Registration lapsed No litigation declared Others project

RISHABH HEIGHT

By ADINATH ENTERPRISE

RG-MH-25151 · RERA P51800003448 · Last updated on MahaRERA portal: 22 Aug 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 69 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jan 2021Possession promised69 months past this date
11 of 11Construction stages doneevery applicable stage filed complete
1Complaints at MahaRERAon this registration
Jump to the 42 documents Report an error

RISHABH HEIGHT is a Others project by ADINATH ENTERPRISE in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003448 on 5 Aug 2017. Possession was promised by 30 Jan 2021 and is now 69 months past that date. The completion date has moved by 18 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameRISHABH HEIGHT
  • TypeOthers
  • Location
    • royal complex
    • borivali west
    • Borivali
    • Mumbai Suburban
    • 400092
  • Pincode400092
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800003448
  • ReraGenie IDRG-MH-25151

Builder

  • NameADINATH ENTERPRISE
  • Entity typePartnership
  • PartnersANITA ABHAY BHANDARI, GUNVANTI NAGINCHAND JAIN, PRAKASH VIMALCHAND DHOKA
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

69 months past promisethis monthRegisteredAug 2017First promiseJul 2019Revised toJan 2021

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Aug 2017
  • Promised completion30 Jan 2021
  • Revised completionRevised to 30 Jan 2021 (originally 31 Jul 2019)
  • Buildings1 building record
  • Documents filed42 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RISHABH HEIGHTNA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Aug 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

RISHABH HEIGHT: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 22 Aug 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes50%
Open ParkingYes100%

Parking filed9

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots9
Open Space9

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,715 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
VASUNDHARA BUILDER & DEVELOPERBorivaliMumbai Suburban

Approvals and building plan

Permissible FSI2983.71
Proposed, not sanctioned2,293 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchP D MELLO ROAD

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNeo Con Infrastructure
EngineerR D Magdum
PartnerRole in project
ADINATH ENTERPRISE-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800002138Jul 2019 → Jul 2020

Reason as filed by the promoterSINCE THE DP ROAD PASSING NEXT TO OUR PLOT IS NOT YET CONSTRUCTED BY BMC BECAUSE OF THIS REASON WE ARE NOT ABLE TO GET THE FIRE NOC . WE WOULD LIKE TO REQUEST YOU TO PLEASE GRANT US THE EXTENSION FOR FURTHER 12 MONTHS.

Litigation declared6

CaseCourtStatus
220/2012GOREGAON CITI CIVIL COURTSUIT
2452/2016GOREGAON CITY CIVIL COURTPENDING SUIT
323/12/2013NATIONAL CONSUMER DISPUTE REDRESSAL COMMISSION MUMBAIWON AT STATE CONSUMER
3818/2016Goregoan CITY CIVIL COURTINTERIM RELIEF IS PENDING
256/2008GOREGAON CITI CIVIL COURTPENDING
725/2016NATIONAL CONSUMER DISPUTE REDRESSAL COMMISSION NEW DELHIPENDING

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000055778Mrs. Prabha Dhirendra MehtaM/s. Adinath Enterprise13/08/2018

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed42

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society formation certificate.pdf22 Aug 2022
CERSAI detailsFile: CERSAI_Search_Report.pdf3 Mar 2022
Disclosure of sold/ booked inventoryFile: inventory dislcosure.pdf1 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA FORM 5 20-21.pdf23 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: ENGINEER FORM 2A 19-20.pdf11 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGINEER FORM 2A 20-21.pdf11 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CA FORM 5 19-20.pdf23 Nov 2021
Declaration about Commencement CertificateFile: cc declaration.pdf18 Sep 2021
Disclosure of sold/ booked inventoryFile: disclosure of inventory.pdf18 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: rishabh heights architect letter (1).pdf9 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH.pdf28 Jan 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: ADINATH.pdf23 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH ADINATH.pdf19 Oct 2019
Certificates of CA (Form 5)File: Adinath Enterprises.pdf21 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH NO PROGRESS.pdf17 Jul 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf16 Apr 2019
Certificates of CA (Form 3)File: Amit Dave CA.pdf20 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ADINATH ARCHITECT.pdf14 Feb 2019
Certificates of CA (Form 3)File: ADINATH CA.PDF14 Feb 2019
Certificates of CA (Form 3)File: Rishabh height.pdf19 Nov 2018
OtherFile: OTHER RH.pdf19 Nov 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH COMP.pdf31 Oct 2018
Certificates of CA (Form 5)File: form5.pdf31 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf30 Jul 2017
Certificates of CA (Form 3)File: Form 3 FINAL.pdf30 Jul 2017
Certificates of CA (Form 3)File: form-3 COPROMOTER AD FINAL.pdf30 Jul 2017
Proforma of Allotment letterFile: Affidavit for Agreement for Sale_AE.pdf30 Jul 2017
Proforma of Allotment letterFile: Allotment Letter_AE.pdf30 Jul 2017
Layout approvalFile: MYSCAN_20170717_0001.pdf27 Jul 2017
Building plan approvalFile: MYSCAN_20170717_0002.pdf27 Jul 2017
Building plan approvalFile: MYSCAN_20170717_0007.pdf27 Jul 2017
Building plan approvalFile: MYSCAN_20170717_0005.pdf27 Jul 2017
PAN CardFile: AE PAN CARD FINAL.pdf27 Jul 2017
Copy of the legal title reportFile: Title certificate.pdf27 Jul 2017
Details of encumbrancesFile: Encumberances letter FINAL.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: MYSCAN_20170717_0001.pdf27 Jul 2017
Building Plan Approval (IOD)File: MYSCAN_20170717_0002.pdf27 Jul 2017
Building Plan Approval (IOD)File: MYSCAN_20170717_0005.pdf27 Jul 2017
Building Plan Approval (IOD)File: MYSCAN_20170717_0007.pdf27 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC final.pdf27 Jul 2017
Declaration in FORM BFile: FORM ‘B’ Affidavit cum Declaration_Adinath Enterprises FINAL.pdf27 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 18 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep RISHABH HEIGHT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near borivali west6,700+ in Mumbai Suburban

2 kmRISHABH HEIGHTCompleted 166Lapsed / revoked 97Other 226Dot size: filed unitsN

Filed coordinates, straight-line distance. 489 registered projects within 2 km.

Builder: ADINATH ENTERPRISE

ADINATH ENTERPRISE has 2 registrations on MahaRERA, including SAANVI HEIGHTS and RISHABH HEIGHT. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that RISHABH HEIGHT shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if RISHABH HEIGHT is delayed beyond 30 Jan 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RISHABH HEIGHT?

The registered promoter entity is ADINATH ENTERPRISE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RISHABH HEIGHT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against RISHABH HEIGHT?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for RISHABH HEIGHT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RISHABH HEIGHT?

The professionals named in the filing: Architect: Neo Con Infrastructure; Engineer: R D Magdum. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RISHABH HEIGHT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RISHABH HEIGHT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RISHABH HEIGHT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.