RUSTTAGI AARAMBHA PHASE- I

By RUSTAGI ESTATES PRIVATE LIMITED

RG-MH-38311 · RERA P51700034204 · Last updated on MahaRERA portal: 30 Mar 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date
  • Completion date moved by 25 months
  • 2 extensions taken
  • Rs 15.00 crore secured on the land, in favour of Aditya Birla Finance Ltd

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2026Possession promised7 months past this date
22 of 22Construction stages doneacross 2 buildings; every applicable stage filed complete
5 of 18Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 169 documents Report an error

RUSTTAGI AARAMBHA PHASE- I is a Commercial project by RUSTAGI ESTATES PRIVATE LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700034204 on 25 Mar 2022. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 25 months from the original filing. 13 of the 18 units on this registration are recorded sold or booked, and 22 of 22 construction stages are filed complete.

At a glance

Project

  • NameRUSTTAGI AARAMBHA PHASE- I
  • TypeCommercial
  • Location
    • MDTC MHASKAL ROAD
    • TITWALA
    • Kalyan
    • Thane
    • 421605
  • Pincode421605
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700034204
  • ReraGenie IDRG-MH-38311

Builder

  • NameRUSTAGI ESTATES PRIVATE LIMITED
  • Entity typeCompany
  • DirectorsSANJAY SUBHASHCHAND GUPTA, RAJKUMAR DATTATRAY PATKAR, RAMIT SANJAY RUSTAGI, URVASHI SANJAY GUPTA, Bhavesh Sanjay Rustagi
  • Other registrations3 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

7 months past promisethis monthRegisteredMar 2022First promiseFeb 2024Revised toMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on25 Mar 2022
  • Promised completion31 Mar 2026
  • Revised completionRevised to 31 Mar 2026 (originally 22 Feb 2024)
  • Buildings2 building records
  • Documents filed169 files

Current status

72%13 of 18 units booked
100.0%Work done, per cost certificate

Figures as on 30 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 1NA20000
BUILDING NO 2NA2101818

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 30 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 22 construction stages are filed complete across 2 buildings.

BUILDING NO 1100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 2100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 30 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed10

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots10
Open Space10
BuildingOpen SpaceTotal
BUILDING NO 155
BUILDING NO 255

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area2,290 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofAditya Birla Finance Ltd
Secured amountRs 15.00 crore
CERSAI search filedYes
Declared on30 Mar 2026

Approvals and building plan

Sanctioning authorityMAHARASHTRA HOUSING AND DEVELOPMENT AUTHORITY
Permissible FSI250.28
Proposed, not sanctioned250 sq m
Buildings approved1
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 17 PLOT NO 2A SARASWATI BLDG SANROSHI MATA ROAD RAMBAUG KALYAN 421301
Estimated costRs 5.76 cr
Cost incurredRs 5.76 cr
Work done100.0%
BuildingWingEstimatedIncurred
BUILDING NO 1NARs 3.38 crRs 3.38 cr
BUILDING NO 2NARs 1.38 crRs 1.38 cr
-NARs 1.00 crRs 1.00 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUB ARCHITECTS
EngineerAJAY MAHALE & ASSOCIATES
Chartered AccountantRD Bhatia & Associates
Chartered AccountantK B BHAT
PartnerRole in project
RUSTAGI ESTATES PRIVATE LIMITED-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700019345Feb 2024 → Feb 2025

Reason as filed by the promoterthe Project got delayed due to various reasons including labour problem after COVID-19 impact because workers had gone to their native place. Apart of labour issues, there were changes in DP Rules and approval thereunder. Approval took lots of time in getting the revised plans amended and approved from the planning authority. We had to do correction in specification of the project having three phases in this same layout to meet the customers requirements. Thereafter approaching allottees to get their consent for changes in the specification in the project under section 14(2) of RERA. We now go

