Home / Browse projects / Mumbai Suburban, Maharashtra / Ruparel Westsky

Registered No litigation declared Residential / Group Housing project

Ruparel Westsky

By RUPAREL SHREEJI CONSTRUCTION PVT LTD

RG-MH-27002 · RERA P51800007630 · Last updated on MahaRERA portal: 23 Jun 2026

Source: official MahaRERA filing

Red flags

  • 50 complaints at MahaRERA
  • Completion date moved by 54 months
  • 3 extensions taken
  • Rs 205.00 crore secured on the land, in favour of SWAMIH
  • The charge is held by SWAMIH, a distressed-debt buyer or stressed-asset fund rather than an originating lender

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 54 months from the original
1 of 11Construction stages donefurthest along: Excavation, 95%
119 of 336Units unsoldnot recorded sold or booked
50Complaints at MahaRERAon this registration
Jump to the 139 documents Report an error

Ruparel Westsky is a Residential / Group Housing project by RUPAREL SHREEJI CONSTRUCTION PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800007630 on 17 Aug 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 54 months from the original filing. 217 of the 336 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete. 50 complaints are on record with the regulator.

At a glance

Project

  • NameRuparel Westsky
  • TypeResidential / Group Housing
  • Location
    • New Link Road
    • Kandivali
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800007630
  • ReraGenie IDRG-MH-27002

Builder

  • NameRUPAREL SHREEJI CONSTRUCTION PVT LTD
  • Entity typePartnership
  • PartnerAmit Ruparel
  • DirectorParikshit Sharma

Key dates

this monthRegisteredAug 2017First promiseJun 2023Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Aug 2017
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Jun 2023)
  • Buildings1 building record
  • Documents filed139 files

Current status

65%217 of 336 units booked
46.0%Work done, per cost certificate

Figures as on 23 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ParkviewNA61543288336

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 95%.

Parkview: 49% average across the applicable activities

ActivityProgress
Excavation95%
Basement (if any)100%
Podiums (if any)0%
Plinth95%
Stilt Floor95%
Slabs of Super Structure51%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises51%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks51%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 23 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed412

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots412
Closed/Covered412

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area3,142 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofSWAMIH
Secured amountRs 205.00 crore
CERSAI search filedYes
Declared on31 Dec 2025
LandownerVillageDistrict
Ruparel Shreeji Construction Private LimitedOthersMumbai City

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI10950.0
Proposed, not sanctioned4,825 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMadame Kama Marg, Fort, Mumbai
Estimated costRs 396.56 cr
Cost incurredRs 182.26 cr
Work done45.96%
BuildingWingEstimatedIncurred
ParkviewNARs 396.56 crRs 182.26 cr

Certifying professionals and partners10

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDaisaria Associates
ArchitectMr Rahul Kamathi
ArchitectRahul Kamathi
EngineerAjay Gade
EngineerParikh & Kulkarni
EngineerMr Sanjeev R Sinha
EngineerSanjeev Sinha
Chartered AccountantCA Shereena V Jacob
Chartered AccountantSherrena Jacob
Chartered AccountantSarveshwar Sharma
PartnerRole in project
RUPAREL SHREEJI CONSTRUCTION PVT LTD-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800010896Jun 2023 → Dec 2025

Reason as filed by the promoterDue to Increase in FSI, Construction area has increase and therefore request you to grant us extension for completion of project.

EXT51800010780Jun 2023 → Jun 2024

Reason as filed by the promoterdue increase in FSI as per DCR 2034, sale construction area has been increased

EA23012619568Jun 2023 → Dec 2027

Reason as filed by the promoter“Ruparel Westsky” is a single residential tower comprising Basement (services) + Ground + 59 floors, being developed under a redevelopment scheme in accordance with Regulation 33(10) of DCPR 2034. The project is registered with MahaRERA, with the latest registration certificate issued on 5th October 2021 and valid up to 31st December 2025. Due to circumstances beyond the control of the promoter, the project has suffered delays, necessitating an application for extension of registration under Section 7(3) of the Real Estate (Regulation and Development) Act, 2016. The primary cause of delay is t

