Home / Browse projects / Palghar, Maharashtra / ROOP RAJAT PARK BUILDING NO 7A AND 7B

Registered No litigation declared Residential / Group Housing project

ROOP RAJAT PARK BUILDING NO 7A AND 7B

By GAURAV RAMASHANKAR SINGH

RG-MH-06213 · RERA P99000054501 · Last updated on MahaRERA portal: 19 Mar 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 14 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 14 months from the original
17 of 22Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 95%
28 of 56Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 72 documents Report an error

ROOP RAJAT PARK BUILDING NO 7A AND 7B is a Residential / Group Housing project by GAURAV RAMASHANKAR SINGH in Palghar, Maharashtra, registered with MahaRERA as P99000054501 on 25 Jan 2024. Possession is promised by 31 Mar 2027. The completion date has moved by 14 months from the original filing. 28 of the 56 units on this registration are recorded sold or booked, and 17 of 22 construction stages are filed complete.

At a glance

Project

  • NameROOP RAJAT PARK BUILDING NO 7A AND 7B
  • TypeResidential / Group Housing
  • Location
    • BETEGAON ROAD
    • BETEGAON
    • Boisar
    • Palghar
    • 401501
  • Pincode401501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000054501
  • ReraGenie IDRG-MH-06213

Builder

  • NameGAURAV RAMASHANKAR SINGH
  • Entity typeIndividual

Key dates

this monthRegisteredJan 2024First promiseJan 2026Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Jan 2024
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Jan 2026)
  • Buildings2 building records
  • Documents filed72 files

Current status

50%28 of 56 units booked
94.8%Work done, per cost certificate

Figures as on 19 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 7ANA8728028
BUILDING NO 7BNA7728028

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 19 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

17 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 95%.

BUILDING NO 7A82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 7B81%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 19 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed16

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots16
Closed/Covered16
BuildingClosed/CoveredTotal
BUILDING NO 7A88
BUILDING NO 7B88

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,911 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
PRABHA HOMESVasai-Virar City (M Corp)Palghar

Approvals and building plan

Sanctioning authorityCOLLECTOR OFFICE PALGHAR
Permissible FSI3283.13
Proposed, not sanctioned3,283 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMANGESH BHUVAN, GURU NANAK NAGAR, AMBADI ROAD VASAI WEST
Estimated costRs 13.86 cr
Cost incurredRs 13.14 cr
Work done94.81%
BuildingWingEstimatedIncurred
BUILDING NO 7ANARs 6.66 crRs 6.33 cr
BUILDING NO 7BNARs 6.66 crRs 6.33 cr
-NARs 54.00 lakhRs 48.60 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPranav Deshmukh
EngineerMeshram & Thakural
EngineerCENTRELINE CONSULTANTS & ENGINEERS
Chartered AccountantKANTHAWALA & CO
Chartered AccountantKANTHAWALA & CO.
PartnerRole in project
GAURAV HOME BUILDERS AND DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA19032620289Jan 2026 → Mar 2027

Reason as filed by the promoter1. While registering the project with MahaRERA,we had underestimated the project completion time which proved to be less for such a project. 2. Project got delayed which lead to lack of sales and Financial Difficulties 3. Still the project progress was on track but in between due to some issues with our labour contractor led to few months delay of works. 4. But rest assured,now the works are in full swing & will be completed with in the stipulated time lines of this extended date and OC will be obtained. 5. Also,we are uploading the PERTChart/work completion schedule of the project. 6. Hence,w

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Oct 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Dec 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Dec 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed72