EA04072501948Feb 2024 → Mar 2026

Reason as filed by the promoterThe project is in its final stage of completion, with most construction and finishing works already completed. The delay in obtaining the Occupancy Certificate is due to ongoing documentation compliances and approvals from relevant authorities. Additionally, this phase is interconnected with another under-development phase, requiring coordinated completion of certain utilities and services. OC is expected in the coming months of 2025 only.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Apr 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 17 Feb 2025

Documents filed169

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 169 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM-1 PHASE-1.PDF30 Mar 2026
Withdrawal Update Form 1File: FORM-1 PHASE-1.PDF30 Mar 2026
Withdrawal Update Form 2File: FORM-2 PHASE-1.PDF30 Mar 2026
Withdrawal Update Form 2File: FORM-2 PHASE-1.PDF30 Mar 2026
Withdrawal Update Form 3File: FORM-3 PHASE-1.PDF30 Mar 2026
Withdrawal Update Form 3File: FORM-3 PHASE-1.PDF30 Mar 2026
Withdrawal Update Form 1File: FORM-1 PHASE-1.PDF29 Mar 2026
Withdrawal Update Form 2File: FORM-2 PHASE-1.PDF29 Mar 2026
Withdrawal Update Form 3File: FORM-3 PHASE-1.PDF29 Mar 2026
Withdrawal Update Form 1File: PHASE-1 FORM-1_0001.pdf10 Dec 2025
Withdrawal Update Form 1File: PHASE-1 FORM-1_0001.pdf10 Dec 2025
Withdrawal Update Form 1File: FORM-1 PHASE-1.PDF10 Dec 2025
Withdrawal Update Form 2File: PHASE-1 FORM-2_0001.pdf10 Dec 2025
Withdrawal Update Form 2File: PHASE-1 FORM-2_0001.pdf10 Dec 2025
Withdrawal Update Form 2File: FORM-2 PHASE-1.PDF10 Dec 2025
Withdrawal Update Form 3File: PHASE-1 FORM-3_0001.pdf10 Dec 2025
Withdrawal Update Form 3File: PHASE-1 FORM-3_0001.pdf10 Dec 2025
Withdrawal Update Form 3File: FORM-3 PHASE-1.PDF10 Dec 2025
Form 2A (FY 2024-2025)File: Form 2A Phase I_0001.pdf11 Sep 2025
Form 1File: Form 1.pdf23 Jul 2025
Form 2File: Form 2.pdf23 Jul 2025
Form 3File: Form 3.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold unsold.pdf23 Jul 2025
Form 1File: PHASE-1 FORM - 1.pdf19 Jul 2025
Form 2File: PHASE-1 FORM - 2.pdf19 Jul 2025
Form 3File: PHASE-1 FORM - 3_merged.pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: Phase I Sold_Unsold.pdf19 Jul 2025
Form 1File: Form 1 Architect certificate_Mar 22.pdf2 Jul 2025
Form 2File: Form 2_engineer_phase I_Mar22.pdf2 Jul 2025
Form 3File: Form 3 CA_Signed_phase I_Mar22.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: sold unsold phase_I Mar 22.pdf2 Jul 2025
Form 1File: Form 1_ Phase 1_Dec 22.pdf2 Jul 2025
Form 2File: Form 2 Phase1_Dec22.pdf2 Jul 2025
Form 3File: Form 3 Dec22.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold_Unsold Dec 22.pdf2 Jul 2025
Form 1File: form I Phase I_Mar23.pdf2 Jul 2025
Form 2File: form 2 Phase I_mar23.pdf2 Jul 2025
Form 3File: Form 3 Mar 23_Phase I.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold_Unsold Mar 23.pdf2 Jul 2025
Form 1File: Form 1 June 23 Phase I june23.pdf2 Jul 2025
Form 2File: Form 2 phase i june 2023.pdf2 Jul 2025
Form 3File: FORM 3 PHASE 1_June23.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold_Unsold June_23.pdf2 Jul 2025
Form 1File: SIGNED FORM 1 PHASE 1 Sep23.pdf2 Jul 2025
Form 2File: SIGNED FORM 2 PHASE 1 Sep 23.pdf2 Jul 2025
Form 3File: SIGNED FORM 3 PHASE 1_Sep23.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold_Unsold Sep_23.pdf2 Jul 2025
Form 1File: Form 1 Phase I Dec 23.PDF2 Jul 2025
Form 2File: Form 2 Phase I Dec 23.PDF2 Jul 2025
Form 3File: Phase I Form 3 Dec 23.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold_unsold_dec 23.pdf2 Jul 2025
Form 1File: form 1phase1_0001_Sep24.pdf2 Jul 2025
Form 2File: form 2 phase 1_0001_sep24.pdf2 Jul 2025
Form 3File: form 3 phase 1_Sep 24.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold_Unsold Sep_24.pdf2 Jul 2025
Form 1File: Form1_phase I Dec24.pdf2 Jul 2025
Form 2File: Form2_phase I Dec 24.pdf2 Jul 2025
Form 3File: FROM-3 PHASE-I Dec 24.PDF2 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold_unsold_dec 24.pdf2 Jul 2025
Form 1File: Qpr Phase I June 22.pdf2 Jul 2025
Form 2File: Qpr Phase I June 22.pdf2 Jul 2025
Form 3File: Qpr Phase I June 22.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: Qpr Phase I June 22.pdf2 Jul 2025
Form 1File: Form 1 Phase I Dec 23.PDF2 Jul 2025
Form 2File: Form 2 Phase I Dec 23.PDF2 Jul 2025
Form 3File: Phase I Form 3 Dec 23.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold_unsold_dec 23.pdf2 Jul 2025
Self-declaration of Quarterly ProgressFile: Qpr Phase 1 mar 24.pdf2 Jul 2025
Form 1File: Form 1 Phase I Dec 23.PDF2 Jul 2025
Form 2File: Form 2 Phase I Dec 23.PDF2 Jul 2025
Form 3File: Phase I Form 3.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold_unsold_dec 23.pdf2 Jul 2025
Self-declaration of Quarterly ProgressFile: Qpr Phase I June 24.pdf2 Jul 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Architect completion certificate_shop Building_2.pdf17 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Architect completion certificate_shop Building_2.pdf17 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3_Phase I_compressed.pdf10 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2_phase I.pdf10 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_Phase 1.PDF10 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Phase II_0001.pdf5 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Phase I_0001.pdf5 Feb 2025

