Home / Browse projects / Raigarh, Maharashtra / RHYTHM PLANET

Registered No litigation declared Others project

RHYTHM PLANET

By SKY HOME DEVELOPERS

RG-MH-05787 · RERA P52000051457 · Last updated on MahaRERA portal: 18 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 18 months from the original
3 of 11Construction stages donefurthest along: Stilt Floor, 50%
17 of 22Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 53 documents Report an error

RHYTHM PLANET is a Others project by SKY HOME DEVELOPERS in Raigarh, Maharashtra, registered with MahaRERA as P52000051457 on 23 Jun 2023. Possession is promised by 30 Jun 2027. The completion date has moved by 18 months from the original filing. 5 of the 22 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameRHYTHM PLANET
  • TypeOthers
  • Location
    • SECTOR 25A
    • PUSHPAK WAHAL
    • Wahal
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • RERA no.P52000051457
  • ReraGenie IDRG-MH-05787

Builder

  • NameSKY HOME DEVELOPERS
  • Entity typePartnership
  • PartnersSUBHASH MADHUKAR PAWAR, AYUB ISHAQUE MOHAMMED KHAN

Key dates

this monthRegisteredJun 2023First promiseDec 2025Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Jun 2023
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed53 files

Current status

23%5 of 22 units booked

Figures as on 18 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RHYTHAM PLANETNA6618422

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 50%.

RHYTHAM PLANET: 40% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor50%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed4

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots4
Closed/Covered4

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area363 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
Pramod Atmaram BhatkarKombadbhujeRaigarh
Draupadi Pramod BhatkarKombadbhujeRaigarh

Approvals and building plan

Sanctioning authorityCIDCO
Permissible FSI858.68
Proposed, not sanctioned859 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGOODWILL EXCELLENCY SECTOR 17 VASHI THANE 400705

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVINOD M TANDON
EngineerB S SUKTHANKAR AND ASSOCIATES
Chartered AccountantCA DEVYANI SHEJWAL
Chartered AccountantM.S K Hemant & C O
PartnerRole in project
SKY HOME DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA29072621922Dec 2025 → Jun 2027

Reason as filed by the promoter1) Poor booking response from customer. 2) Because of poor response our work was very slow.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 May 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 May 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 May 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 May 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed53

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2023-2024)File: FORM 5 Rhythum Planet 2023-24.pdf18 Aug 2026
Form 5 (FY 2024-2025)File: FORM 5 Rhythum Planet 2024-25.pdf18 Aug 2026
Form 2A (FY 2023-2024)File: Form 2A 2023-24.pdf29 Jul 2026
Form 2A (FY 2024-2025)File: Form 2A 2024-25.pdf29 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A 2025-26.pdf29 Jul 2026
Form 1File: Form 1 300625 signed planet.pdf22 Jul 2026
Form 2File: Form 2 300625 signed planet.pdf22 Jul 2026
Form 3File: FORM 3 30-06-25 Sky Home Developers.pdf22 Jul 2026
Disclosure of Sold and Booked InventoryFile: Discloser sold unsold.pdf22 Jul 2026
Form 1File: Form 1 30092025 signed.pdf22 Jul 2026
Form 2File: Form 2 Sep 25.pdf22 Jul 2026
Disclosure of Sold and Booked InventoryFile: Discloser sold unsold.pdf22 Jul 2026
Form 3File: FORM 3 30-09-25 Sky Home Developers.pdf22 Jul 2026
Form 1File: Form 1 311225 signed.pdf22 Jul 2026
Form 2File: Form 2 311225 signed.pdf22 Jul 2026
Disclosure of Sold and Booked InventoryFile: Discloser of sold and book.pdf22 Jul 2026
Form 3File: FORM 3 31-12-25 Sky Home Developers.pdf22 Jul 2026
Form 1File: Form 1 skyhome q4.pdf18 Jun 2025
Form 2File: Form 2 skyhome q4.pdf18 Jun 2025
Form 3File: FORM 3 Sky q4.pdf18 Jun 2025
Disclosure of Sold and Booked InventoryFile: sold unsold skyhome q4.pdf18 Jun 2025
Self-declaration of Quarterly ProgressFile: Dclaration for qpr skyhome q4.pdf18 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Signed.pdf15 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf15 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf15 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf4 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - converted.pdf4 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 sign.pdf28 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 sign.pdf28 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arcti-Certificate.pdf20 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng-certif.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 New.pdf1 Jun 2023
Proforma of Allotment letterFile: ALLOTMENT DRAFT NEW.pdf1 Jun 2023
Other - LegalFile: decleration about partner change (4 files merged).pdf1 Jun 2023
Other - TechnicalFile: decleration about partner change (4 files merged).pdf1 Jun 2023
Details of encumbrances concerned to FinanceFile: declartion of encumbrances.pdf6 May 2023
Details of encumbrances concerned to LegalFile: declartion of encumbrances.pdf6 May 2023
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf6 May 2023
Declaration about Commencement CertificateFile: cc declaration.pdf6 May 2023
Declaration in FORM BFile: From B PROMOTER.pdf6 May 2023
CERSAI detailsFile: CERSAI Search Report.pdf6 May 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE IN OTHER.pdf6 May 2023
Proforma of Agreement for saleFile: AFS.pdf6 May 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: declarion of bank acc.pdf6 May 2023
Deviation Report with respect to Allotment letterFile: declartion of allottemment leeter.pdf6 May 2023
Deviation Report with respect to model copy of AgreementFile: declartion of draft sale.pdf6 May 2023
Building plan approvalFile: paln.pdf5 May 2023
Layout approvalFile: paln.pdf5 May 2023
PAN CardFile: COMPANY PAN.pdf5 May 2023
Copy of the legal title reportFile: Legal Title Report.pdf5 May 2023
Copy of Layout Approval (in case of layout)File: paln.pdf5 May 2023
Building Plan Approval / NA Order for plotted developmentFile: paln.pdf5 May 2023

How this compares with Raigarh

23%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 18 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep RHYTHM PLANET on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUSHPAK WAHAL5,900+ in Raigarh

Builder: SKY HOME DEVELOPERS

SKY HOME DEVELOPERS has 1 registration on MahaRERA, including RHYTHM PLANET. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if RHYTHM PLANET is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RHYTHM PLANET?

The registered promoter entity is SKY HOME DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RHYTHM PLANET?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for RHYTHM PLANET?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RHYTHM PLANET?

The professionals named in the filing: Architect: VINOD M TANDON; Engineer: B S SUKTHANKAR AND ASSOCIATES; Chartered Accountant: CA DEVYANI SHEJWAL; Chartered Accountant: M.S K Hemant & C O. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RHYTHM PLANET?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RHYTHM PLANET. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RHYTHM PLANET to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.