Home / Browse projects / RIGVED WINDSONG

Registered No litigation declared Residential / Group Housing project

RIGVED WINDSONG

By RIGVED LANDMARKS AOP

RG-MH-53446 · RERA P51900046334 · Last updated on MahaRERA portal: 30 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Mar 2028Possession promisedmoved 24 months from the original
4 of 11Construction stages donefurthest along: Internal walls, 92%
22 of 27Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 98 documents Report an error

RIGVED WINDSONG is a Residential / Group Housing project by RIGVED LANDMARKS AOP in MATUNGA, 400019, registered with MahaRERA as P51900046334 on 22 Jun 2022. Possession is promised by 31 Mar 2028. The completion date has moved by 24 months from the original filing. 5 of the 27 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameRIGVED WINDSONG
  • TypeResidential / Group Housing
  • Location
    • CHANDAVARKAR ROAD
    • MATUNGA
    • 400019
  • Pincode400019
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900046334
  • ReraGenie IDRG-MH-53446

Builder

  • NameRIGVED LANDMARKS AOP
  • Entity typeOthers
  • Named personsDILIP SOMAIYA, SARLA SOMAIYA

Key dates

this monthRegisteredJun 2022First promiseMar 2026Revised toMar 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Jun 2022
  • Promised completion31 Mar 2028
  • Revised completionRevised to 31 Mar 2028 (originally 31 Mar 2026)
  • Buildings1 building record
  • Documents filed98 files

Current status

19%5 of 27 units booked
91.7%Work done, per cost certificate

Figures as on 30 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RIGVED WINDSONGNA171625227

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 92%.

RIGVED WINDSONG: 78% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises92%
Sanitary Fittings within the flats / premises92%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks92%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.92%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.92%

Progress on shared amenities15

As on 30 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes85%
Storm Water DrainsYes85%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes85%
Water conservation /Rain water harvestingYes85%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed38

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots38
Closed/Covered35
Open Space3

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area472 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on10 Sep 2025
LandownerVillageDistrict
DILIP SOMAIYA-Mumbai City
SARLA SOMAIYA-Mumbai City

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI2392.37
Proposed, not sanctioned2,122 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRAJ NIKETAN BHANDARKAR ROAD MATUNGA CENTRAL MUMBAI 400019
Estimated costRs 15.75 cr
Cost incurredRs 14.44 cr
Work done91.66%
BuildingWingEstimatedIncurred
RIGVED WINDSONGNARs 11.25 crRs 10.61 cr
-NARs 4.50 crRs 3.83 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectA P DHARIA AND ASSOCIATES
EngineerU D CHANDE LLP
Chartered AccountantHAY AND ASSOCIATES
Chartered AccountantD L CHOTHANI & CO
PartnerRole in project
RIGVED LANDMARKS AOP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA27042620748Mar 2026 → Mar 2028

Reason as filed by the promoterThe Promoter is in a process of obtaining approval for an additional Six floors up to 90 mtrs.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 May 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Dec 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Apr 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2028

Documents filed98

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 98 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Arch Rera Certificate upto Jun 26.pdf30 Jul 2026
Withdrawal Update Form 1File: Arch Rera Certificate upto Jun 26.pdf30 Jul 2026
Withdrawal Update Form 2File: RCC certi upto June 2026 Form 2.pdf30 Jul 2026
Withdrawal Update Form 2File: RCC certi upto June 2026 Form 2.pdf30 Jul 2026
Withdrawal Update Form 3File: CA Certificate up to June 2026.pdf30 Jul 2026
Withdrawal Update Form 3File: CA Certificate up to June 2026.pdf30 Jul 2026
Withdrawal Update Form 1File: Arch Form1.pdf4 Jun 2026
Withdrawal Update Form 2File: Rev RCC form 2.pdf4 Jun 2026
Withdrawal Update Form 3File: Rera Form 3 26052026.pdf4 Jun 2026
Form 2A (FY 2025-2026)File: Form 2A.pdf8 May 2026
Withdrawal Update Form 1File: Arch Form1.pdf6 May 2026
Withdrawal Update Form 2File: Rev RCC form 2.pdf6 May 2026
Withdrawal Update Form 3File: Signed Certificate - Rera Form 3.pdf6 May 2026
Withdrawal Update Form 1File: Arch Form1.pdf27 Apr 2026
Withdrawal Update Form 2File: Rev RCC form 2.pdf27 Apr 2026
Withdrawal Update Form 3File: Signed Certificate - Rera Form 3.pdf27 Apr 2026
Withdrawal Update Form 1File: Arch Form1.pdf24 Apr 2026
Withdrawal Update Form 2File: Rev RCC form 2.pdf24 Apr 2026
Withdrawal Update Form 3File: Rev CA July2025 to Sept2025 Form 3.pdf24 Apr 2026
Withdrawal Update Form 1File: Arch Rera Certificate upto Dec 25.pdf21 Jan 2026
Withdrawal Update Form 2File: RCC RERA Certificate upto Dec 25.pdf21 Jan 2026
Withdrawal Update Form 3File: Rev CA July2025 to Sept2025 Form 3.pdf21 Jan 2026
Withdrawal Update Form 1File: Architect certificate July 2025 to Sept 2025.pdf13 Jan 2026
Withdrawal Update Form 2File: RCC consultant certificate July 2025 to Sept 2025.pdf13 Jan 2026
Withdrawal Update Form 3File: Rev CA July2025 to Sept2025 Form 3.pdf13 Jan 2026
Layout approvalFile: Part OC plan 1.pdf31 Dec 2025
Withdrawal Update Form 1File: Architect certificate July 2025 to Sept 2025.pdf31 Dec 2025
Withdrawal Update Form 2File: RCC consultant certificate July 2025 to Sept 2025.pdf31 Dec 2025
Withdrawal Update Form 3File: Rev CA July2025 to Sept2025 Form 3.pdf31 Dec 2025
Withdrawal Update Form 1File: Architect certificate July 2025 to Sept 2025.pdf4 Dec 2025
Withdrawal Update Form 2File: RCC consultant certificate July 2025 to Sept 2025.pdf4 Dec 2025
Withdrawal Update Form 3File: CA certificate July2025 to Sept 2025.pdf4 Dec 2025
Form 5 (FY 2024-2025)File: Form 5 - RERA Certificate.pdf21 Nov 2025
Withdrawal Update Form 1File: Architect certificate July 2025 to Sept 2025.pdf10 Nov 2025
Withdrawal Update Form 1File: Architect certificate July 2025 to Sept 2025.pdf10 Nov 2025
Withdrawal Update Form 2File: RCC consultant certificate July 2025 to Sept 2025.pdf10 Nov 2025
Withdrawal Update Form 2File: RCC consultant certificate July 2025 to Sept 2025.pdf10 Nov 2025
Withdrawal Update Form 3File: CA certificate 30062024.pdf10 Nov 2025
Withdrawal Update Form 3File: CA certificate 30062024.pdf10 Nov 2025
Form 1File: Arch Certificate upto June 25.pdf10 Sep 2025
Form 2File: RCC Engineer certificate April 2025 to June 2025.pdf10 Sep 2025
Form 3File: CA certi upto June 2025.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold Inventory Letter.pdf10 Sep 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Rera Certificate upto Mar 25.pdf21 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Upto march 2025.pdf21 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RCC consultant upto March 2025.pdf21 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archi Rera Certificate.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certi.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RCC consultant.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch rera Certificate.pdf5 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf5 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Civil Eng rera certificate.pdf5 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA Certificate.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archi certificate.pdf19 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RCC Certificate.pdf19 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate 30062024.pdf19 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archi Certi upto March 24.pdf3 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RCC Consultant Certificate.pdf3 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA RERA FORM 3 AY 23-24-Q4.pdf3 May 2024
Building plan approvalFile: Amended Approved Plan.pdf8 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: Amended Approved Plan.pdf8 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold Inventory Letter.pdf8 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf5 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect RERA certificate Oct 2023 to Dec 2023.pdf22 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: CA RERA Certificate - OCT 2023 to Dec 2023 - 1.pdf22 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Civil Eng RERA Cert Oct 2023 to Dec 2023 1.pdf22 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA RERA Certificate - OCT 2023 to Dec 2023 - 1.pdf22 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archi Rera Certificate July 2023 to Sep 2023.pdf1 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RCC RERA Certificate July 2023 To Sep 2023.pdf1 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA RERA Certificate - July to Sept 2023 New.pdf1 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archi Rera Certificate - April to June2023.pdf13 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RCC Certificate - April to June 2023.pdf13 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - April to June 2023.pdf13 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Audit Report - Form 5 2022-2023.pdf26 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archi Cert.pdf12 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Certificate.pdf12 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf12 Jul 2023
Commencement Certificates / NA Order for plotted developmentFile: Revalidated CC.pdf7 Jun 2023
Details of encumbrancesFile: Declaration.pdf24 Nov 2022
Declaration about Commencement CertificateFile: Declaration about CC .pdf24 Nov 2022

Keep RIGVED WINDSONG on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MATUNGA

Builder: RIGVED LANDMARKS AOP

RIGVED LANDMARKS AOP has 1 registration on MahaRERA, including RIGVED WINDSONG. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What are my rights if RIGVED WINDSONG is delayed beyond 31 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RIGVED WINDSONG?

The registered promoter entity is RIGVED LANDMARKS AOP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RIGVED WINDSONG?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for RIGVED WINDSONG?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RIGVED WINDSONG?

The professionals named in the filing: Architect: A P DHARIA AND ASSOCIATES; Engineer: U D CHANDE LLP; Chartered Accountant: HAY AND ASSOCIATES; Chartered Accountant: D L CHOTHANI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RIGVED WINDSONG?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RIGVED WINDSONG. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RIGVED WINDSONG to a free account