ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Ruparel Palacio Ph I

Registration lapsed No litigation declared Residential / Group Housing project

Ruparel Palacio Ph I

By Shree Siddhivinayak Infrastructure & Realty

RG-MH-72996 · RERA P51800013681 · Last updated on MahaRERA portal: 21 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 3 complaints at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
3 of 11Construction stages donefurthest along: Podiums (if any), 0%
23 of 90Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 46 documents Report an error

Ruparel Palacio Ph I is a Residential / Group Housing project by Shree Siddhivinayak Infrastructure & Realty in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800013681 on 23 Oct 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 24 months from the original filing. 67 of the 90 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameRuparel Palacio Ph I
  • TypeResidential / Group Housing
  • Location
    • Old Link Road
    • Kandivali
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800013681
  • ReraGenie IDRG-MH-72996

Builder

  • NameShree Siddhivinayak Infrastructure & Realty
  • Entity typePartnership
  • GSTIN27ABVFS5422N1ZC
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersAmit Ruparel, Shree Siddhivinayak Real Homes Pvt Ltd
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live1 lapsed, de-registered or revoked

Key dates

10 months past promisethis monthRegisteredOct 2017First promiseDec 2023Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on23 Oct 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed46 files

Current status

74%67 of 90 units booked

Figures as on 21 Feb 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Ruparel PalacioNA434384690

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Ruparel Palacio: 27% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities19

As on 21 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable
Swimming PoolYes0%
Senior Citizen ParkYes0%
Kids Play AreaYes0%
GymnasiumYes0%

Parking filed50

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots50
Open Space50

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,065 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI4177.8
Proposed, not sanctioned4,178 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHiranandani Meadows

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRahul Kamathi
EngineerAjay Gade
Chartered AccountantShereena Jacob
PartnerRole in project
Shree Siddhivinayak Infrastructure & Realty-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800018866Dec 2023 → Dec 2025

Reason as filed by the promoterSubject: Application for Extension of Project "Ruparel Palacio" - RERA Regn. No.: P51800013681 Respected Authority Members, We, M/s. Shree Siddhivinayak Infra & Realty, promoters of the project Ruparel Palacio (RERA Regn. No. P51800013681), request an extension of the project completion date to 31st December 2025 due to unavoidable delays. Project Overview: Ruparel Palacio is a high-rise residential project with a ground floor and 43 upper floors. The project has received a No Objection Certificate from the Airports Authority of India (issued on 31st January 2018, valid until 30th January 2026

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC12502547Rizwana KhojaShree Siddhivinayak Infrastructure & Realty23/07/2025
CC12502548Rizwana KhojaShree Siddhivinayak Infrastructure & Realty23/07/2025
CC12504175Mukesh Suresh AgarwalShree Siddhivinayak Infrastructure & Realty25/11/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Oct 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Aug 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Apr 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed46

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Form B Affidavit Cum Declaration.pdf21 Feb 2025
Certificates of CA (Form 3)File: Form 3 Ruparel Palacio Dec 24 Final compressed.pdf21 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Ruparel Palacio.pdf21 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory 31122024.pdf21 Feb 2025
CERSAI detailsFile: CERSAI Search Report.pdf21 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A Dec 2024.pdf21 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest Shree Siddhivinayak Infra and Realty.pdf21 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Ruparel Palacio FY 2024.pdf21 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate Ruparel Palacio.pdf20 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A Bank Declaration Ruparel Palacio.pdf20 Feb 2025
Building plan approvalFile: IOA Amemded 250823.pdf22 Apr 2024
Building Plan Approval (IOD)File: IOA Amemded 250823.pdf22 Apr 2024
Declaration about Commencement CertificateFile: Declaration about CC.pdf22 Apr 2024
Declaration in FORM BFile: 1Declaration in Form B.pdf22 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect’s Certificate of Percentage of Completion of Work.pdf22 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer’s Certificate on Cost Incurred on Project.pdf22 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Palacio.pdf22 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Palacio Form 5 FY 22 23.pdf22 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Palacio March- 2020.pdf1 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Palacio March-2021.pdf1 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Palacio March-2022.pdf1 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Palacio 2019-20.pdf24 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Palacio 2020-21.pdf24 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Palacio 2021-22.pdf24 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: CC-Palacio.pdf22 Dec 2021
Building plan approvalFile: Palacio-IOA.pdf16 Jul 2021
Building Plan Approval (IOD)File: Palacio-IOA.pdf16 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: Palacio-CC.pdf16 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Palacio.pdf2 Jan 2020
Layout approvalFile: Palacio - IOA - Layout Aug 2019.pdf31 Aug 2019
Building plan approvalFile: Palacio - IOA - Covering Letter.pdf31 Aug 2019
Copy of Layout Approval (in case of layout)File: Palacio - IOA - Layout Aug 2019.pdf31 Aug 2019
Building Plan Approval (IOD)File: Palacio - IOA - Covering Letter.pdf31 Aug 2019
Commencement Certificates / NA Order for plotted developmentFile: Palacio Bldg CC.pdf31 Aug 2019
Certificates of CA (Form 5)File: Palacio.pdf3 Jan 2019
Commencement Certificates / NA Order for plotted developmentFile: Palacio - CC.pdf27 Apr 2018
Certificates of CA (Form 3)File: CA CERTIFICATE PALACIO.pdf17 Oct 2017
Copy of the legal title reportFile: Title Certificate.pdf9 Oct 2017
Proforma of Allotment letterFile: Draft Allotment - Palacio.pdf9 Oct 2017
Building plan approvalFile: IOA Sale Palacio.pdf7 Oct 2017
Layout approvalFile: Palacio layout Plan.pdf7 Oct 2017
PAN CardFile: SSIR PAN.pdf7 Oct 2017
Details of encumbrancesFile: Encumberance Certificate.pdf7 Oct 2017
Copy of Layout Approval (in case of layout)File: Palacio layout Plan.pdf7 Oct 2017
Building Plan Approval (IOD)File: IOA Sale Palacio.pdf7 Oct 2017
Declaration in FORM BFile: Form B Prasad.pdf7 Oct 2017

How this compares with Mumbai Suburban

74%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Ruparel Palacio Ph I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kandivali6,700+ in Mumbai Suburban

2 kmRuparel Palacio Ph ICompleted 115Lapsed / revoked 70Other 155Dot size: filed unitsN

Filed coordinates, straight-line distance. 340 registered projects within 2 km.

Builder: Shree Siddhivinayak Infrastructure & Realty

Shree Siddhivinayak Infrastructure & Realty has 3 registrations on MahaRERA, including Ruparel Elara and Ruparel Skygreens I. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Ruparel Palacio Ph I shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Ruparel Palacio Ph I is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Ruparel Palacio Ph I?

The registered promoter entity is Shree Siddhivinayak Infrastructure & Realty, a partnership as per the filing. Its GSTIN 27ABVFS5422N1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Ruparel Palacio Ph I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Ruparel Palacio Ph I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Ruparel Palacio Ph I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Ruparel Palacio Ph I?

The professionals named in the filing: Architect: Rahul Kamathi; Engineer: Ajay Gade; Chartered Accountant: Shereena Jacob. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ruparel Palacio Ph I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ruparel Palacio Ph I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ruparel Palacio Ph I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.