Home / Browse projects / Raigarh, Maharashtra / ROYAL DIAMOND APARTMENT
ROYAL DIAMOND APARTMENT
RG-MH-74265 · RERA P52000051010 · Last updated on MahaRERA portal: 21 Jun 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 16 months past the filed date
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ROYAL DIAMOND APARTMENT is a Residential / Group Housing project by AMOL ASHOK PATIL in Raigarh, Maharashtra, registered with MahaRERA as P52000051010 on 19 May 2023. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 12 months from the original filing.
At a glance
Project
- NameROYAL DIAMOND APARTMENT
- TypeResidential / Group Housing
- Location
- SECTOR-1
- NODE PUSHPAK
- Vadghar (CT)
- Panvel
- Raigarh
- 410206
- Pincode410206
- RERA no.P52000051010
- ReraGenie IDRG-MH-74265
Builder
- NameAMOL ASHOK PATIL
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on19 May 2023
- Promised completion30 Jun 2025
- Revised completionRevised to 30 Jun 2025 (originally 30 Jun 2024)
- Buildings1 building record
- Documents filed53 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| ROYAL DIAMOND APARTMENT | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 21 Jun 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 90%.
ROYAL DIAMOND APARTMENT: 48% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 20% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 21 Jun 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed5
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| KALPANA ROHIDAS GHARAT | Owle | Raigarh |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DEEPALI KULKARNI |
| Engineer | STRUCON CONSULTING ENGINEERS |
| Chartered Accountant | CA NACHIKET DHANDEKAR |
| Partner | Role in project |
|---|---|
| AMOL ASHOK PATIL | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterExplanatory note regarding the state of development works in the projects and reason for being not completing development works of the projects within the period declared in the declaration submitted in FORM ‘B’ at the time of making the application for the registration of ROYAL DIAMOND APARTMENT’ - As per the details mentioned at the time of registration of the project at the MahaRERA Website we had mentioned 30/06/2024 as the project completion date, we will not be able to complete the project due to various unavoidable reasons. Such as 1) After the impact of the pandemic, the increasing pri
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Apr 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Apr 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Apr 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed53
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2 (4).pdf | 21 Jun 2024 |
| Declaration in FORM BFile: FORM B_compressed.pdf | 13 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 FORM 1.pdf | 13 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 FORM 1.pdf | 13 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 FORM 1.pdf | 13 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 FORM 1.pdf | 13 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 FORM 2.pdf | 13 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 FORM 2.pdf | 13 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7 FORM 2.pdf | 13 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8 FORM 2.pdf | 13 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 9 FORM 3.pdf | 13 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 10 FORM 3.pdf | 13 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 11 FORM 3.pdf | 13 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 15 FORM 3.pdf | 13 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf | 13 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 FORM 1 JUNE 2023.pdf | 26 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 FORM 1 SEPT 2023.pdf | 26 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 FORM 1 DECEMBER 2023.pdf | 26 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 FORM 1 MARCH 2024.pdf | 26 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 FORM 2 JUNE 2023.pdf | 26 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 FORM 2 SEPT 2023.pdf | 26 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7 FORM 2 DEC 2023.pdf | 26 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8 FORM 2 MAR 2024.pdf | 26 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: 13 SOLD UNSOLD JUNE 2023.pdf | 26 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: 14 SOLD UNSOLD SEPT 2023.pdf | 26 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: 15 SOLD UNSOLD DEC 2023.pdf | 26 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: 16 SOLD UNSOLD MAR 2023.pdf | 26 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 9 FORM 3 JUNE 2023.pdf | 26 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 10 FORM 3 SEPT 2023.pdf | 26 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 11 FORM 3 DEC 2023.pdf | 26 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 12 FORM 3 MARH 2024.pdf | 26 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 12 May 2023 |
| CERSAI detailsFile: 1 CERSAI details (1).pdf | 11 May 2023 |
| Layout approvalFile: LAYOUT.pdf | 25 Apr 2023 |
| Building plan approvalFile: FLOOR.pdf | 25 Apr 2023 |
| Copy of the legal title reportFile: TILE.pdf | 25 Apr 2023 |
| Details of encumbrances concerned to FinanceFile: ENCUM.pdf | 25 Apr 2023 |
| Details of encumbrances concerned to LegalFile: ENCUM.pdf | 25 Apr 2023 |
| Copy of Layout Approval (in case of layout)File: LAYOUT.pdf | 25 Apr 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: FLOOR.pdf | 25 Apr 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 25 Apr 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: plint.pdf | 25 Apr 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Disclosure of Interest in Other Real Estate Organizations (1).pdf | 25 Apr 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: separate.pdf | 25 Apr 2023 |
| Deviation Report with respect to Allotment letterFile: ALLOTMENT (1).pdf | 25 Apr 2023 |
| Deviation Report with respect to model copy of AgreementFile: AGREEMENT (1).pdf | 25 Apr 2023 |
| Declaration in FORM BFile: FORM B-PROMOTER.pdf | 14 Feb 2023 |
| PAN CardFile: PAN CARD COPY.pdf | 13 Feb 2023 |
| Declaration about Commencement CertificateFile: 1 Declaration about Commencement Certificate (1).pdf | 13 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 13 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 13 Feb 2023 |
| Proforma of Agreement for saleFile: AGREEMENT FOR SALE.pdf | 13 Feb 2023 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER DRAFT.pdf | 13 Feb 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- All 53 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep ROYAL DIAMOND APARTMENT on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NODE PUSHPAK5,900+ in Raigarh
SHREE RAM DELTA
Shreenathji Enterprises
Brillante
Callista Realty Limited
SAI SUNCITY PHASE 3
Chariot Properties LLP
ANANDAM PHASE - II
TODAY GLOBAL HOMES
Maximus Residency Phase-I
Superb Maa Developers LLP
Sai Vrindavan Dham
KT & LK SWEET HOMES
See every Raigarh project, with the district possession charts
Builder: AMOL ASHOK PATIL
AMOL ASHOK PATIL has 1 registration on MahaRERA, including ROYAL DIAMOND APARTMENT. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What does it mean that ROYAL DIAMOND APARTMENT shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if ROYAL DIAMOND APARTMENT is delayed beyond 30 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ROYAL DIAMOND APARTMENT?
The registered promoter entity is AMOL ASHOK PATIL, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ROYAL DIAMOND APARTMENT?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for ROYAL DIAMOND APARTMENT?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ROYAL DIAMOND APARTMENT?
The professionals named in the filing: Architect: DEEPALI KULKARNI; Engineer: STRUCON CONSULTING ENGINEERS; Chartered Accountant: CA NACHIKET DHANDEKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ROYAL DIAMOND APARTMENT?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback