Rite Perinto

By Rite Developers Pvt. Ltd.

RG-MH-23967 · RERA P51800005813 · Last updated on MahaRERA portal: 6 Jan 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 55 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2022Possession promised55 months past this date
6 of 11Construction stages donefurthest along: Staircases, 90%
1Complaints at MahaRERAon this registration
Jump to the 84 documents Report an error

Rite Perinto is a Residential / Group Housing project by Rite Developers Pvt. Ltd. in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800005813 on 14 Aug 2017. Possession was promised by 30 Mar 2022 and is now 55 months past that date. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameRite Perinto
  • TypeResidential / Group Housing
  • Location
    • Dattapada Road
    • Diwan Compound Asara Colony
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800005813
  • ReraGenie IDRG-MH-23967

Builder

  • NameRite Developers Pvt. Ltd.
  • Entity typeCompany
  • Other registrations9 more →
  • Completed4 of 10
  • No longer live6 lapsed, de-registered or revoked
  • Declared earlier projects6 →

Key dates

55 months past promisethis monthRegisteredAug 2017First promiseMar 2021Revised toMar 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on14 Aug 2017
  • Promised completion30 Mar 2022
  • Revised completionRevised to 30 Mar 2022 (originally 30 Mar 2021)
  • Buildings1 building record
  • Documents filed84 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Rite PerintoNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Jan 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 90%.

Rite Perinto: 64% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities16

As on 6 Jan 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
OthersNoNot applicable

Parking filed15

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots15
Closed/Covered15

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,205 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3033.86
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCTS No 1023, PN 9, Esperanca Poly CHS, Holy Cross Rd, I C Colony, Borivali West, Mumbai, Maharashtra

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMS TANVI DEDHIA
EngineerRajesh Tailor
Chartered AccountantJigar Zaveri & Associates
Chartered AccountantC S Mehta & Co
PartnerRole in project
Rite Developers Pvt. Ltd.-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800009528Mar 2021 → Mar 2022

Reason as filed by the promoterWe hereby submit and Declare that delay in project and delay in getting approvals are due to implementation of DCPR 2034. We obtain Commencement Certificate bearing No. CHE/WSII/0575/R1/337(New)/FCC/1/New dated 17th March, 2020 for upto 9th Slabs. We further state that due to outbreak of life threatening COVID-19 which had already been declared as a Pandemic by World Health Organization (WHO) and complete lockdown imposed in the country and Authority had invoked force majeure clause, in such situation we could not carry out construction activity and once it got unlocked, we commenced Construct

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000374812GUMPHADARSHAN A&B CHS LTD R S PAIRITE DEVELOPERS PVT LTD16/03/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Jul 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Jul 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 6 Jan 2024

