S Cube Nest is a Mixed Development project by VINU G NAIR in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/210928/004308 on 28 Sep 2021. Possession is promised by 30 Jun 2023. The completion date has moved by 6 months from the original filing.

At a glance

Project

  • NameS Cube Nest
  • TypeMixed Development
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/210928/004308
  • ReraGenie IDRG-KA-03033

Builder

  • NameVINU G NAIR
  • Entity typeProprietorship Firm
  • Authorized SignatoryVINU G NAIR

Key dates

this monthRegisteredSep 2021First promiseDec 2022Revised toJun 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on28 Sep 2021
  • Promised completion30 Jun 2023
  • Revised completionRevised to 30 Jun 2023 (originally 24 Dec 2022)
  • Buildings1 building record
  • Documents filed106 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
S Cube Nest-----22

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 10 Sep 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & CeilingNot applicable
Joinery: Doors, Windows, Ventilators etcNot applicable
Basic work of Water supply, Sanitary and ElectrificationNot applicable
Dadoing, Skirting, Flooring, Tiles work (All types)Not applicable
Railing and Grill fixingNot applicable
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
PaintingNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

As on 10 Sep 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemNoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area607 sq m
Named landowners2
LandownerVillageDistrict
Mrs.BEEFATHUMMA--
Mr. MUKHTAR M. SHAREEF--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 3.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr. Snehaja
EngineerH Anand Bhat

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1257/334/PR/230321/004308Dec 2022 → Jun 2023

Reason as filed by the promoterShortage of Building Materials, Concrete, Jalli etc

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed106

As listed on the registration, under the names the promoter filed them with; the newest 80 of 106 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/210928/004308 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Deed Of Surrender of Mulgeni Right 5 centsFile: 5cents Property Documents.pdf10 Sep 2021
Katha with rectified adressFile: E Katha New S Cube Nest.pdf10 Sep 2021
2017-2018File: Vinu FS-2017-18.jpg21 Jul 2021
2018-2019File: Vinu FS-18-19.jpg21 Jul 2021
2019-2020File: Vinu FS-2019-20.jpg21 Jul 2021
BANK STATEMENTFile: S4 Enterprises Rera Bank Ac.pdf21 Jul 2021
certified copy of conversion order dated 17-01-2007 and conversion survey sketch.File: Certified copy of conversion order.pdf21 Jul 2021
Docement For Remaining 5CentsFile: 5cents Property Documents.pdf21 Jul 2021
Clear Copy of Rtc for 5 CentsFile: Document (1).pdf21 Jul 2021
Nest Plan Blueprint Image 1 Site plan & ground floor planFile: Nest Plan Blueprint Image 1.jpg9 Jul 2021
Nest Plan Blueprint Image 2 first floor plan & typical Floor PlanFile: Nest Plan Blueprint Image 2.jpg9 Jul 2021
Nest Plan Blueprint Image 3 Elivation, Section & Terrace Floor PlanFile: Nest Plan Blueprint Image 3.jpg9 Jul 2021
Nest Plan Copy 1 Site plan & ground floor planFile: Nest Plan Copy 1.jpg9 Jul 2021
Nest Plan Copy 2 first floor plan & typical Floor PlanFile: Nest Plan Copy 2.jpg9 Jul 2021
Nest Plan Copy 3 Elivation, Section & Terrace Floor PlanFile: Nest Plan Copy 3.jpg9 Jul 2021
Bank Name mentioned as per direction circularFile: Bank Statement.pdf9 Jul 2021
Conversion orderFile: CONVERSION 684 DATED 24 11 2006.pdf9 Jul 2021
Conversion orderFile: CONVERSION 872 DATED 17 01 2007.pdf9 Jul 2021
Gift Deed By Mr. Mohammad shareef To Beefathumma W/o K Mohammad Shareef & S/o Mukthar M ShareefFile: GIFT DEED 9929 20-21.pdf9 Jul 2021
GPA By Mr. Mohammad shareef To Mr. Mukthar M Shareef S/o Mohammad shareefFile: GPA K MOHAMMED SHARIEF IN FAVOUR OF MUKTHAR M SHAREEF.pdf9 Jul 2021
Latest KathaFile: Befathuma Katha.pdf9 Jul 2021
Latest Tax PaidFile: 2021-22 Tax Receipt.pdf9 Jul 2021
EC up to 15062021File: EC S CUBE NEST 03 09 20 TO 15 06 2021.pdf9 Jul 2021
Form BFile: Form B Affidavit.pdf9 Jul 2021
JA AffidavitFile: JA Affidavit.pdf9 Jul 2021
AffidavitFile: Affidavit RERA.pdf9 Jul 2021
RELINQUISHMENT DEED 7814 2014-15File: RELINQUISHMENT DEED 7814 2014-15.pdf9 Jul 2021
Single siteFile: SINGLE SITE 04 03 2014.pdf9 Jul 2021
Property CardFile: PROPERTY CARD.pdf9 Jul 2021
1)3) Bank NameFile: Bank Statement.pdf14 Jun 2021
2)2) JDA - Relinquishment DeedFile: RELINQUISHMENT DEED 7814 2014-15.pdf14 Jun 2021
2)1) Conversion CopyFile: CONVERSION 872 DATED 17 01 2007.pdf14 Jun 2021
CertificateFile: REGISTRATION CERTIFICATE.pdf-
Architect Certificate for Work Completion Schedule till DateFile: 012.jpg-
Engineer Certificate for Work Completion Schedule till DateFile: 011.jpg-
CA Certificate for Funds UtilizationFile: FORM-EX3.pdf-
Architect Certificate for Pending Work Completion Schedule.File: 01.jpg-
Engineer Certificate for Pending Work Completion Schedule.File: 013.jpg-
CA Certificate for Funds required for Project CompletionFile: FORM-EX4.pdf-
AffidavitFile: Affidavit for seeking extension of Registered Project.pdf-
Latest Encumbrance CertificateFile: EC latest pdf.pdf-
Details Of Sold/ Un-sold UnitsFile: FORM 3 compressed file-5-6.pdf-
Lisence copy 1-converted-
BUILDING LICENSCE WITH PLAN-
BUILDING LICENSCE WITH PLAN-
Request Letter for RERA-
Sale Agreement draft-
SALE DEED 8405 2006-07-
BUILDING LICENSCE WITH PLAN-
Document 85-
Allotment letter-
Nest Broucher-
Project Specifications-
EC-
Request Letter for RERA-
Request Letter for RERA-
KHATHA IN THE NAME MOHAMMED SHARIFF-
JOINT AGREEMENT S CUBE NEST-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
CONVERSION 684 DATED 24 11 2006-
RELINQUISHMENT DEED 7814 2014-15-compressed-
Fire NOC (1)-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one moved by 6 months
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep S Cube Nest on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmS Cube NestOther 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 11 registered projects within 2 km.

Builder: VINU G NAIR

VINU G NAIR has 1 registration on RERA Karnataka, including S Cube Nest. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if S Cube Nest is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of S Cube Nest?

The registered promoter entity is VINU G NAIR, a proprietorship firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in S Cube Nest?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at S Cube Nest?

The professionals named in the filing: Architect: Ar. Snehaja; Engineer: H Anand Bhat. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in S Cube Nest?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About S Cube Nest. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save S Cube Nest to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.