ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / RIVANTA

Registration lapsed No litigation declared Residential / Group Housing project

RIVANTA

By THE RESIDENTEUR GROUP

RG-MH-84653 · RERA P52100050932 · Last updated on MahaRERA portal: 16 Dec 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2026Possession promised7 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
6 of 14Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 98 documents Report an error

RIVANTA is a Residential / Group Housing project by THE RESIDENTEUR GROUP in Pune, Maharashtra, registered with MahaRERA as P52100050932 on 15 May 2023. Possession was promised by 31 Mar 2026 and is now 7 months past that date. 8 of the 14 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameRIVANTA
  • TypeResidential / Group Housing
  • Location
    • AKURDI PRADHIKARAN
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 411044
  • Pincode411044
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100050932
  • ReraGenie IDRG-MH-84653

Builder

  • NameTHE RESIDENTEUR GROUP
  • Entity typePartnership
  • PartnersGIRISH SHRIKRISHNA KARNATAKI, SUMANGALA SHRIKRISHNA KARNATAKI

Key dates

7 months past promisethis monthRegisteredMay 2023PromisedMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on15 May 2023
  • Promised completion31 Mar 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed98 files

Current status

57%8 of 14 units booked
99.1%Work done, per cost certificate

Figures as on 16 Dec 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RIVANTANA8714014

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

RIVANTA: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 16 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed22

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots22
Closed/Covered22

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area488 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityPIMPRI CHINCHWAD MUNICIPAL CORPORATION
Permissible FSI1835.23
Proposed, not sanctioned835 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHINJEWADI PUNE 411057
Estimated costRs 5.45 cr
Cost incurredRs 5.40 cr
Work done99.08%
BuildingWingEstimatedIncurred
RIVANTANARs 4.45 crRs 4.45 cr
-NARs 1.00 crRs 95.00 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShekhar Kokane Planning & Design Consultants
EngineerRoyal Constructions
Chartered AccountantNavdeep Jindal
PartnerRole in project
THE RESIDENTEUR GROUP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Mar 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Mar 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Nov 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed98

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 98 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Rivanta - Form 1 - Architect Certificate 2024 Q2.pdf16 Dec 2025
Withdrawal Update Form 1File: FORM_1-_Architect_Q2_2025-26[1].pdf16 Dec 2025
Withdrawal Update Form 2File: Rivanta - Form 2 - Engineer Certificate 2024 Q2.pdf16 Dec 2025
Withdrawal Update Form 2File: FORM_2_-_Rivanta_v30th_Sept25[1].pdf16 Dec 2025
Withdrawal Update Form 3File: Rivanta - Form 3 - CA Certificate 2024 Q2_compressed.pdf16 Dec 2025
Withdrawal Update Form 3File: FORM_3_Residenture_Sep25[1]_compressed.pdf16 Dec 2025
Form 2A (FY 2023-2024)File: FORM 2 A- Quality Rivanta v 23-24 .pdf16 Dec 2025
Form 2A (FY 2024-2025)File: FORM 2 A- Quality Rivanta v 24-25 .pdf16 Dec 2025
Form 2A (FY 2025-2026)File: FORM 2 A- Quality Rivanta v 25-26 .pdf16 Dec 2025
Form 1File: Form 1- Rivanta Q3 -2023-24.pdf24 Nov 2025
Form 2File: Form 2 - Rivanta Q3 2023-24.pdf24 Nov 2025
Form 3File: Form 3-Rivanta-Q3 2023-24.pdf24 Nov 2025
Disclosure of Sold and Booked InventoryFile: Rivanta - Disclosure of Sold-Unsold Inventory Q3 2023-24.pdf24 Nov 2025
Form 1File: Form 1 - Rivanta Q2 2023-24.pdf24 Nov 2025
Form 2File: Form 2 - Rivanta Q2 2023-24.pdf24 Nov 2025
Form 3File: Form 3 - CA - Rivanta Q2 2023-24 2.pdf24 Nov 2025
Disclosure of Sold and Booked InventoryFile: Rivanta - Disclosure of Sold-Unsold Inventory Q2 2023-24.pdf24 Nov 2025
Form 1File: Form 1 Architect Q1 2023-24.pdf24 Nov 2025
Form 2File: Form 2 - Rivanta Q1 2023-24.pdf24 Nov 2025
Disclosure of Sold and Booked InventoryFile: Rivanta - Disclosure of Sold-Unsold Inventory Q1 2023-24.pdf24 Nov 2025
Form 3File: FORM 3 Rivanta 2023-24 Q1_compressed.pdf24 Nov 2025
Disclosure of Sold and Booked InventoryFile: Rivanta - Disclosure of Sold-Unsold Inventory Q4 2024-25.pdf24 Nov 2025
Form 1File: Rivanta - Form 1 - Architect Certificate Q4 2024-25.pdf24 Nov 2025
Form 2File: Rivanta - Form 2 Engineer Q4.pdf24 Nov 2025
Form 3File: Rivanta - Form 3 - CA Q4 2024-25_compressed.pdf24 Nov 2025
Disclosure of Sold and Booked InventoryFile: Rivanta_-_Disclosure_of_Sold-Unsold_Inventory_Q1_2024-25[1].pdf8 Nov 2025
Form 1File: Rivanta_-_Form_1_-_Architect_Certificate_Q1_2024-25[1].pdf8 Nov 2025
Form 2File: Rivanta_-_Form_2_-_Engineer_Certificate_Q1_2024-25[1].pdf8 Nov 2025
Form 3File: Rivanta_-_Form_3_-_CA_Certificate_Q1_2024-25[1]_compressed.pdf8 Nov 2025
Form 1File: Rivanta_-_Form_1_-_Architect_Certificate_Q1_2025-26[1].pdf8 Nov 2025
Form 2File: Rivanta_-_Form_2_-_Engineer_Certificate_Q1_2025-26_2[1].pdf8 Nov 2025
Form 3File: Rivanta_-_Form_3_-_CA_Certificate_Q1_2025-26[1].pdf8 Nov 2025
Disclosure of Sold and Booked InventoryFile: Rivanta_-Disclosure__Sold-Unsold_Inventory_Q1_2025-26[1].pdf8 Nov 2025
Form 1File: Rivanta_-_Form_1_-_Architect_Certificate_Q2_2024-25[1].pdf8 Nov 2025
Form 2File: Rivanta_-_Form_2_-_Engineer_Certificate_Q2_2024-25_2[1].pdf8 Nov 2025
Disclosure of Sold and Booked InventoryFile: Rivanta_-_Disclosure_of_Sold-Unsold_Inventory_Q2_2024-25[1].pdf8 Nov 2025
Form 3File: Rivanta_-_Form_3_-_CA_Certificate_Q2_2024-25[1]_compressed.pdf8 Nov 2025
Form 1File: Rivanta_-_Form_1_-_Architect_Certificate_Q3_2024-25[1].pdf8 Nov 2025
Form 2File: Rivanta_-_Form_2_-_Engineer_Certificate_Q3_2024-25[1].pdf8 Nov 2025
Form 3File: Rivanta-_Form_3_CA_Certificate_Q3_2024-25[1]_compressed.pdf8 Nov 2025
Disclosure of Sold and Booked InventoryFile: Rivanta_-_Disclosure_of_Sold-Unsold_Inventory_Q3_2024-25[1].pdf8 Nov 2025
Form 1File: Rivanta_-_Form_1_-_Architect_Q4_2023-24[1].pdf8 Nov 2025
Form 2File: Rivanta_-_Form_2_-_Engineer_Q4_2023-24[1].pdf8 Nov 2025
Disclosure of Sold and Booked InventoryFile: Rivanta_-_Disclosure_of_Sold-Unsold_Inventory_Q4_2023-24[1].pdf8 Nov 2025
Form 3File: Rivanta_-_FORM-3_-_CA_Q4_2023-24[1]_compressed.pdf8 Nov 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf29 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 architect.pdf29 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA_compressed.pdf29 Jan 2025
Disclosure of sold/ booked inventoryFile: Rivanta - Disclosure of Sold-Unsold Inventory 2024-Q4.pdf29 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Rivanta - Form 2 - Engineer Certificate 2024 Q4.pdf29 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rivanta - Form 1 - Architect Certificate 2024 Q4.pdf21 Jan 2025
