Home / Browse projects / Raigarh, Maharashtra / ROYAL PALM

Completed No litigation declared Residential / Group Housing project

ROYAL PALM

By MARQUIS BUILDERS

RG-MH-76713 · RERA P52000033516 · Last updated on MahaRERA portal: 10 Jun 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedregistration recorded completed
14 of 21Construction stages doneacross 2 buildings; furthest along: External plumbing and external plaster, 97%
89 of 140Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 165 documents Report an error

ROYAL PALM is a Residential / Group Housing project by MARQUIS BUILDERS in Raigarh, Maharashtra, registered with MahaRERA as P52000033516 on 22 Feb 2022. The registration is recorded completed; possession was promised by 31 Dec 2026. 51 of the 140 units on this registration are recorded sold or booked, and 14 of 21 construction stages are filed complete.

At a glance

Project

  • NameROYAL PALM
  • TypeResidential / Group Housing
  • Location
    • PLOT NO-98
    • SECTOR-18
    • ULWE NODE
    • Ulawe
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000033516
  • ReraGenie IDRG-MH-76713

Builder

  • NameMARQUIS BUILDERS
  • Entity typePartnership
  • PartnersBRIJESH VRAJLAL MAVANI, PRAFUL MANJIBHAI KAPUPARA, MUKESH NAHCHALDAS LAKHANI, RAJESH NAHCHALDAS LAKHANI

Key dates

this monthRegisteredFeb 2022PromisedDec 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on22 Feb 2022
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed165 files

Current status

36%51 of 140 units booked
66.7%Work done, per cost certificate

Figures as on 10 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ROYAL PALMA1513711182
ROYAL PALMB1513471158

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 10 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 21 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 97%.

ROYAL PALM · wing A84%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.97%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.52%
ROYAL PALM · wing B93%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.97%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.52%

Progress on shared amenities15

As on 10 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes40%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes60%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed162

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots162
Closed/Covered162
BuildingClosed/CoveredTotal
ROYAL PALM A8181
ROYAL PALM B8181

Land and ownership7

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,650 sq m
Land owned byNot the promoter
Named landowners7
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Dec 2025
LandownerVillageDistrict
SUMAN RAMNATH PATILGavhanRaigarh
ANKUSH RAMNATH PATILGavhanRaigarh
VIKAS RAMNATH PATILGavhanRaigarh
PRAVIN RAMNATH PATILGavhanRaigarh
MAHESH RAMNATH PATILGavhanRaigarh
NITIN RAMNATH PATILGavhanRaigarh
KRISHNA BABU PATILGavhanRaigarh

Approvals and building plan

Sanctioning authorityCIDCO (City and Industrial Development Corporation of Maharashtra Limited)
Permissible FSI12428.06
Proposed, not sanctioned12,379 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNERUL, NAVI MUMBAI
Estimated costRs 42.88 cr
Cost incurredRs 28.58 cr
Work done66.66%
BuildingWingEstimatedIncurred
ROYAL PALMARs 41.00 crRs 27.33 cr
-NARs 1.88 crRs 1.25 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAtul Patel
EngineerCSE Consultants
EngineerShahaji Tanpure
Chartered AccountantJ B PATEL AND ASSOCIATES
Chartered AccountantCA Rishabh Lodaya
PartnerRole in project
MARQUIS BUILDERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jan 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Feb 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Jan 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed165