How this compares with Thane

72%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 25 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep RUSTTAGI AARAMBHA PHASE- I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near TITWALA7,600+ in Thane

2 kmRUSTTAGI AARAMBHA PHASE-Completed 26Lapsed / revoked 16Other 20Dot size: filed unitsN

Filed coordinates, straight-line distance. 62 registered projects within 2 km.

Builder: RUSTAGI ESTATES PRIVATE LIMITED

RUSTAGI ESTATES PRIVATE LIMITED has 4 registrations on MahaRERA, including RUSTTAGI AARAMBHA PHASE- I and RUSTTAGI AARAMBHA PHASE-II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that RUSTTAGI AARAMBHA PHASE- I shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if RUSTTAGI AARAMBHA PHASE- I is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RUSTTAGI AARAMBHA PHASE- I?

The registered promoter entity is RUSTAGI ESTATES PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RUSTTAGI AARAMBHA PHASE- I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for RUSTTAGI AARAMBHA PHASE- I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RUSTTAGI AARAMBHA PHASE- I?

The professionals named in the filing: Architect: UB ARCHITECTS; Engineer: AJAY MAHALE & ASSOCIATES; Chartered Accountant: RD Bhatia & Associates; Chartered Accountant: K B BHAT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RUSTTAGI AARAMBHA PHASE- I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RUSTTAGI AARAMBHA PHASE- I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RUSTTAGI AARAMBHA PHASE- I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.