Documents filed84

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 84 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Gumpha Part OC 04012024.pdf6 Jan 2024
Certificates of CA (Form 3)File: Form 3 Perinto.pdf17 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Signed Form 1 Rite Perinto 30 Sep 2023.pdf10 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Signed Rite Perinto Engineer Form 2 September 23.pdf7 Oct 2023
Certificates of CA (Form 3)File: Signed CA Certificate Rite Perinto 30 June 23.pdf25 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Signed Rite Perinto architect Form 1 June 2023 (5).pdf18 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Signed Aspire Engineer Form 2 - June 23.pdf18 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Signed Rite Perinto Engineer Form 2 June 23.pdf13 Jul 2023
OtherFile: 5_6296554753245579468.pdf16 Feb 2023
OtherFile: architect certificate other.pdf14 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rite Perinto Architect form 1 30 sep 2022.pdf5 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rite Perinto Architect form 1 31 dec 2022.pdf5 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RITE PERINTO sep 2020.pdf7 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RITE PERINTO dec 2020.pdf7 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RITE PERINTO march 2021.pdf7 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RITE PERINTO june 2021.pdf7 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RITE PERINTO sep 2021.pdf7 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RITE PERINTO dec 2021.pdf7 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RITE PERINTO march 2022.pdf7 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RITE PERINTO june 2022.pdf7 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RITE PERINTO 30 SEP 2020.pdf7 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RITE PERINTO 31 DEC 2020.pdf7 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RITE PERINTO 31 MAR 2021.pdf7 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RITE PERINTO 30 JUN 2021.pdf7 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RITE PERINTO 30 SEP 2021.pdf7 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RITE PERINTO 31 DEC 2021.pdf7 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RITE PERINTO 31 MAR 2022.pdf7 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RITE PERINTO 30 JUN 2022.pdf7 Oct 2022
Commencement Certificates / NA Order for plotted developmentFile: Rite Perinto Commencement Certificate.pdf20 Dec 2021
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory Rite Perinto.pdf14 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Rite Perinto.pdf14 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A QAC Rite Perinto FY 2019-2020.pdf11 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A QAC Rite Perinto FY 2020-2021.pdf11 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Rite Perinto.pdf10 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Rite Perinto.pdf10 Aug 2021
Certificates of CA (Form 3)File: Form 3 Rite Perinto.pdf10 Aug 2021
Declaration about Commencement CertificateFile: Format D Rite Perinto 06082021.pdf7 Aug 2021
Commencement Certificates / NA Order for plotted developmentFile: 0575_FurtherCC_signed.pdf6 Aug 2021
Building plan approvalFile: Rite Perinto - Amended Approval Letter.pdf14 Jul 2021
Layout approvalFile: Plan 3-4-1 (1).pdf14 Jul 2021
Layout approvalFile: Plan 3-4-2 (1).pdf14 Jul 2021
Layout approvalFile: Plan 5-6-1.pdf14 Jul 2021
Layout approvalFile: Plan 5-6-2.pdf14 Jul 2021
Copy of Layout Approval (in case of layout)File: Plan 3-4-1 (1).pdf14 Jul 2021
Copy of Layout Approval (in case of layout)File: Plan 3-4-2 (1).pdf14 Jul 2021
Copy of Layout Approval (in case of layout)File: Plan 5-6-1.pdf14 Jul 2021
Copy of Layout Approval (in case of layout)File: Plan 5-6-2.pdf14 Jul 2021
Building Plan Approval (IOD)File: Rite Perinto - Amended Approval Letter.pdf14 Jul 2021
Disclosure of sold/ booked inventoryFile: Rite Perinto.pdf9 Jun 2021
Certificates of CA (Form 3)File: FORM 3 Rite Perinto.pdf21 Jul 2020
Commencement Certificates / NA Order for plotted developmentFile: Rite Perinto CC.pdf17 Mar 2020
Building plan approvalFile: IOD.pdf17 Feb 2020
Building plan approvalFile: IOD (2).pdf17 Feb 2020
Building plan approvalFile: IOD (4).pdf17 Feb 2020
Building Plan Approval (IOD)File: IOD.pdf17 Feb 2020
Building Plan Approval (IOD)File: IOD (2).pdf17 Feb 2020
Building Plan Approval (IOD)File: IOD (4).pdf17 Feb 2020
OtherFile: Provisional CFO NOC_compressed.pdf9 Jan 2020
OtherFile: CFO NOC.pdf13 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: rite perinto.pdf11 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 RITE PERINTO.pdf25 Oct 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 RITE PERINTO.pdf25 Oct 2018
Certificates of CA (Form 3)File: FORM 3 RITE PERINTO.pdf25 Oct 2018
Certificates of CA (Form 5)File: FORM 5 RITE PERINTO.pdf15 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 MunArch Certificate.pdf2 Aug 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engg Certificate.pdf2 Aug 2018
Certificates of CA (Form 3)File: Form 3 CA Certificate.pdf2 Aug 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Rite Perimto.pdf30 Dec 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Rite Perimto.pdf30 Dec 2017
Certificates of CA (Form 3)File: Form 3 Rite Perimto.pdf30 Dec 2017
Building plan approvalFile: IOD.pdf28 Jul 2017
Layout approvalFile: (1) IOD.pdf28 Jul 2017
Copy of the legal title reportFile: Title Certificate.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: (1) IOD.pdf28 Jul 2017
Building Plan Approval (IOD)File: IOD.pdf28 Jul 2017
Certificates of CA (Form 3)File: Form 3 - CA Certificate.pdf28 Jul 2017
Proforma of Allotment letterFile: Agreement For Sale.pdf28 Jul 2017
Proforma of Allotment letterFile: Allottment Letter .pdf28 Jul 2017
OtherFile: Resolution.pdf28 Jul 2017
OtherFile: GIS Survey Certificate.pdf28 Jul 2017

Promoter's earlier projects6

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

6 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Rite PrimeAndheri West9CompletedMay 2016Late, Mar 2018
Rite CelestaKandivali West24CompletedJun 2015Late, Sep 2017
Rite OpusKandivali West16CompletedMar 2015Late, Mar 2016
Rite SplendorBorivali East31CompletedDec 2014Late, Apr 2015
Rite SenorMulund East43CompletedMar 2014Late, May 2015
Rite FortuneKandivali West51CompletedApr 2013Late, Mar 2016

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Rite Perinto on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Diwan Compound Asara Colony6,700+ in Mumbai Suburban

2 kmRite PerintoCompleted 151Lapsed / revoked 85Other 206Dot size: filed unitsN

Filed coordinates, straight-line distance. 442 registered projects within 2 km.

Builder: Rite Developers Pvt. Ltd.

Rite Developers Pvt. Ltd. has 10 registrations on MahaRERA, including Rite Bliss and Rite Aspire. Its filings disclose 6 earlier MahaRERA projects: declares 0 of 6 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Rite Perinto shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Rite Perinto is delayed beyond 30 Mar 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Rite Perinto?

The registered promoter entity is Rite Developers Pvt. Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Rite Perinto?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Rite Perinto?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Rite Perinto?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Rite Perinto?

The professionals named in the filing: Architect: MS TANVI DEDHIA; Engineer: Rajesh Tailor; Chartered Accountant: Jigar Zaveri & Associates; Chartered Accountant: C S Mehta & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Rite Perinto?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Rite Perinto. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Rite Perinto to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.