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 165 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: PLAN-pages-2.pdf10 Jun 2026
Occupational CertificateFile: PLAN-pages-3.pdf10 Jun 2026
Occupational CertificateFile: PLAN-pages-4.pdf10 Jun 2026
Occupational CertificateFile: PLAN-pages-5.pdf10 Jun 2026
Occupational CertificateFile: PLAN-pages-6.pdf10 Jun 2026
Occupational CertificateFile: PLAN-pages-7.pdf10 Jun 2026
Occupational CertificateFile: PLAN-pages-8.pdf10 Jun 2026
Occupational CertificateFile: PLAN-pages-9.pdf10 Jun 2026
Occupational CertificateFile: PLAN-pages-10.pdf10 Jun 2026
Occupational CertificateFile: Form 1 Royal Palm.pdf10 Jun 2026
Occupational CertificateFile: Form 2 Royal Palm.pdf10 Jun 2026
Occupational CertificateFile: Form 3 Royal Palm.pdf10 Jun 2026
Occupational CertificateFile: OC mail verification.pdf10 Jun 2026
Occupational CertificateFile: PLAN-pages-1.pdf10 Jun 2026
Occupational CertificateFile: OC.pdf10 Jun 2026
Withdrawal Update Form 1File: Royal Palm - Q4 - Form 1.pdf30 Apr 2026
Withdrawal Update Form 2File: Royal Palm - Q4 - Form 2.pdf30 Apr 2026
Withdrawal Update Form 3File: Royal Palm - Q4 - Form 3.pdf30 Apr 2026
Form 2A (FY 2024-2025)File: Form 2 A 2024-25 final.pdf9 Mar 2026
Withdrawal Update Form 1File: ROYAL PALM - Q3 FORM 1 (Proper Sign).pdf5 Feb 2026
Withdrawal Update Form 2File: ROYAL PALM - Q3 - FORM 2 _compressed.pdf5 Feb 2026
Withdrawal Update Form 3File: ROYAL PALM - Q3 FORM 3.pdf5 Feb 2026
Withdrawal Update Form 1File: form 1 2025 SEPTEMBER.pdf18 Nov 2025
Withdrawal Update Form 2File: Form 2 Sept 2025.pdf18 Nov 2025
Withdrawal Update Form 3File: Form 3 Royal Palm (30-09-2025)_Cleint Signed (1).pdf18 Nov 2025
Form 5 (FY 2024-2025)File: Form 5 royal palm_fy 2024-25_Scanned.pdf4 Oct 2025
Form 1File: Form -1 Sept 24.pdf29 Sep 2025
Form 2File: form 2.pdf29 Sep 2025
Form 3File: CA Certificate(Royal palm) Signed.pdf29 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold unsold.pdf29 Sep 2025
Form 1File: Form 1 - Dec 24.pdf29 Sep 2025
Form 2File: form 2 (1).pdf29 Sep 2025
Form 3File: Form-3(Signed).pdf29 Sep 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked inventory.pdf29 Sep 2025
Withdrawal Update Form 1File: Form - 1.pdf29 Sep 2025
Withdrawal Update Form 2File: FORM 2.pdf29 Sep 2025
Withdrawal Update Form 3File: Form 3_Royal Palm_Signed.pdf29 Sep 2025
Form 1File: Form 1 Mar 25.pdf25 Sep 2025
Form 2File: Form - 2.pdf25 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold 25.pdf25 Sep 2025
Form 3File: Form 3 Royal palm.pdf25 Sep 2025
Form 1File: Form - 1.pdf19 Sep 2025
Form 2File: FORM 2.pdf19 Sep 2025
Form 3File: Form 3_Royal Palm_Signed.pdf19 Sep 2025
Disclosure of Sold and Booked InventoryFile: SOLD BOOK.pdf19 Sep 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold 25.pdf23 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Mar 25.pdf21 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Royal palm.pdf21 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2.pdf21 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3(Signed).pdf25 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1).pdf25 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 FINAL.pdf25 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf25 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Dec 24.pdf23 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Signed_compressed (1).pdf22 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 June 24.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 March 24.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 March 23.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 June 23.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Sept 23.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Dec 23.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 March 24.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 June 24.pdf20 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2022-23- RP.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 March 23.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 June 23.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sept 23.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 23.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD DISCLOSURE.pdf11 Jan 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD DISCLOSURE - Revised Final.pdf11 Jan 2025
Building plan approvalFile: Highlighted Plan-1.pdf8 Jan 2025
Building plan approvalFile: Highlighted Plan 2.pdf8 Jan 2025
Building plan approvalFile: Highlighted Plan- 3.pdf8 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: Highlighted CC.pdf8 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: Highlighted Plan 2.pdf8 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: Highlighted Plan- 3.pdf8 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: Highlighted Plan-1.pdf8 Jan 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD DISCLOSURE.pdf8 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 fy 22-23.pdf8 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 fy 22-23.pdf8 Jan 2025

How this compares with Raigarh

36%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ROYAL PALM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ULWE NODE5,900+ in Raigarh

2 kmROYAL PALMCompleted 129Lapsed / revoked 41Other 128Dot size: filed unitsN

Filed coordinates, straight-line distance. 298 registered projects within 2 km.

Builder: MARQUIS BUILDERS

MARQUIS BUILDERS has 1 registration on MahaRERA, including ROYAL PALM. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if ROYAL PALM is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ROYAL PALM?

The registered promoter entity is MARQUIS BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ROYAL PALM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ROYAL PALM?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ROYAL PALM?

The professionals named in the filing: Architect: Atul Patel; Engineer: CSE Consultants; Engineer: Shahaji Tanpure; Chartered Accountant: J B PATEL AND ASSOCIATES; Chartered Accountant: CA Rishabh Lodaya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ROYAL PALM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ROYAL PALM. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ROYAL PALM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.