Home / Browse projects / Palghar, Maharashtra / ROOP RAJAT PARK BUILDING NO 7A AND 7B
ROOP RAJAT PARK BUILDING NO 7A AND 7B
RG-MH-06213 · RERA P99000054501 · Last updated on MahaRERA portal: 19 Mar 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 14 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ROOP RAJAT PARK BUILDING NO 7A AND 7B is a Residential / Group Housing project by GAURAV RAMASHANKAR SINGH in Palghar, Maharashtra, registered with MahaRERA as P99000054501 on 25 Jan 2024. Possession is promised by 31 Mar 2027. The completion date has moved by 14 months from the original filing. 28 of the 56 units on this registration are recorded sold or booked, and 17 of 22 construction stages are filed complete.
At a glance
Project
- NameROOP RAJAT PARK BUILDING NO 7A AND 7B
- TypeResidential / Group Housing
- Location
- BETEGAON ROAD
- BETEGAON
- Boisar
- Palghar
- 401501
- Pincode401501
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000054501
- ReraGenie IDRG-MH-06213
Builder
- NameGAURAV RAMASHANKAR SINGH
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on25 Jan 2024
- Promised completion31 Mar 2027
- Revised completionRevised to 31 Mar 2027 (originally 31 Jan 2026)
- Buildings2 building records
- Documents filed72 files
Current status
Figures as on 19 Mar 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING NO 7A | NA | 8 | 7 | 28 | 0 | 28 |
| BUILDING NO 7B | NA | 7 | 7 | 28 | 0 | 28 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 19 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
17 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 95%.
BUILDING NO 7A82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING NO 7B81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 19 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed16
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| BUILDING NO 7A | 8 | 8 |
| BUILDING NO 7B | 8 | 8 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| PRABHA HOMES | Vasai-Virar City (M Corp) | Palghar |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| BUILDING NO 7A | NA | Rs 6.66 cr | Rs 6.33 cr |
| BUILDING NO 7B | NA | Rs 6.66 cr | Rs 6.33 cr |
| - | NA | Rs 54.00 lakh | Rs 48.60 lakh |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Pranav Deshmukh |
| Engineer | Meshram & Thakural |
| Engineer | CENTRELINE CONSULTANTS & ENGINEERS |
| Chartered Accountant | KANTHAWALA & CO |
| Chartered Accountant | KANTHAWALA & CO. |
| Partner | Role in project |
|---|---|
| GAURAV HOME BUILDERS AND DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1. While registering the project with MahaRERA,we had underestimated the project completion time which proved to be less for such a project. 2. Project got delayed which lead to lack of sales and Financial Difficulties 3. Still the project progress was on track but in between due to some issues with our labour contractor led to few months delay of works. 4. But rest assured,now the works are in full swing & will be completed with in the stipulated time lines of this extended date and OC will be obtained. 5. Also,we are uploading the PERTChart/work completion schedule of the project. 6. Hence,w
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Oct 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Dec 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Dec 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Mar 2027
Documents filed72
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form-1.pdf | 19 Mar 2026 |
| Withdrawal Update Form 2File: Form-2.pdf | 19 Mar 2026 |
| Withdrawal Update Form 3File: Form-3-.pdf | 19 Mar 2026 |
| Form 5 (FY 2024-2025)File: Form-5(Fy 2024-25).pdf | 12 Mar 2026 |
| Withdrawal Update Form 1File: Form-1 Dec 2025.pdf | 9 Mar 2026 |
| Withdrawal Update Form 2File: Form-2 Dec 2025.pdf | 9 Mar 2026 |
| Withdrawal Update Form 3File: Form-3 Dec 2025_compressed.pdf | 9 Mar 2026 |
| Withdrawal Update Form 1File: Form-1 Sep 2025.pdf | 26 Jan 2026 |
| Withdrawal Update Form 2File: Form-2 Sep 2025.pdf | 26 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 Sep 2025_C.pdf | 26 Jan 2026 |
| Form 1File: Form-1 31032025.pdf | 15 Oct 2025 |
| Form 2File: Form-2 31032025.pdf | 15 Oct 2025 |
| Form 3File: Form-3 31032025.pdf | 15 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold 31032025.pdf | 15 Oct 2025 |
| Form 2A (FY 2024-2025)File: Form-2A(Fy 2024-25).pdf | 15 Oct 2025 |
| Form 1File: Form-1 30062024.pdf | 13 Oct 2025 |
| Form 2File: Form-2 30062024.pdf | 13 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold 30062024.pdf | 13 Oct 2025 |
| Form 3File: Form-3 30062024.pdf | 13 Oct 2025 |
| Form 1File: Form-1 30092024.pdf | 13 Oct 2025 |
| Form 2File: Form-2 30092024.pdf | 13 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold 30092024.pdf | 13 Oct 2025 |
| Form 3File: Form-3 30092024.pdf | 13 Oct 2025 |
| Form 1File: Form-1 31122024.pdf | 13 Oct 2025 |
| Form 2File: Form-2 31122024.pdf | 13 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold 31122024 (2).pdf | 13 Oct 2025 |
| Form 3File: Form-3 31122024.pdf | 13 Oct 2025 |
| Form 1File: Form-1 31032024.pdf | 13 Oct 2025 |
| Form 2File: Form-2 31032024.pdf | 13 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold 31032024.pdf | 13 Oct 2025 |
