ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / RSG TOWN

Registered No litigation declared Plotted project

RSG TOWN

By R SANDESH INFRASTRUCTURES PRIVATE LIMITED

RG-MH-35279 · RERA P50500049658 · Last updated on MahaRERA portal: 18 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 36 months from the original
68 of 142Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 94 documents Report an error

RSG TOWN is a Plotted project by R SANDESH INFRASTRUCTURES PRIVATE LIMITED in Nagpur, Maharashtra, registered with MahaRERA as P50500049658 on 22 Feb 2023. Possession is promised by 30 Jun 2027. The completion date has moved by 36 months from the original filing. 74 of the 142 units on this registration are recorded sold or booked.

At a glance

Project

  • NameRSG TOWN
  • TypePlotted
  • Location
    • BORKHEDI
    • Nagpur (Rural)
    • Nagpur
    • 441108
  • Pincode441108
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500049658
  • ReraGenie IDRG-MH-35279

Builder

  • NameR SANDESH INFRASTRUCTURES PRIVATE LIMITED
  • Entity typeCompany
  • DirectorsRAMDEO PRAHLADRAI AGRAWAL, DILIP PRAHLADRAI AGRAWAL
  • Other registrations6 more →
  • Completed3 of 7
  • Declared earlier projects4 →

Key dates

this monthRegisteredFeb 2023First promiseJun 2024Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Feb 2023
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2024)
  • BuildingsNot stated in filing
  • Documents filed94 files

Current status

52%74 of 142 units booked

Figures as on 18 Jul 2026, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 18 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes98%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes96%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes99%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area24,601 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityMunicipal Council Butibori, Nagpur

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRAJMAHAL' 267, CENTRAL AVENUE ROAD,NAGPUR (E)

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectLOKESH KADU
EngineerLOKESH KADU
EngineerSANJAY BIRLA
Chartered AccountantCA ANKIT TALREJA
Chartered AccountantSUMIT SANTOSH AGRAWAL & ASSOCIATES
Chartered AccountantUTSAV SUMIT AND ASSOCIATES
PartnerRole in project
R SANDESH INFRASTRUCTURES PRIVATE LIMITED-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50500024362Jun 2024 → Jun 2025

Reason as filed by the promoterDECLARATION AND UNDERTAKING Registration Number: P50500049658 Project Name: “RSG TOWN” Address: Situated at Kh/ Survey No.137, P.S.K 74, admeasuring 24,593.207 Sq Mtrs, Village: Borkhedi, Tahsil & District Nagpur-441108. The undersigned Authorized Signatory/Partners hereby declare and undertake as follows: 1. The project “RSG TOWN,” admeasuring 24,593.207 Sq Mtrs, situated at Kh/ Survey No.137, P.S.K 74, Village: Borkhedi, Tahsil & District Nagpur-441108, was registered with the RERA Department in February 2023 for 141 plots admeasuring 24,593.207 Sq Mtrs. The promoter has already completed mo

EA31072502278Jun 2024 → Jun 2027

Reason as filed by the promoterDate: 15/07/2025 To The Maharashtra Real Estate Regulatory Authority (MahaRERA) Mumbai, Maharashtra Subject: Declaration for Extension of Completion Date for the Project RSG TOWN RERA Registration Number: P50500049658 Respected Sir/Madam, We, R Sandesh Infrastructure Private Limited, the Promoter of the real estate project known as RSG TOWN, bearing MahaRERA Registration Number P50500049658, situated at Survey No. 137, Borkhedi, Nagpur (Rural), Nagpur - 441108, do hereby solemnly declare as under: 1. That the registration of the said project was granted under Section 5 of the Real Estate (Regu

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Feb 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Jan 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Feb 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed94

