ReraGenieLog inGet a buyer report

Home / Browse projects / Sangli, Maharashtra / RIVA ICONIC B

Completed No litigation declared Residential / Group Housing project

RIVA ICONIC B

By ROHAN SUBHASH PATIL

RG-MH-77850 · RERA P53100017582 · Last updated on MahaRERA portal: 4 Sep 2021

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 2 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 57 documents Report an error

RIVA ICONIC B is a Residential / Group Housing project by ROHAN SUBHASH PATIL in Sangli, Maharashtra, registered with MahaRERA as P53100017582 on 28 Aug 2018. The registration is recorded completed; possession was promised by 30 Dec 2021.

At a glance

Project

  • NameRIVA ICONIC B
  • TypeResidential / Group Housing
  • Location
    • Anna Satyagonda Patil Nagar road
    • Near ST stand
    • Sangli
    • Sangli Miraj Kupwad (M Corp.)
    • Miraj
    • Sangli
    • 416416
  • Pincode416416
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P53100017582
  • ReraGenie IDRG-MH-77850

Builder

  • NameROHAN SUBHASH PATIL
  • Entity typeIndividual
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects3 →

Key dates

this monthRegisteredAug 2018PromisedDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on28 Aug 2018
  • Promised completion30 Dec 2021
  • Revised completionNone
  • Buildings1 building record
  • Documents filed57 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RIVA ICONIC BNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Sep 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

RIVA ICONIC B: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 4 Sep 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed26

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots26
Open Space26

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area859 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1486.76
Proposed, not sanctioned1,202 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchThe Ratnakar Bank Ltd, Mehendale Kulkarni Bhavan, Gaonbhag, Sangli 416416

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRachana Sharma
PartnerRole in project
ROHAN SUBHASH PATIL-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Aug 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Aug 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Aug 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 19 Jun 2021

Documents filed57

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration about Commencement CertificateFile: RIB Declaration Cartificate.pdf4 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: RIB FORM 2A_compressed.pdf4 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: RIB FORM 5 17-18.pdf4 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: RIB Form5 18-19.pdf4 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RIB Form 5 19-20.pdf4 Sep 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: RIB index 2.pdf4 Sep 2021
Status of ConveyanceFile: Rib Declaration Part 1.pdf6 Aug 2021
Status of ConveyanceFile: Rib declaration Part 2.pdf6 Aug 2021
Status of ConveyanceFile: Rib Declaration Part 3.pdf6 Aug 2021
Status of ConveyanceFile: Rib Declaration Part 4.pdf6 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RIB ENGG MAR 20.pdf24 Jun 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RIB ENGG JUN 20.pdf24 Jun 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RIB ENGG SEP 20.pdf24 Jun 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RIB ENGG DEC 20.pdf24 Jun 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RIB ENGG MAR 21.pdf24 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RIB ARC DEC 20.pdf23 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RIB ARC MAR 21.pdf23 Jun 2021
Disclosure of sold/ booked inventoryFile: RIB DIS OF SOLD APT.pdf23 Jun 2021
Certificates of CA (Form 3)File: RIB CA DEC 20.pdf23 Jun 2021
Certificates of CA (Form 3)File: RIB CA MAR 21.pdf23 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RIB CA MAR 21 FORM 5.pdf23 Jun 2021
Architect’s Certificate on Completion of Project (Form 4)File: RIB ARC COMPLETION.pdf23 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: RIB MNP REVISE PERMISSION.pdf19 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RIB ARC MAR 20.pdf19 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RIB ARC JUN 20.pdf19 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RIB ARC SEP 20.pdf19 Jun 2021
Certificates of CA (Form 3)File: RIB CA MAR 20.pdf19 Jun 2021
Certificates of CA (Form 3)File: RIB CA JUN 20.pdf19 Jun 2021
Certificates of CA (Form 3)File: RIB CA SEP 20.pdf19 Jun 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: RIB MNP COMPLETION.pdf19 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RIB RERA DEC 19 ARCH.pdf21 Feb 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RIB RERA DEC 19 ENG.pdf21 Feb 2020
Certificates of CA (Form 3)File: RIB RERA DEC 19 CA.pdf21 Feb 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA OCT 19 ARCH RIB.pdf16 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA OCT 19 ENG RIB.pdf16 Nov 2019
Certificates of CA (Form 3)File: RERA OCT 19 CA RIB Min.pdf16 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA JUN 19 ARCH RIB.pdf20 Sep 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA JUN 19 ENG RIB.pdf20 Sep 2019
Certificates of CA (Form 3)File: RERA JUN 19 CA RIB.pdf20 Sep 2019
Form 2AFile: RERA MA19 QA RIB.pdf14 Jun 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Ma19 Arch RIB Final.pdf20 May 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA MA19 ENG RIB(2).pdf20 May 2019
Certificates of CA (Form 3)File: RERA MA19 CA RIB(2).pdf20 May 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate RIB.pdf18 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate RIB.pdf18 Jan 2019
Certificates of CA (Form 3)File: CA cert RIB dec 18.pdf18 Jan 2019
Building plan approvalFile: Blue print 32 36.pdf16 Aug 2018
Layout approvalFile: Blank 2.pdf16 Aug 2018
PAN CardFile: pan Rohan Patil.pdf16 Aug 2018
Copy of the legal title reportFile: Legal Title 32 36 com.pdf16 Aug 2018
Details of encumbrancesFile: Encumbrance 32 36.pdf16 Aug 2018
Copy of Layout Approval (in case of layout)File: Blank 2.pdf16 Aug 2018
Building Plan Approval (IOD)File: Blue print 32 36.pdf16 Aug 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate 32 36-min.pdf16 Aug 2018
Declaration in FORM BFile: Form B 32 36-min (1).pdf16 Aug 2018
Certificates of CA (Form 3)File: C A certificate 32 36.pdf16 Aug 2018
Proforma of Allotment letterFile: agreement copy 32 36.pdf16 Aug 2018

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
RATNA HOMESAnna Satyagonda Patil Nagar Near ST stand Sangli17CompletedDec 2017Dec 2017
RATNA HOUSEAnna Satyagonda Patil nagar near st stand sangli11CompletedNov 2017Jul 2017

How this compares with Sangli

11%of Sangli projects moved their completion datethis one has not
29%of Sangli registrations have lapsed or been cancelledthis one is completed

Computed across the 790+ Sangli projects on ReraGenie, from their own filings.

Keep RIVA ICONIC B on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near ST stand, Sangli790+ in Sangli

2 kmRIVA ICONIC BCompleted 22Lapsed / revoked 11Other 7Dot size: filed unitsN

Filed coordinates, straight-line distance. 40 registered projects within 2 km.

Builder: ROHAN SUBHASH PATIL

ROHAN SUBHASH PATIL has 2 registrations on MahaRERA, including RIVA ICONIC B and Ratna Nests. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Sangli district page.

Frequently asked questions

What are my rights if RIVA ICONIC B is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RIVA ICONIC B?

The registered promoter entity is ROHAN SUBHASH PATIL, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RIVA ICONIC B?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for RIVA ICONIC B?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RIVA ICONIC B?

The professionals named in the filing: Architect: Rachana Sharma. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RIVA ICONIC B?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RIVA ICONIC B. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RIVA ICONIC B to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.