Home / Browse projects / Palghar, Maharashtra / Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail

Registration lapsed No litigation declared Others project

Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail

By KEYSTONE INFRASTRUCTURE PRIVATE LIMITED

RG-MH-54400 · RERA P99000020216 · Last updated on MahaRERA portal: 7 May 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 27 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
8 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 90%
1Complaints at MahaRERAon this registration
Jump to the 47 documents Report an error

Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail is a Others project by KEYSTONE INFRASTRUCTURE PRIVATE LIMITED in Palghar, Maharashtra, registered with MahaRERA as P99000020216 on 29 Mar 2019. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 27 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameRustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail
  • TypeOthers
  • Location
    • Chikhadongari Road
    • Avenue L4
    • Dongare
    • Palghar
    • 401303
  • Pincode401303
  • RERA no.P99000020216
  • ReraGenie IDRG-MH-54400

Builder

  • NameKEYSTONE INFRASTRUCTURE PRIVATE LIMITED
  • Entity typeCompany
  • DirectorVINCENT PATRICK RODRIGUES
  • Other registrations8 more →
  • Completed5 of 9
  • No longer live4 lapsed, de-registered or revoked

Key dates

10 months past promisethis monthRegisteredMar 2019First promiseSep 2023Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on29 Mar 2019
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Sep 2023)
  • Buildings3 building records
  • Documents filed47 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing INA180000
Wing JNA180000
RetailNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 7 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 90%.

Wing I65%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Wing J55%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Retail0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities30

As on 7 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%
walking cum jogging track on podium topYes0%
Staircase and lift lobbiesYes0%
Solar SystemYes0%
skating area on podium topYes0%
podium top landscaping and trees plantingYes0%
futsal court on podium topYes0%
ElevatorsYes0%
Earthquake resistant structureYes0%
DG Back up for Elevators and Common area LightingYes0%
Designer Entrance LobbyYes0%
common area lightingYes0%
common area fire sprinklersYes0%
box cricket on podium topYes0%
Organic Waste converter for recycle of wet garbageYes0%
multipurpose lawn on podium topYes0%

Parking filed103

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots103
Closed/Covered88
Open Space15
BuildingClosed/CoveredOpen SpaceTotal
Wing I44448
Wing J44448
Retail077

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,319 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI10383.18
Proposed, not sanctioned10,383 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch349 Business Point Branch Western Express Highway Andheri E Mumbai 400 069

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectM/s. Abhikalpan Architects & Planners
EngineerM/s. J W Consultant LLP
PartnerRole in project
KEYSTONE INFRASTRUCTURE PRIVATE LIMITED-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000011503Sep 2023 → Sep 2024

Reason as filed by the promoterThe promoter has received full approval of building plans and has completed construction upto plinth level; however, Promoter is awaiting further commencement Certificate to commence construction as more particularly mentioned in application.

EXT99000019068Sep 2023 → Dec 2025

Reason as filed by the promoter1. The Real Estate Project comprises of three Buildings i.e. Wing I, Wing J and Retail Building. The super structure of Wing I and Wing J of the said Real Estate Project is completed and is presently at the stage of completion of block work together with internal finishing works. However, the construction of the Retail Building of said Real Estate Project has still not progressed. 2. There are several instances that have caused hurdles in the said Real Estate Project’s completion and yet Wing I and Wing J of the Real Estate Project have been substantially completed. We state that Covid 19 pand

Litigation declared1

CaseCourtStatus
7413/2017Bombay High CourtThis WP is filed challenging order passed by CCRA Pune for stamp duty demand stay granted

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12604280KEYSTONE INFRASTRUCTURE PRIVATE LIMITEDMr Tarun Rai08/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Nov 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Mar 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Nov 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Nov 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed47

