Home / Browse projects / Raigarh, Maharashtra / ROYAL RESIDENCY

Registered No litigation declared Residential / Group Housing project

ROYAL RESIDENCY

By Royal Enterprises

RG-MH-85790 · RERA P52000011059 · Last updated on MahaRERA portal: 29 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 36 months from the original
9 of 22Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 95%
98 of 133Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 149 documents Report an error

ROYAL RESIDENCY is a Residential / Group Housing project by Royal Enterprises in Raigarh, Maharashtra, registered with MahaRERA as P52000011059 on 31 Aug 2017. Possession is promised by 31 Mar 2027. The completion date has moved by 36 months from the original filing. 35 of the 133 units on this registration are recorded sold or booked, and 9 of 22 construction stages are filed complete.

At a glance

Project

  • NameROYAL RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • KHOPOLI
    • TAKAI
    • Khalapur
    • Raigarh
    • 410203
  • Pincode410203
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000011059
  • ReraGenie IDRG-MH-85790

Builder

  • NameRoyal Enterprises
  • Entity typePartnership
  • PartnerKAJAL BHAVANDAS JESWANI
  • Other registrations5 more →
  • Completed2 of 6
  • No longer live1 lapsed, de-registered or revoked
  • Past their filed date1

Key dates

this monthRegisteredAug 2017First promiseMar 2024Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Aug 2017
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 30 Mar 2024)
  • Buildings2 building records
  • Documents filed149 files

Current status

26%35 of 133 units booked
65.3%Work done, per cost certificate

Figures as on 29 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING 1 - A to ENA5497097
BUILDING 2NA6536036

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 29 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 95%.

BUILDING 1 - A to E90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
BUILDING 20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes20%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes40%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,840 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
NARAYAN BAPU PATILKhopoliRaigarh

Approvals and building plan

Sanctioning authorityKhopoli Muncipal Corporation
Permissible FSI5251.71
Proposed, not sanctioned5,252 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch228/4 AND 228/6, KARNALA ROYAL, PANVEL 410206
Estimated costRs 12.26 cr
Cost incurredRs 8.01 cr
Work done65.35%
BuildingWingEstimatedIncurred
BUILDING 1 - A to ENARs 8.17 crRs 8.01 cr
BUILDING 2NARs 2.45 cr-
-NARs 1.63 cr-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVastukalp, Partner Shri. Satish Manohar
ArchitectVASTUKALP
EngineerVastukalp, Partner Shri. Yateesh Tare
EngineerVASTUKALP
Chartered AccountantChaplot & Co
Chartered AccountantGanapath Jain
PartnerRole in project
Royal Enterprises-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000019759Mar 2024 → Mar 2026

Reason as filed by the promoterDue to unfavourable market conditions & very low bookings (Sale of under construction units) we could not complete the project on or before the 31/03/2024.Hence we request Maharera Authorities to extend the time period for completion of project up to 31/03/2026.

EA26032620383Mar 2024 → Mar 2027

Reason as filed by the promoter3. That at the time of applying for RERA registration we envisaged to complete the project on or before 31/03/2026. However the construction work was delayed due to unfavourable market conditions & low bookings (Sale of under construction units).4. Up till now we have completed 95% of the work of Building-1 of the project as per Architect Certificate enclosed. We expect to complete the pending project work and collect necessary NOC and obtain Occupancy Certificate on or before 31/03/2027.Hence we request Maharera Authorities to grant us necessary extension up to 31/03/2027 for completing the p