Complaints filed with MahaRERA50

Case no.ComplainantRespondentFiled
CC006000000000565DIVYANG VINOD KANTHARIAKIRTI MEHTA14/09/2017
CC006000000001259Rajkumar ShakyaKirti Mehta19/05/2018
CC006000000303302Sagar sopan naleShreeji Construction21/11/2022
CC006000000194102ASHOK MADHUBHAI DESAISHREEJI CONSTRUCTION28/09/2020
CC006000000198583Mr. Ashok M. DesaiM/s Shreeji Construction07/10/2021
CC006000000171647hardik hasmukhlal shahBuildwell Constructions a/w Shreeji Constructions23/11/2019
CC006000000194061Akshali Devendra VaityShri Kiran Mehta17/09/2020
CC006000000194191VIRAL B MODISHREEJI CONSTRUCTION28/09/2020
CC006000000194192CHINMAY OZASHREEJI CONSTRUCTION28/09/2020
CC006000000194193HEMAL K PATELSHREEJI CONSTRUCTION28/09/2020
CC006000000194194KALPESH SHAHSHREEJI CONSTRUCTION04/10/2020
CC006000000194281MANJIT R GWALANISHREEJI CONSTRUCTION04/10/2020
CC006000000194282SUNITASHREEJI CONSTRUCTION04/10/2020
CC006000000194294APARNA DALVISHREEJI CONSTRUCTION04/10/2020
CC006000000196782PRAYAG B SHAHshreeji construction21/04/2021
CC006000000197550SMITA PRAMOD CHAKNEshreeji construction08/07/2021
CC006000000198196KAVITA V LOHARSHREEJI CONSTRUCTION01/09/2021
CC006000000198197AMIT HARIBHAI VARIYAshreeji construction18/09/2021
CC006000000198585CHINMAY OZAshreeji construction17/10/2021
CC006000000198588KALPESH SHAHshreeji construction17/10/2021
CC006000000198589HEMAL K PATELshreeji construction17/10/2021
CC006000000198590APARNA DALVIshreeji construction17/10/2021
CC006000000198592PRAYAG BHARAT SHAHshreeji construction03/12/2021
CC006000000196574Pravin ShettyBuildwell Construction & ORs31/03/2021
CC006000000198708Minal Sudhakar VaityShreeji Construction17/10/2021
CC006000000209549DINESH YADAVSHREEJI CONSTRUCTION06/01/2022
CC006000000209550HEMANT YADAVM/S SHREE CONSTURCTION06/01/2022
CC006000000209551RAMBRIJ YADAVM/S SHREEJI CONSTURCTION06/01/2022
CC006000000209552SUSHMA YADAVM/S SHREEJI CONSTRUCTION06/01/2022
CC006000000220819Bhavesh ShahShreeji Constructions13/04/2022
CC006000000220825Rajiv Ramcharan AgrawalShreeji Constructions15/04/2022
CC006000000221105kalpesh harshad mehtaShreeji Constructions06/05/2022
CC006000000303175RAGHUNATH SHANKAR PRABHUshreeji construction29/10/2022
CC006000000396528Akshay YadavShreeji Construction24/07/2023
CC006000000396683Shomik RanavatM/s Shreeji Construction25/07/2023
CC006000000396808Sangeeta RanawatM/s Shreeji Construction25/07/2023
CC006000000396809Vasantraj RanawatM/s Shreeji Construction25/07/2023
CC006000000396812Rekha RanawatM/s Shreeji Construction24/07/2023
CC006000000408644Shreeji Constructions Shreeji Constructions Shreeji ConstructionsHemat Patel05/01/2024
CC006000000479999CHINMAY OZASHREEJI CONSTRUCTION22/04/2024
CC006000000480176ASHWIN C DALVISHREEJI CONSTRUCTION22/04/2024
CC006000000591540SHREEJI CONSTRUCTIONJaymanv Singh20/08/2024
CC12500892Rajnish JhaShreeji Construction13/03/2025
CC12600031Bhavesh Sudhir BhideRUPAREL SHREEJI CONSTRUCTION PVT LTD03/01/2026
CC12600211RUPAREL SHREEJI CONSTRUCTION PVT LTDVeena darji12/01/2026
CC12600533RUPAREL SHREEJI CONSTRUCTION PVT LTDMilind Manohar Jadhav31/01/2026
CC12600883RUPAREL SHREEJI CONSTRUCTION PVT LTDMr Milind Manohar Jadhav18/02/2026
CC12603542Gaurav Sunil ShuklaRUPAREL SHREEJI CONSTRUCTION PVT LTD08/06/2026
CC12601260RANBIR DIWANSINGH NAYALRUPAREL SHREEJI CONSTRUCTION PVT LTD08/03/2026
CC12603353Sanket Uday MorwaleRUPAREL SHREEJI CONSTRUCTION PVT LTD01/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Dec 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Dec 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Dec 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed139