Disclosure of sold/ booked inventoryFile: Rivanta - Disclosure of Sold-Unsold Inventory 2024-Q4.pdf21 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Rivanta - Form 2 - Engineer Certificate 2024 Q4.pdf21 Jan 2025
Building plan approvalFile: Rivanta - Sanction Plan Rev 1 - v27-Mar24_compressed.pdf29 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: REVISED Commencement Certificate.pdf29 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: Rivanta - Sanction Plan Rev 1 - v27-Mar24_compressed.pdf29 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rivanta - Form 1 - Architect Certificate 2024 Q3.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rivanta - Form 2 - Engineer Certificate 2024 Q3 2.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: Rivanta - Disclosure of Sold-Unsold Inventory 2024-Q3.pdf19 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Rivanta - Form 2 - Engineer Quality Certificate 2024 Q3 2.pdf19 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Rivanta - Form 3 - CA Certificate 2024 Q3_compressed.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rivanta - Form 1 - Architect Certificate 2024 Q2.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rivanta - Form 2 - Engineer Certificate 2024 Q2.pdf22 Jul 2024
Disclosure of sold/ booked inventoryFile: Rivanta - Disclosure of Sold-Unsold Inventory 2024-Q2.pdf22 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Rivanta - Form 3 - CA Certificate 2024 Q2_compressed.pdf22 Jul 2024
Disclosure of sold/ booked inventoryFile: Rivanta - Disclosure of Sold-Unsold Inventory 2024-Q1.pdf18 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Rivanta Q2.pdf5 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Rivanta Q3.pdf5 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Rivanta Q4.pdf5 Mar 2024
Disclosure of sold/ booked inventoryFile: Rivanta - Disclosure of Sold-Unsold Inventory Q4.pdf5 Mar 2024
Disclosure of sold/ booked inventoryFile: Rivanta - Disclosure of Sold-Unsold Inventory Q3.pdf5 Mar 2024
Disclosure of sold/ booked inventoryFile: Rivanta - Disclosure of Sold-Unsold Inventory Q2.pdf5 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA - Rivanta Q3 compressed.pdf5 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rivanta - RERA - Architect Form 1- v12-Feb.pdf20 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rivanta - RERA Architect Form - Feb24.pdf13 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Rivanta - RERA - Engineer Form 2 Feb-24.pdf13 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Rivanta - RERA - CA Form 3 Dec-23 compressed.pdf13 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE - NEW.pdf6 Apr 2023
Details of encumbrances concerned to FinanceFile: Encumbrances Certificate.pdf3 Apr 2023
Details of encumbrances concerned to LegalFile: Encumbrances Certificate.pdf3 Apr 2023

How this compares with Pune

57%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep RIVANTA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near AKURDI PRADHIKARAN13,700+ in Pune

2 kmRIVANTACompleted 38Lapsed / revoked 29Other 45Dot size: filed unitsN

Filed coordinates, straight-line distance. 112 registered projects within 2 km.

Builder: THE RESIDENTEUR GROUP

THE RESIDENTEUR GROUP has 1 registration on MahaRERA, including RIVANTA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that RIVANTA shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if RIVANTA is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RIVANTA?

The registered promoter entity is THE RESIDENTEUR GROUP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RIVANTA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for RIVANTA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RIVANTA?

The professionals named in the filing: Architect: Shekhar Kokane Planning & Design Consultants; Engineer: Royal Constructions; Chartered Accountant: Navdeep Jindal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RIVANTA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RIVANTA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RIVANTA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.