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed149

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 149 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: DEC 25-ARCHITECTS CERTIFICATE.pdf29 Jun 2026
Withdrawal Update Form 2File: DEC 25-ENGINEERS CERTIFICATE.pdf29 Jun 2026
Withdrawal Update Form 3File: Sold and Unsold Inventory.pdf29 Jun 2026
Form 5 (FY 2024-2025)File: Form 5-2025.pdf29 Apr 2026
Withdrawal Update Form 1File: DEC 25-ARCHITECTS CERTIFICATE.pdf26 Mar 2026
Withdrawal Update Form 2File: DEC 25-ENGINEERS CERTIFICATE.pdf26 Mar 2026
Withdrawal Update Form 3File: Royal Enterprise Q3 Form 3.pdf26 Mar 2026
Withdrawal Update Form 1File: SEP 25-ARCHITECTS CERTIFICATE.pdf25 Mar 2026
Withdrawal Update Form 2File: SEP 25-ENGINEERS CERTIFICATE.pdf25 Mar 2026
Withdrawal Update Form 3File: Royal Enterprise Q2 Form 3.pdf25 Mar 2026
Form 1File: Jun 25-ARCHITECTS CERTIFICATE.pdf17 Mar 2026
Form 2File: Jun 25-ENGINEERS CERTIFICATE.pdf17 Mar 2026
Form 3File: Royal Enterprise Q1 Form 3.pdf17 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold June 25.pdf17 Mar 2026
Form 1File: Form 1_Mar 24.pdf29 May 2025
Form 2File: Mar 24_organized.pdf29 May 2025
Form 3File: Form 3_Mar 24_compressed.pdf29 May 2025
Disclosure of Sold and Booked InventoryFile: Mar 24.pdf29 May 2025
Form 1File: Form1_June 24.pdf29 May 2025
Form 2File: June 24_organized.pdf29 May 2025
Form 3File: Form 3_June 24_compressed.pdf29 May 2025
Disclosure of Sold and Booked InventoryFile: June 24.pdf29 May 2025
Form 1File: Form 1_Sep 24.pdf29 May 2025
Form 2File: Sep 24_organized.pdf29 May 2025
Form 3File: Form 3_Sep 24_compressed.pdf29 May 2025
Disclosure of Sold and Booked InventoryFile: Sep 24.pdf29 May 2025
Form 1File: Form 1_Dec 24.pdf29 May 2025
Form 2File: Dec 24_organized.pdf29 May 2025
Form 3File: Form 3_Dec 24_compressed.pdf29 May 2025
Disclosure of Sold and Booked InventoryFile: Dec 24.pdf29 May 2025
Form 1File: Form 1_Mar 25.pdf29 May 2025
Form 2File: Mar 25_organized.pdf29 May 2025
Form 3File: Form 3_Mar 25_compressed.pdf29 May 2025
Disclosure of Sold and Booked InventoryFile: Mar 25.pdf29 May 2025
Form 5 (FY 2023-2024)File: From 5.pdf29 May 2025
Declaration in FORM BFile: Form B.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 ARCHITECT’S CERTIFICATE -Dec 17.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2 ARCHITECT’S CERTIFICATE -MARCH 18.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3 ARCHITECT’S CERTIFICATE -JUNE 18.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 4 ARCHITECT’S CERTIFICATE -SEP 18.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 6 ARCHITECT’S CERTIFICATE -March 19.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 5 ARCHITECT’S CERTIFICATE -DEC 18.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 7 ARCHITECT’S CERTIFICATE -June 19.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 5 ARCHITECT’S CERTIFICATE -DEC 18.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 9 ARCHITECT’S CERTIFICATE -Dec 19.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 10 ARCHITECT’S CERTIFICATE -March 20.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 11 ARCHITECT’S CERTIFICATE -June 20.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 12 ARCHITECT’S CERTIFICATE -Sep 20.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 13 ARCHITECT’S CERTIFICATE -Dec 20.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 14 ARCHITECT’S CERTIFICATE -March 21.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 15 ARCHITECT’S CERTIFICATE -June 21.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 16 ARCHITECT’S CERTIFICATE -Sep 21.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 17 ARCHITECT’S CERTIFICATE -Dec 21.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 18 ARCHITECT’S CERTIFICATE -March 22.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 19 ARCHITECT’S CERTIFICATE -June 22.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20 ARCHITECT’S CERTIFICATE -Sep 22.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 21 ARCHITECT’S CERTIFICATE -Dec 22.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 22 ARCHITECT’S CERTIFICATE -March 23.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 23 ARCHITECT’S CERTIFICATE -June 23.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 24 ARCHITECT’S CERTIFICATE -Sep 23.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 25 ARCHITECT’S CERTIFICATE -Dec 23.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 ENGINEER’S CERTIFICATE- March 18.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3 ENGINEER’S CERTIFICATE- JUNE 18.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4 ENGINEER’S CERTIFICATE- SEP 18.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 5 ENGINEER’S CERTIFICATE- DEC 18.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 6 ENGINEER’S CERTIFICATE- March 19.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 7 ENGINEER’S CERTIFICATE- June 19.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 8 ENGINEER’S CERTIFICATE- Sep 19.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 9 ENGINEER’S CERTIFICATE- Dec 19.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 10 ENGINEER’S CERTIFICATE- March 20.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 11 ENGINEER’S CERTIFICATE- June 20.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 12 ENGINEER’S CERTIFICATE- Sep 20.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 13 ENGINEER’S CERTIFICATE- Dec 20.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 14 ENGINEER’S CERTIFICATE- March 21.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 15 ENGINEER’S CERTIFICATE- June 21.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 16 ENGINEER’S CERTIFICATE- Sep 21.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 17 ENGINEER’S CERTIFICATE- Dec 21.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 18 ENGINEER’S CERTIFICATE- March 22.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 19 ENGINEER’S CERTIFICATE- June 22.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20 ENGINEER’S CERTIFICATE- Sep 22.pdf10 May 2024

How this compares with Raigarh

26%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 36 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ROYAL RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near TAKAI5,900+ in Raigarh

2 kmROYAL RESIDENCYCompleted 225Lapsed / revoked 56Other 124Dot size: filed unitsN

Filed coordinates, straight-line distance. 405 registered projects within 2 km.

Builder: Royal Enterprises

Royal Enterprises has 6 registrations on MahaRERA, including ROYAL HERITAGE and ROYAL RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if ROYAL RESIDENCY is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ROYAL RESIDENCY?

The registered promoter entity is Royal Enterprises, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ROYAL RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ROYAL RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ROYAL RESIDENCY?

The professionals named in the filing: Architect: Vastukalp, Partner Shri. Satish Manohar; Architect: VASTUKALP; Engineer: Vastukalp, Partner Shri. Yateesh Tare; Engineer: VASTUKALP; Chartered Accountant: Chaplot & Co; Chartered Accountant: Ganapath Jain. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ROYAL RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ROYAL RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ROYAL RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.