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 139 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Ruparel Westsky.pdf23 Jun 2026
Withdrawal Update Form 2File: Form 2 Ruparel Westsky.pdf23 Jun 2026
Withdrawal Update Form 3File: Form 3 Ruparel Westsky.pdf23 Jun 2026
Form 5 (FY 2024-2025)File: Ruparel Westsky Form 5 FY 2024-25.pdf12 Feb 2026
Withdrawal Update Form 1File: Form 1 Ruparel Westsky.pdf23 Jan 2026
Withdrawal Update Form 2File: Form 2 Ruparel Westsky.pdf23 Jan 2026
Withdrawal Update Form 3File: Form 3 Ruparel Westsky.pdf23 Jan 2026
Layout approvalFile: Layout Approval dt 260924.pdf31 Dec 2025
Building plan approvalFile: IOA 2 dt 260924.pdf31 Dec 2025
Building plan approvalFile: IOA 3 dt 260924.pdf31 Dec 2025
Building plan approvalFile: IOA 4 dt 260924.pdf31 Dec 2025
Building plan approvalFile: IOA 5 dt 260924.pdf31 Dec 2025
Building plan approvalFile: IOA 6 dt 260924.pdf31 Dec 2025
Building plan approvalFile: IOA 7 dt 260924.pdf31 Dec 2025
Building plan approvalFile: IOA 8 dt 260924.pdf31 Dec 2025
Building plan approvalFile: IOA 9 dt 260924.pdf31 Dec 2025
Building plan approvalFile: IOA 10 dt 260924.pdf31 Dec 2025
Building plan approvalFile: IOA 11 dt 260924.pdf31 Dec 2025
Commencement certificateFile: CC Ruparel Westsky 280325.pdf31 Dec 2025
Layout approvalFile: Layout Approval dt 260924.pdf31 Dec 2025
Building plan approvalFile: IOA 2 dt 260924.pdf31 Dec 2025
Building plan approvalFile: IOA 3 dt 260924.pdf31 Dec 2025
Building plan approvalFile: IOA 4 dt 260924.pdf31 Dec 2025
Building plan approvalFile: IOA 5 dt 260924.pdf31 Dec 2025
Building plan approvalFile: IOA 6 dt 260924.pdf31 Dec 2025
Building plan approvalFile: IOA 7 dt 260924.pdf31 Dec 2025
Building plan approvalFile: IOA 8 dt 260924.pdf31 Dec 2025
Building plan approvalFile: IOA 9 dt 260924.pdf31 Dec 2025
Building plan approvalFile: IOA 10 dt 260924.pdf31 Dec 2025
Building plan approvalFile: IOA 11 dt 260924.pdf31 Dec 2025
Commencement certificateFile: CC Ruparel Westsky 280325.pdf31 Dec 2025
Withdrawal Update Form 1File: Form 1 Ruparel Westsky 30092025 Final.pdf31 Dec 2025
Withdrawal Update Form 1File: Form 1 Ruparel Westsky 30092025 Final.pdf31 Dec 2025
Withdrawal Update Form 2File: Form 2 Ruparel Westsky 30092025.pdf31 Dec 2025
Withdrawal Update Form 2File: Form 2 Ruparel Westsky 30092025.pdf31 Dec 2025
Withdrawal Update Form 3File: Form 3 Ruparel Westsky 30092025.pdf31 Dec 2025
Withdrawal Update Form 3File: Form 3 Ruparel Westsky 30092025.pdf31 Dec 2025
Form 1File: Form 1.pdf25 Nov 2025
Form 2File: Form 2.pdf25 Nov 2025
Form 3File: Form 3.pdf25 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold Inventory.pdf25 Nov 2025
Form 1File: Form 1 Ruparel Westsky.pdf25 Nov 2025
Form 2File: Ruparel Westky Form 2 31122024.pdf25 Nov 2025
Form 3File: Ruparel Westsky Form 3 Dec24.pdf25 Nov 2025
Disclosure of Sold and Booked InventoryFile: Ruparel Westsky Sold Unsold Inventory 31122024.pdf25 Nov 2025
Form 2A (FY 2018-2019)File: Ruparel Westsky Form 2A.pdf25 Nov 2025
Form 2A (FY 2019-2020)File: Ruparel Westsky Form 2A.pdf25 Nov 2025
Form 2A (FY 2020-2021)File: Ruparel Westsky Form 2A.pdf25 Nov 2025
Form 2A (FY 2021-2022)File: Ruparel Westsky Form 2A.pdf25 Nov 2025
Form 2A (FY 2022-2023)File: Ruparel Westsky Form 2A.pdf25 Nov 2025
Form 2A (FY 2023-2024)File: Ruparel Westsky Form 2A.pdf25 Nov 2025
Form 2A (FY 2024-2025)File: Ruparel Westsky Form 2A.pdf25 Nov 2025
Form 2A (FY 2017-2018)File: Ruparel Westsky Form 2A.pdf25 Nov 2025
Form 2A (FY 2025-2026)File: Ruparel Westsky Form 2A FY25-26.pdf25 Nov 2025
Form 5 (FY 2018-2019)File: Form 5 FY 18-19.pdf25 Nov 2025
Form 5 (FY 2019-2020)File: form 5 FY 19-20.pdf25 Nov 2025
