ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Royal Orange County C Wing

Completed No litigation declared Residential / Group Housing project

Royal Orange County C Wing

By Navras Sthapatya LLP

RG-MH-12410 · RERA P52100003764 · Last updated on MahaRERA portal: 20 Jul 2021

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2022Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 62 documents Report an error

Royal Orange County C Wing is a Residential / Group Housing project by Navras Sthapatya LLP in Pune, Maharashtra, registered with MahaRERA as P52100003764 on 6 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2022.

At a glance

Project

  • NameRoyal Orange County C Wing
  • TypeResidential / Group Housing
  • Location
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 411017
  • Pincode411017
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100003764
  • ReraGenie IDRG-MH-12410

Builder

  • NameNavras Sthapatya LLP
  • Entity typeOthers
  • Named personsSandeep Sonigra, Anand Chhajed
  • Other registrations1 more →
  • Completed2 of 2

Key dates

this monthRegisteredAug 2017PromisedJun 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on6 Aug 2017
  • Promised completion30 Jun 2022
  • Revised completionNone
  • Buildings1 building record
  • Documents filed62 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C WINGNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jul 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

C WING: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 Jul 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes95%
Landscaping & Tree PlantingYes80%
Street LightingYes0%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes95%
Solid Waste Management And DisposalYes95%
Water conservation /Rain water harvestingYes95%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes95%
Open ParkingYes0%

Parking filed47

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots47
Closed/Covered26
Open Space21

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,597 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
RAJESH VASWANIPimpri Chinchawad (M Corp.)Pune
HARGOBIND TEJWANIKirkee (CB)Pune

Approvals and building plan

Permissible FSI3272.29
Proposed, not sanctioned3,272 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJangali Maharaj road,Deccan GymKhana

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSACHIN KANKARIA
PartnerRole in project
Navras Sthapatya LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 13 May 2021

Documents filed62

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: SOCIETY FORMATION CERTIFICATE.pdf20 Jul 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: completion certificate.pdf13 May 2021
Architect’s Certificate on Completion of Project (Form 4)File: c building completion certificate letter.pdf10 May 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rahatani C Wing Certificate.pdf23 Jan 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: eng cer c wing.pdf23 Jan 2021
Certificates of CA (Form 3)File: ca cer c wing.pdf23 Jan 2021
Certificates of CA (Form 3)File: CA CE C WING 300920.pdf28 Oct 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CER C WING 300920.pdf21 Oct 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG WING C SEP20.pdf21 Oct 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH C 300620.pdf11 Sep 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG C 300620.pdf11 Sep 2020
Certificates of CA (Form 3)File: CA C 31320.pdf11 Sep 2020
Certificates of CA (Form 3)File: CA C 300620.pdf11 Sep 2020
Certificates of CA (Form 5)File: FORM 5 C.pdf11 Sep 2020
Certificates of CA (Form 3)File: Rera-Wing C 31122019_compressed.pdf17 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch cer c wing 31122019.pdf13 Jan 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CER DEC 2019 C WING.pdf13 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch cer C WING.pdf15 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch cer C WING.pdf15 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CER C WING.pdf15 Nov 2019
Certificates of CA (Form 3)File: CA Wing C Rera certi compressed.pdf15 Nov 2019
Certificates of CA (Form 5)File: CA Wing C Rera certi compressed.pdf15 Nov 2019
Certificates of CA (Form 5)File: C Rera form 5 march 2019.pdf9 Aug 2019
Certificates of CA (Form 5)File: C Rera form 5 march 2019.pdf9 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: C WING ENG 30TH JUNE 19.pdf27 Jul 2019
Certificates of CA (Form 3)File: RERA CER C WING Q1 2019.pdf27 Jul 2019
Certificates of CA (Form 3)File: CACER C WING.pdf14 May 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG C WING31ST MAR 19.pdf10 May 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: eng_C WING- 31ST DEC18.pdf23 Jan 2019
Certificates of CA (Form 3)File: ca cer_q32018_cwing.pdf23 Jan 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH_CWING_Q22018.pdf12 Nov 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH_CWING_Q22018.pdf12 Nov 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG_C WING_Q2-2018.pdf12 Nov 2018
Certificates of CA (Form 3)File: RERA_C WING.pdf12 Nov 2018
Certificates of CA (Form 5)File: RERA_FORM5_C-WING.pdf5 Sep 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH_CWING_Q12018.pdf30 Jul 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG_C WING_Q12018.pdf30 Jul 2018
Certificates of CA (Form 3)File: ca cer_c wing_q12018.pdf30 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arc c wing march18.pdf21 Jun 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arc c wing march18.pdf21 Jun 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engcercwingmarch18.pdf21 Jun 2018
Certificates of CA (Form 3)File: ca cer march c wing.pdf21 Jun 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: archc wing31122017.pdf2 Feb 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: eng_C WING.pdf2 Feb 2018
Certificates of CA (Form 3)File: cac wing31122017.pdf2 Feb 2018
Details of encumbrancesFile: ENCUBRANCES.pdf20 Nov 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arc cer c wing 30sepCOMPRESSED.pdf20 Nov 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: eng cer c wing 30sep.pdf20 Nov 2017
Certificates of CA (Form 3)File: ca certificate C wing30sep.pdf20 Nov 2017
Proforma of Allotment letterFile: navras flat aggrement.pdf20 Nov 2017
Layout approvalFile: layout Plan compressed.pdf28 Jul 2017
Building plan approvalFile: layout Plan compressed.pdf28 Jul 2017
Copy of the legal title reportFile: NAV_SEARCH.pdf28 Jul 2017
Details of encumbrancesFile: navras encumbrances.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: layout Plan compressed.pdf28 Jul 2017
Building Plan Approval (IOD)File: layout Plan compressed.pdf28 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: COMM CER APRIL.pdf28 Jul 2017
Declaration in FORM BFile: s sonigra navras form b.pdf28 Jul 2017
Certificates of CA (Form 3)File: c a certificate compressed.pdf28 Jul 2017
Proforma of Allotment letterFile: navras flat aggrement.pdf28 Jul 2017
OtherFile: Navras affiadiate fstar.pdf28 Jul 2017
OtherFile: Navras affiadiate ghv.pdf28 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Royal Orange County C Wing on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pimpri Chinchawad (M Corp.)13,700+ in Pune

Builder: Navras Sthapatya LLP

Navras Sthapatya LLP has 2 registrations on MahaRERA, including Royal Orange County C Wing and Royal Orange County D wing. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Royal Orange County C Wing is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Royal Orange County C Wing?

The registered promoter entity is Navras Sthapatya LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Royal Orange County C Wing?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Royal Orange County C Wing?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Royal Orange County C Wing?

The professionals named in the filing: Architect: SACHIN KANKARIA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Royal Orange County C Wing?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Royal Orange County C Wing. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Royal Orange County C Wing to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.