Home / Browse projects / Raigarh, Maharashtra / RUDRA MAHADEV

Completed No litigation declared Others project

RUDRA MAHADEV

By RUDRA DEVELOPERS

RG-MH-18179 · RERA P52000066458 · Last updated on MahaRERA portal: 11 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 13 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedregistration recorded completed
7 of 11Construction stages donefurthest along: Installation of Lifts, 86%
28 of 44Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 71 documents Report an error

RUDRA MAHADEV is a Others project by RUDRA DEVELOPERS in Raigarh, Maharashtra, registered with MahaRERA as P52000066458 on 5 Jun 2024. The registration is recorded completed; possession was promised by 31 Dec 2027. 16 of the 44 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameRUDRA MAHADEV
  • TypeOthers
  • Location
    • Plot No 86 Sector 25A
    • Pushpak Node
    • Ulawe
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000066458
  • ReraGenie IDRG-MH-18179

Builder

  • NameRUDRA DEVELOPERS
  • Entity typePartnership
  • PartnersNARENDRA BHIMJI ISASARIYA, KHODA PANCHA VAVIA, AMOL MARUTI RAJGE
  • Other registrations13 more →
  • Completed7 of 14
  • No longer live2 lapsed, de-registered or revoked

Key dates

this monthRegisteredJun 2024PromisedDec 2027Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on5 Jun 2024
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed71 files

Current status

36%16 of 44 units booked
76.6%Work done, per cost certificate

Figures as on 11 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RUDRA MAHADEVNA8840444

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 86%.

RUDRA MAHADEV: 79% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.86%

Progress on shared amenities15

As on 11 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed7

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots7
Closed/Covered7

Land and ownership5

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area550 sq m
Land owned byThe promoter, with other names on the file
Named landowners5
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on15 Jun 2025
LandownerVillageDistrict
SHANTIBAI KAMLAKAR KOLIUlaweRaigarh
PANDHARINATH MAHADEV KOLIUlaweRaigarh
RAMKRUSHNA MAHADEV KOLIUlaweRaigarh
VANDANA GANESH KOLIUlaweRaigarh
VINAYAK KAMLAKAR KOLIUlaweRaigarh

Approvals and building plan

Sanctioning authorityCITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED
Permissible FSI1840.41
Proposed, not sanctioned1,840 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 1 To 3 Shagun Essentia Plot No 05 Sector 19 Ulwe Navi Mumbai
Estimated costRs 5.10 cr
Cost incurredRs 3.90 cr
Work done76.56%
BuildingWingEstimatedIncurred
RUDRA MAHADEVNARs 4.69 crRs 3.90 cr
-NARs 40.76 lakh-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectATUL PATEL ARCHITECTS
EngineerB S SUKHTHANKAR & ASSOCIATES
EngineerS R CONSULTANTS
Chartered AccountantKANKOTIYA & CO
Chartered AccountantKAUSHALYA PATEL & CO
PartnerRole in project
RUDRA DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 May 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Jun 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Apr 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed71