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form-1.pdf19 Mar 2026
Withdrawal Update Form 2File: Form-2.pdf19 Mar 2026
Withdrawal Update Form 3File: Form-3-.pdf19 Mar 2026
Form 5 (FY 2024-2025)File: Form-5(Fy 2024-25).pdf12 Mar 2026
Withdrawal Update Form 1File: Form-1 Dec 2025.pdf9 Mar 2026
Withdrawal Update Form 2File: Form-2 Dec 2025.pdf9 Mar 2026
Withdrawal Update Form 3File: Form-3 Dec 2025_compressed.pdf9 Mar 2026
Withdrawal Update Form 1File: Form-1 Sep 2025.pdf26 Jan 2026
Withdrawal Update Form 2File: Form-2 Sep 2025.pdf26 Jan 2026
Withdrawal Update Form 3File: Form 3 Sep 2025_C.pdf26 Jan 2026
Form 1File: Form-1 31032025.pdf15 Oct 2025
Form 2File: Form-2 31032025.pdf15 Oct 2025
Form 3File: Form-3 31032025.pdf15 Oct 2025
Disclosure of Sold and Booked InventoryFile: sold unsold 31032025.pdf15 Oct 2025
Form 2A (FY 2024-2025)File: Form-2A(Fy 2024-25).pdf15 Oct 2025
Form 1File: Form-1 30062024.pdf13 Oct 2025
Form 2File: Form-2 30062024.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold 30062024.pdf13 Oct 2025
Form 3File: Form-3 30062024.pdf13 Oct 2025
Form 1File: Form-1 30092024.pdf13 Oct 2025
Form 2File: Form-2 30092024.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: sold unsold 30092024.pdf13 Oct 2025
Form 3File: Form-3 30092024.pdf13 Oct 2025
Form 1File: Form-1 31122024.pdf13 Oct 2025
Form 2File: Form-2 31122024.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: sold unsold 31122024 (2).pdf13 Oct 2025
Form 3File: Form-3 31122024.pdf13 Oct 2025
Form 1File: Form-1 31032024.pdf13 Oct 2025
Form 2File: Form-2 31032024.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold 31032024.pdf13 Oct 2025
Form 3File: Form-3 31032024.pdf13 Oct 2025
Withdrawal Update Form 1File: Form-1 30062025.pdf13 Oct 2025
Withdrawal Update Form 2File: Form-2 30062025.pdf13 Oct 2025
Withdrawal Update Form 3File: Form-3 30062025.pdf13 Oct 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate -FORM -1 14122024.pdf4 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 (5).pdf4 May 2025
Disclosure of sold/ booked inventoryFile: New Document(64) 04-May-2025 17-59-24.pdf4 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fORM-1.pdf24 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf24 Apr 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf24 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: fORM-3_compressed.pdf24 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: new form-3 with date_compressed.pdf15 Jan 2024
Declaration about Commencement CertificateFile: gaurav home declaration cc.pdf14 Jan 2024
Other - LegalFile: gaurav home Plot arae explanation.pdf14 Jan 2024
Other - TechnicalFile: gaurav home Plot arae explanation.pdf14 Jan 2024
Layout approvalFile: 1 Copy of Layout Approval (in case of layout) (1).pdf29 Dec 2023
Building plan approvalFile: 1 Building Plan Approval _ NA Order for plotted development.pdf29 Dec 2023
Copy of Layout Approval (in case of layout)File: 1 Copy of Layout Approval (in case of layout) (1).pdf29 Dec 2023
Building Plan Approval / NA Order for plotted developmentFile: 1 Building Plan Approval _ NA Order for plotted development.pdf29 Dec 2023
Other - TechnicalFile: plinth intimation.pdf29 Dec 2023
Other - TechnicalFile: PLINTH ARCHITECT CERT.pdf29 Dec 2023
Other - TechnicalFile: EMAIL VERIFICATION.pdf29 Dec 2023
Other - TechnicalFile: Affidavit cum Declaration.pdf25 Nov 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf4 Oct 2023
Other - TechnicalFile: PRABHA HOMES AGREEMENT DOCUMENT1-compressed (1).pdf4 Oct 2023
Other - TechnicalFile: declaration for cc not in the name of land owner.pdf4 Oct 2023
PAN CardFile: gaurav singh pan card.pdf3 Oct 2023
Copy of the legal title reportFile: LEGAL AND TITLE CERT.pdf3 Oct 2023
Details of encumbrances concerned to FinanceFile: ENCUMBRANCES TO FINANCE.pdf3 Oct 2023
Details of encumbrances concerned to FinanceFile: ENCUMBRANCES TO LEGAL.pdf3 Oct 2023
Details of encumbrances concerned to LegalFile: ENCUMBRANCES TO FINANCE.pdf3 Oct 2023
Details of encumbrances concerned to LegalFile: ENCUMBRANCES TO LEGAL.pdf3 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: LATEST CC 26-05-22.pdf3 Oct 2023
Declaration in FORM BFile: form b _ Gaurav.pdf3 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERT.pdf3 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERT.pdf3 Oct 2023
CERSAI detailsFile: cersai declaration.pdf3 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE IN INTEREST IN OTHER REAL ESTATE ORGINATION.pdf3 Oct 2023
Proforma of Agreement for saleFile: AGREEMENT FOR SELL.pdf3 Oct 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER- NEW FORMAT (1).pdf3 Oct 2023
Deviation Report with respect to Allotment letterFile: Deviation Report with respect to allotment letter(7).pdf3 Oct 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to RERA Sale Agreement(4).pdf3 Oct 2023

How this compares with Palghar

50%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 14 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ROOP RAJAT PARK BUILDING NO 7A AND 7B on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BETEGAON3,200+ in Palghar

2 kmROOP RAJAT PARK BUILDINGCompleted 13Lapsed / revoked 15Other 38Dot size: filed unitsN

Filed coordinates, straight-line distance. 66 registered projects within 2 km.

Builder: GAURAV RAMASHANKAR SINGH

GAURAV RAMASHANKAR SINGH has 1 registration on MahaRERA, including ROOP RAJAT PARK BUILDING NO 7A AND 7B. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if ROOP RAJAT PARK BUILDING NO 7A AND 7B is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ROOP RAJAT PARK BUILDING NO 7A AND 7B?

The registered promoter entity is GAURAV RAMASHANKAR SINGH, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ROOP RAJAT PARK BUILDING NO 7A AND 7B?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ROOP RAJAT PARK BUILDING NO 7A AND 7B?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ROOP RAJAT PARK BUILDING NO 7A AND 7B?

The professionals named in the filing: Architect: Pranav Deshmukh; Engineer: Meshram & Thakural; Engineer: CENTRELINE CONSULTANTS & ENGINEERS; Chartered Accountant: KANTHAWALA & CO; Chartered Accountant: KANTHAWALA & CO.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ROOP RAJAT PARK BUILDING NO 7A AND 7B?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ROOP RAJAT PARK BUILDING NO 7A AND 7B. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ROOP RAJAT PARK BUILDING NO 7A AND 7B to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.