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: 2024 07 20 RG KIPL PROJECTS RERA JUNE 2024- WING IJ.pdf7 May 2025
Certificates of CA (Form 3)File: Retail-5.pdf16 Feb 2024
Certificates of CA (Form 3)File: 2023 08 17 RG KIPL PROJECTS RERA JUNE 2023- WING IJ.pdf14 Feb 2024
Certificates of CA (Form 3)File: 2023 11 18 RG KIPL PROJECTS RERA SEPT 2023 WING IJ.pdf14 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10-MAHARERA Form 1 - Wing I J as on Dec 2023.pdf5 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7-MAHARERA Form 1 - Wing I J as on March 2023.pdf19 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8-MAHARERA Form 1 - Wing I J as on June 2023.pdf19 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9-MAHARERA Form 1 - Wing I J as on September2023.pdf19 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Virar Avenue L1 L2 and L4 Wing IJ.pdf30 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Wing I and J.pdf30 Jul 2023
Certificates of CA (Form 3)File: Form 3 KIPL WING IJ RERA DEC 2022.pdf30 Jul 2023
Certificates of CA (Form 3)File: Form 3 KIPL WING IJ March 2023.pdf30 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 -Virar Avenue L Wing I J - SEPT 2022.pdf2 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_KIPL IJ WING_Sept 2022.pdf2 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 VIRAR L WING I J SEPT 2022.pdf30 Sep 2022
Declaration about Commencement CertificateFile: RERA Declaration Wing I J.pdf9 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Virar Avenue L Wing I J June 2022.pdf9 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 VIRAR AVENUE L Wing IJ - June 2022.pdf9 Sep 2022
CERSAI detailsFile: CERSAI_REPORT- VIRAR.pdf15 Jun 2022
CERSAI detailsFile: CERSAI_REPORT- VIRAR.pdf15 Jun 2022
Details of encumbrancesFile: Encumbrance Certificate TCHFL.pdf8 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5 Virar avenue L wing I J.pdf30 Sep 2021
Form 2AFile: QAC JUNE 21 WING IJ RETAIL.pdf2 Jul 2021
Form 2AFile: QAC MARCH 21 WING IJ RETAIL.pdf2 Jul 2021
Details of encumbrancesFile: Virar Encumbrane Certificate 05042021.pdf7 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Virar Avenue L1 I J.pdf30 Sep 2020
Form 2AFile: RERA I n J.pdf17 Jan 2020
Form 2AFile: I J.pdf7 Oct 2019
Form 2AFile: Virar L Avenue wing I J.pdf27 Jul 2019
Layout approvalFile: MYSCAN_20181112_0001.pdf29 Mar 2019
Layout approvalFile: MYSCAN_20181112_0015.pdf29 Mar 2019
Layout approvalFile: MYSCAN_20181112_0016.pdf29 Mar 2019
Layout approvalFile: MYSCAN_20181112_0017.pdf29 Mar 2019
Layout approvalFile: MYSCAN_20181112_0018.pdf29 Mar 2019
Copy of Layout Approval (in case of layout)File: MYSCAN_20181112_0001.pdf29 Mar 2019
Copy of Layout Approval (in case of layout)File: MYSCAN_20181112_0015.pdf29 Mar 2019
Copy of Layout Approval (in case of layout)File: MYSCAN_20181112_0016.pdf29 Mar 2019
Copy of Layout Approval (in case of layout)File: MYSCAN_20181112_0017.pdf29 Mar 2019
Copy of Layout Approval (in case of layout)File: MYSCAN_20181112_0018.pdf29 Mar 2019
Building plan approvalFile: Permission VVCMC L1L2L4 051118.pdf17 Nov 2018
Copy of the legal title reportFile: Report on title 161118.pdf17 Nov 2018
Details of encumbrancesFile: Encumbrance certificate L1 L2 L4 191018.pdf17 Nov 2018
Building Plan Approval (IOD)File: Permission VVCMC L1L2L4 051118.pdf17 Nov 2018
Commencement Certificates / NA Order for plotted developmentFile: Permission VVCMC L1L2L4 051118.pdf17 Nov 2018
Declaration in FORM BFile: Virar Avenue L4 Wing I J.pdf17 Nov 2018
Certificates of CA (Form 3)File: VIRAR L4 WING IJ RETAIL 5 REVISED CERTIFICATE.pdf17 Nov 2018
Proforma of Allotment letterFile: AVENUE L1 L2 L4 AFS DRAFT DTD 27032019.pdf17 Nov 2018

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 27 months
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Rustomjee Virar Avenue L1-L2 and L4 Wing I J on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Avenue L43,200+ in Palghar

Builder: KEYSTONE INFRASTRUCTURE PRIVATE LIMITED

KEYSTONE INFRASTRUCTURE PRIVATE LIMITED has 9 registrations on MahaRERA, including RUSTOMJEE VIRAR AVENUE D1 WING A AND WING B AND RETAIL BUILDING and RUSTOMJEE VIRAR AVENUE D1 WING C AND WING D. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail?

The registered promoter entity is KEYSTONE INFRASTRUCTURE PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail?

The professionals named in the filing: Architect: M/s. Abhikalpan Architects & Planners; Engineer: M/s. J W Consultant LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Rustomjee Virar Avenue L1-L2 and L4 Wing I J to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.