Form 5 (FY 2020-2021)File: form 5 FY 20-21.pdf25 Nov 2025
Form 5 (FY 2023-2024)File: Form 5 FY 23-24.pdf25 Nov 2025
Certificates of CA (Form 3)File: Ruparel Westsky Form 3 Dec24.pdf28 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ruparel Westky Form 2 31122024.pdf28 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Ruparel Westsky.pdf21 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Ruparel Westsky.pdf21 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 7 Ruparel Westsky Form 2A Final.pdf15 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 7 Ruparel Westsky Form 2A Final.pdf15 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 5 Disclosure of sold_ booked inventory (1).pdf1 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 5 Disclosure of sold_ booked inventory (1).pdf1 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 5 Disclosure of sold_ booked inventory (1).pdf1 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 5 Disclosure of sold_ booked inventory (1).pdf1 Feb 2025
Certificates of CA (Form 3)File: Form 3 Ruparel Westsky 22012025.pdf22 Jan 2025
Certificates of CA (Form 3)File: Form 3 Ruparel Westsky 22012025.pdf22 Jan 2025
Certificates of CA (Form 3)File: Form 3 Ruparel Westsky 22012025.pdf22 Jan 2025
Certificates of CA (Form 3)File: Form 3 Ruparel Westsky 22012025.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: Ruparel Westsky Sold Unsold Inventory 30092024.pdf26 Dec 2024
Disclosure of sold/ booked inventoryFile: Ruparel Westsky Sold Unsold Inventory 30092024.pdf26 Dec 2024
Disclosure of sold/ booked inventoryFile: Ruparel Westsky Sold Unsold Inventory 30092024.pdf26 Dec 2024
Disclosure of sold/ booked inventoryFile: Ruparel Westsky Sold Unsold Inventory 30092024.pdf26 Dec 2024
Disclosure of sold/ booked inventoryFile: 3 Disclosure of sold_ booked inventory.pdf11 Dec 2024
Disclosure of sold/ booked inventoryFile: 3 Disclosure of sold_ booked inventory.pdf11 Dec 2024
Disclosure of sold/ booked inventoryFile: 3 Disclosure of sold_ booked inventory.pdf11 Dec 2024
Disclosure of sold/ booked inventoryFile: 3 Disclosure of sold_ booked inventory.pdf11 Dec 2024

How this compares with Mumbai Suburban

65%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 54 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Ruparel Westsky on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kandivali6,700+ in Mumbai Suburban

2 kmRuparel WestskyCompleted 112Lapsed / revoked 68Other 151Dot size: filed unitsN

Filed coordinates, straight-line distance. 331 registered projects within 2 km.

Builder: RUPAREL SHREEJI CONSTRUCTION PVT LTD

RUPAREL SHREEJI CONSTRUCTION PVT LTD has 1 registration on MahaRERA, including Ruparel Westsky. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Ruparel Westsky is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Ruparel Westsky?

The registered promoter entity is RUPAREL SHREEJI CONSTRUCTION PVT LTD, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Ruparel Westsky?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Ruparel Westsky?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Ruparel Westsky?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Ruparel Westsky?

The professionals named in the filing: Architect: Daisaria Associates; Architect: Mr Rahul Kamathi; Architect: Rahul Kamathi; Engineer: Ajay Gade; Engineer: Parikh & Kulkarni; Engineer: Mr Sanjeev R Sinha. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ruparel Westsky?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ruparel Westsky. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ruparel Westsky to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.