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 31120225.pdf11 May 2026
Withdrawal Update Form 1File: Form 1 30092025.pdf11 May 2026
Withdrawal Update Form 1File: Form 1 31120225.pdf11 May 2026
Withdrawal Update Form 1File: Form 1 31032026.pdf11 May 2026
Withdrawal Update Form 2File: Form 2 30092025.pdf11 May 2026
Withdrawal Update Form 2File: Form 2 30092025.pdf11 May 2026
Withdrawal Update Form 2File: Form 2 31120225.pdf11 May 2026
Withdrawal Update Form 2File: Form 2 31032026.pdf11 May 2026
Withdrawal Update Form 3File: Form 3 30092025.pdf11 May 2026
Withdrawal Update Form 3File: Form 3 30092025.pdf11 May 2026
Withdrawal Update Form 3File: Form 3 31122025.pdf11 May 2026
Withdrawal Update Form 3File: Form 3 31032026.pdf11 May 2026
Occupational CertificateFile: OC.pdf11 May 2026
Occupational CertificateFile: OC DRG.pdf11 May 2026
Occupational CertificateFile: Form 4.pdf11 May 2026
Withdrawal Update Form 1File: Form 1 31120225.pdf11 Jan 2026
Withdrawal Update Form 2File: Form 2 31120225.pdf11 Jan 2026
Withdrawal Update Form 3File: Form 3 31122025.pdf11 Jan 2026
Form 1File: Form 1 31032025.pdf20 Sep 2025
Form 2File: Form 2 31032025.pdf20 Sep 2025
Form 3File: Form 3 31032025.pdf20 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold 30092024.pdf20 Sep 2025
Withdrawal Update Form 1File: Form 1 30062025.pdf20 Sep 2025
Withdrawal Update Form 2File: Form 2 30062025.pdf20 Sep 2025
Withdrawal Update Form 3File: Form 3 30062025.pdf20 Sep 2025
Form 1File: Form 1 30092024.pdf8 Jul 2025
Form 2File: Form 2 30092024.pdf8 Jul 2025
Form 3File: Rudra Developers Form 3 30092024.pdf8 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold 30092024.pdf8 Jul 2025
Form 5 (FY 2024-2025)File: Rudra Developers.pdf18 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31032025.pdf30 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31032025.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 31032025.pdf30 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30092024.pdf9 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Rudra Developers Form 3 30092024.pdf9 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30092024.pdf9 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold 30092024.pdf9 Dec 2024
Layout approvalFile: DRG_rotated.pdf6 Jun 2024
Copy of Layout Approval (in case of layout)File: DRG_rotated.pdf6 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: Revised CC1.pdf6 Jun 2024
Declaration about Commencement CertificateFile: DECLARATION ABOUT CC New CC.pdf6 Jun 2024
Copy of the legal title reportFile: Title Report 27052024.pdf27 May 2024
Proforma of Agreement for saleFile: AGREEMENT FOR SALE - 27052024.pdf27 May 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report -Agreement - 27052024.pdf27 May 2024
Other - TechnicalFile: LEASE - rerudbra_11zon.pdf27 May 2024
Other - TechnicalFile: DEVELOPMENT AGREEMENT - rudra developers_11zon.pdf27 May 2024
Declaration about Commencement CertificateFile: Format D New.pdf23 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FINAL FORM 3 RUDRA MAHADEV.pdf20 May 2024
Details of encumbrances concerned to FinanceFile: DETAILS OF ENCUMBRANCES - FINANCIAL.pdf18 May 2024
Details of encumbrances concerned to FinanceFile: DETAILS OF ENCUMBRANCES - LEGAL.pdf18 May 2024
Details of encumbrances concerned to LegalFile: DETAILS OF ENCUMBRANCES - FINANCIAL.pdf18 May 2024
Details of encumbrances concerned to LegalFile: DETAILS OF ENCUMBRANCES - LEGAL.pdf18 May 2024
Declaration in FORM BFile: RERA FORM B-Developers.pdf18 May 2024
CERSAI detailsFile: CRESAI.pdf18 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Partner Organization Details Ann A_Narendra.pdf18 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Partner Organization Details Ann A_Khoda.pdf18 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Partner Organization Details Ann A_Amol.pdf18 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Declaration.pdf18 May 2024
Deviation Report with respect to Allotment letterFile: Deviation Report - Allotment.pdf18 May 2024
Other - TechnicalFile: ANNEXURE A - One Plot One Registation.pdf18 May 2024
Other - LegalFile: Final Order.pdf17 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf15 May 2024
Proforma of Allotment letterFile: Allottment Letter.pdf15 May 2024
CERSAI detailsFile: CERSAI_Report.pdf11 May 2024
Other - TechnicalFile: CC Mail to RERA.pdf11 May 2024
Layout approvalFile: 86-25A Layout_rotated.pdf18 Apr 2024
Building plan approvalFile: 86-25A CC.pdf18 Apr 2024
PAN CardFile: PAN.pdf18 Apr 2024
Copy of Layout Approval (in case of layout)File: 86-25A Layout_rotated.pdf18 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 86-25A CC.pdf18 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: 86-25A CC.pdf18 Apr 2024

How this compares with Raigarh

36%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep RUDRA MAHADEV on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pushpak Node5,900+ in Raigarh

2 kmRUDRA MAHADEVCompleted 79Lapsed / revoked 28Other 104Dot size: filed unitsN

Filed coordinates, straight-line distance. 211 registered projects within 2 km.

Builder: RUDRA DEVELOPERS

RUDRA DEVELOPERS has 14 registrations on MahaRERA, including RUDRA RESIDENCY and RUDRA ENCLAVE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if RUDRA MAHADEV is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RUDRA MAHADEV?

The registered promoter entity is RUDRA DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RUDRA MAHADEV?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for RUDRA MAHADEV?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RUDRA MAHADEV?

The professionals named in the filing: Architect: ATUL PATEL ARCHITECTS; Engineer: B S SUKHTHANKAR & ASSOCIATES; Engineer: S R CONSULTANTS; Chartered Accountant: KANKOTIYA & CO; Chartered Accountant: KAUSHALYA PATEL & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RUDRA MAHADEV?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RUDRA MAHADEV. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RUDRA MAHADEV to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.