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM-1 SEPT-25 RSG TOWN SCANNED.pdf18 Jul 2026
Withdrawal Update Form 2File: FORM-2 SEPT-25 .pdf18 Jul 2026
Withdrawal Update Form 3File: FORM-3 SEPT-25 SCANNED_compressed.pdf18 Jul 2026
Withdrawal Update Form 1File: FORM-1 SEPT-25 RSG TOWN SCANNED.pdf19 Apr 2026
Withdrawal Update Form 2File: FORM-2 SEPT-25 .pdf19 Apr 2026
Withdrawal Update Form 3File: FORM-3 SEPT-25 SCANNED_compressed.pdf19 Apr 2026
Withdrawal Update Form 1File: FORM-1 SEPT-25 RSG TOWN SCANNED.pdf20 Jan 2026
Withdrawal Update Form 2File: FORM-2 SEPT-25 .pdf20 Jan 2026
Withdrawal Update Form 3File: FORM-3 SEPT-25 SCANNED_compressed.pdf20 Jan 2026
Layout approvalFile: LAYOUT PLAN.pdf6 Jan 2026
Layout approvalFile: LAYOUT PLAN.pdf19 Dec 2025
Layout approvalFile: NEW SACTIONED PLAN.pdf1 Dec 2025
Form 2A (FY 2022-2023)File: FORM-2A MAR-23 RSG TOWN.pdf26 Nov 2025
Form 2A (FY 2023-2024)File: FORM-2A_MAR-24.pdf26 Nov 2025
Form 5 (FY 2022-2023)File: Form 5 MAR-23.pdf26 Nov 2025
Form 5 (FY 2023-2024)File: Form 5 MAR-24.pdf26 Nov 2025
Withdrawal Update Form 1File: FORM-1 SEPT-25 RSG TOWN SCANNED.pdf25 Nov 2025
Withdrawal Update Form 2File: FORM-2 SEPT-25 .pdf25 Nov 2025
Withdrawal Update Form 3File: FORM-3 SEPT-25 SCANNED_compressed.pdf25 Nov 2025
Form 2A (FY 2024-2025)File: FORM-2A MAR-25 RSG TOWN.pdf25 Nov 2025
Form 1File: FORM-1_MAR-25.pdf24 Nov 2025
Form 2File: FORM-2_Mar-25.pdf24 Nov 2025
Form 3File: FORM-3_Mar-25_compressed.pdf24 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD_MAR-25.pdf24 Nov 2025
Withdrawal Update Form 1File: FORM-1.pdf24 Nov 2025
Withdrawal Update Form 2File: FORM-2.pdf24 Nov 2025
Withdrawal Update Form 3File: FORM-3 RSG-TOWN GENERATED SCANNED_compressed.pdf24 Nov 2025
Form 5 (FY 2024-2025)File: FORM-5 MAR-25 RSG TOWN SCANNED.pdf31 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: rsg f1.pdf22 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: rsg f3.pdf22 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: rsg f2.pdf22 Apr 2025
Disclosure of sold/ booked inventoryFile: rsg sns.pdf22 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3.pdf5 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2.pdf5 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 RSG TOWN 03-01-2025.pdf10 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_SEP-24.pdf13 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2.pdf13 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 RSG Town_Mar-24.pdf25 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_Sep-24.pdf6 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 RSG TOWN 05-10-2024.pdf20 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RSG TOWN_Form-1- Architect Certificate_June-24_U.pdf23 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_June-24U.pdf23 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_RSG TOWN_JUNE-24.pdf23 Jul 2024
Declaration in FORM BFile: FORM-B.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_June-24.pdf22 Jul 2024
Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD_MAR-24.pdf22 Jul 2024
Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD_June-24.pdf22 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_RSG TOWN_JUNE-24_compressed.pdf22 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 RSG TOWN 02-07-2024.pdf18 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_Mar-24_.pdf17 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM-2A_MAR-24.pdf17 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_Mar-23.pdf15 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_June-23.pdf15 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_Sep-23.pdf15 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_Dec-23.pdf15 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_RSG TOWN_Mar-24.pdf15 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RSG Town Form 1.pdf12 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_RSG TOWN_Dec-23.pdf31 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RSG TOWN_Form-1- Architect Certificate_Dec-23.pdf19 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 RSG.pdf12 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1_RSG TOWN.pdf12 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: RSG Town_Form 2A_March-23.pdf19 Oct 2023
Disclosure of sold/ booked inventoryFile: SOLD_UNSOLD_INVENTORY_RSG TOWN_mar-23.pdf19 Oct 2023
Disclosure of sold/ booked inventoryFile: SOLD_UNSOLD_INVENTORY_RSG TOWN_june-23.pdf19 Oct 2023
Disclosure of sold/ booked inventoryFile: SOLD_UNSOLD_INVENTORY_RSG TOWN_Sep-23.pdf19 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RSG Town Form 3_ Sep 2023.pdf19 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RSG TOWN_FORM-5.pdf10 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SEPT 2023 RSG TOWN.pdf2 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3RGS TOWN JUNE-2023_compressed.pdf27 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_March-23_compressed.pdf26 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RSG TOWN RERA (1).pdf20 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: JUNE 2023 RSG TOWN.pdf20 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: dilip Rev.pdf16 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: INTERES DEC_RAMDEO AGRAWAL.pdf16 Feb 2023
Layout approvalFile: LAYOUT PLAN.pdf11 Feb 2023
Building plan approval or NA orderFile: LAYOUT PLAN.pdf11 Feb 2023
PAN CardFile: PAN.pdf11 Feb 2023
Copy of the legal title reportFile: LEGAL TITLE.pdf11 Feb 2023
Details of encumbrances concerned to FinanceFile: ENCUM_Finance.pdf11 Feb 2023
Details of encumbrances concerned to FinanceFile: ENCUM_LEGAL.pdf11 Feb 2023

How this compares with Nagpur

52%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one moved by 36 months
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep RSG TOWN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BORKHEDI2,800+ in Nagpur

2 kmRSG TOWNCompleted 35Lapsed / revoked 19Other 50Dot size: filed unitsN

Filed coordinates, straight-line distance. 104 registered projects within 2 km.

Builder: R SANDESH INFRASTRUCTURES PRIVATE LIMITED

R SANDESH INFRASTRUCTURES PRIVATE LIMITED has 7 registrations on MahaRERA, including OFFICERS ENCLAVE and RSG - WEST END. Its filings disclose 4 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if RSG TOWN is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RSG TOWN?

The registered promoter entity is R SANDESH INFRASTRUCTURES PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RSG TOWN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for RSG TOWN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RSG TOWN?

The professionals named in the filing: Architect: LOKESH KADU; Engineer: LOKESH KADU; Engineer: SANJAY BIRLA; Chartered Accountant: CA ANKIT TALREJA; Chartered Accountant: SUMIT SANTOSH AGRAWAL & ASSOCIATES; Chartered Accountant: UTSAV SUMIT AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RSG TOWN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RSG TOWN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RSG TOWN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one