| Form 3File: Form-3 31032024.pdf | 13 Oct 2025 |
| Withdrawal Update Form 1File: Form-1 30062025.pdf | 13 Oct 2025 |
| Withdrawal Update Form 2File: Form-2 30062025.pdf | 13 Oct 2025 |
| Withdrawal Update Form 3File: Form-3 30062025.pdf | 13 Oct 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate -FORM -1 14122024.pdf | 4 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 (5).pdf | 4 May 2025 |
| Disclosure of sold/ booked inventoryFile: New Document(64) 04-May-2025 17-59-24.pdf | 4 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fORM-1.pdf | 24 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf | 24 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf | 24 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: fORM-3_compressed.pdf | 24 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: new form-3 with date_compressed.pdf | 15 Jan 2024 |
| Declaration about Commencement CertificateFile: gaurav home declaration cc.pdf | 14 Jan 2024 |
| Other - LegalFile: gaurav home Plot arae explanation.pdf | 14 Jan 2024 |
| Other - TechnicalFile: gaurav home Plot arae explanation.pdf | 14 Jan 2024 |
| Layout approvalFile: 1 Copy of Layout Approval (in case of layout) (1).pdf | 29 Dec 2023 |
| Building plan approvalFile: 1 Building Plan Approval _ NA Order for plotted development.pdf | 29 Dec 2023 |
| Copy of Layout Approval (in case of layout)File: 1 Copy of Layout Approval (in case of layout) (1).pdf | 29 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 1 Building Plan Approval _ NA Order for plotted development.pdf | 29 Dec 2023 |
| Other - TechnicalFile: plinth intimation.pdf | 29 Dec 2023 |
| Other - TechnicalFile: PLINTH ARCHITECT CERT.pdf | 29 Dec 2023 |
| Other - TechnicalFile: EMAIL VERIFICATION.pdf | 29 Dec 2023 |
| Other - TechnicalFile: Affidavit cum Declaration.pdf | 25 Nov 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf | 4 Oct 2023 |
| Other - TechnicalFile: PRABHA HOMES AGREEMENT DOCUMENT1-compressed (1).pdf | 4 Oct 2023 |
| Other - TechnicalFile: declaration for cc not in the name of land owner.pdf | 4 Oct 2023 |
| PAN CardFile: gaurav singh pan card.pdf | 3 Oct 2023 |
| Copy of the legal title reportFile: LEGAL AND TITLE CERT.pdf | 3 Oct 2023 |
| Details of encumbrances concerned to FinanceFile: ENCUMBRANCES TO FINANCE.pdf | 3 Oct 2023 |
| Details of encumbrances concerned to FinanceFile: ENCUMBRANCES TO LEGAL.pdf | 3 Oct 2023 |
| Details of encumbrances concerned to LegalFile: ENCUMBRANCES TO FINANCE.pdf | 3 Oct 2023 |
| Details of encumbrances concerned to LegalFile: ENCUMBRANCES TO LEGAL.pdf | 3 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: LATEST CC 26-05-22.pdf | 3 Oct 2023 |
| Declaration in FORM BFile: form b _ Gaurav.pdf | 3 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERT.pdf | 3 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERT.pdf | 3 Oct 2023 |
| CERSAI detailsFile: cersai declaration.pdf | 3 Oct 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE IN INTEREST IN OTHER REAL ESTATE ORGINATION.pdf | 3 Oct 2023 |
| Proforma of Agreement for saleFile: AGREEMENT FOR SELL.pdf | 3 Oct 2023 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER- NEW FORMAT (1).pdf | 3 Oct 2023 |
| Deviation Report with respect to Allotment letterFile: Deviation Report with respect to allotment letter(7).pdf | 3 Oct 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to RERA Sale Agreement(4).pdf | 3 Oct 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 72 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ROOP RAJAT PARK BUILDING NO 7A AND 7B on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BETEGAON3,200+ in Palghar
Filed coordinates, straight-line distance. 66 registered projects within 2 km.
Birla Mrida
Birla Estates Private Limited
Roop Rajat Park Phase 3
MAHAVIR ASSOCIATES
AGAMI INFINITY PARK
MAYURESH REALTY PRIVATE LIMITED
Luxury Empire Township Phase I
VEENAA DEVELOPERS PRIVATE LIMITED
MAHAVIR ARCADE
MAHAVIR DEVELOPERS AND REALTORS
SHANTI VISTA - II
SHAH REALTY CORPORATION
See every Palghar project, with the district possession charts
Builder: GAURAV RAMASHANKAR SINGH
GAURAV RAMASHANKAR SINGH has 1 registration on MahaRERA, including ROOP RAJAT PARK BUILDING NO 7A AND 7B. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What are my rights if ROOP RAJAT PARK BUILDING NO 7A AND 7B is delayed beyond 31 Mar 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ROOP RAJAT PARK BUILDING NO 7A AND 7B?
The registered promoter entity is GAURAV RAMASHANKAR SINGH, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ROOP RAJAT PARK BUILDING NO 7A AND 7B?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for ROOP RAJAT PARK BUILDING NO 7A AND 7B?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ROOP RAJAT PARK BUILDING NO 7A AND 7B?
The professionals named in the filing: Architect: Pranav Deshmukh; Engineer: Meshram & Thakural; Engineer: CENTRELINE CONSULTANTS & ENGINEERS; Chartered Accountant: KANTHAWALA & CO; Chartered Accountant: KANTHAWALA & CO.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ROOP RAJAT PARK BUILDING NO 7A AND 7B?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback