Home / Browse projects / Reshmanand Park
Reshmanand Park
By Sejal buildcon Pvt ltd and Murlidhar A More
RG-MH-48371 · RERA P51600023553 · Last updated on MahaRERA portal: 26 Jul 2021
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Reshmanand Park is a Residential / Group Housing project by Sejal buildcon Pvt ltd and Murlidhar A More in Shantinagar, 422003, registered with MahaRERA as P51600023553 on 19 Dec 2019. The registration is recorded completed; possession was promised by 3 Oct 2023.
At a glance
Project
- NameReshmanand Park
- TypeResidential / Group Housing
- Location
- Makhmalabad road
- Shantinagar
- 422003
- Pincode422003
- RERA no.P51600023553
- ReraGenie IDRG-MH-48371
Builder
- NameSejal buildcon Pvt ltd and Murlidhar A More
- Entity typeOthers
- Named personsSejal Buildcon Pvt Ltd, Murlidhar A More
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on19 Dec 2019
- Promised completion3 Oct 2023
- Revised completionNone
- Buildings1 building record
- Documents filed23 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Reshmanand Park | NA | 7 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 26 Jul 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
Reshmanand Park: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 26 Jul 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed11
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ramesh Wagh |
| Engineer | Ramesh B Wagh |
| Chartered Accountant | Aditi Saraf & co |
| Partner | Role in project |
|---|---|
| Sejal buildcon Pvt ltd and Murlidhar A More | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Oct 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Nov 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Oct 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Oct 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 20 Jul 2021
Documents filed23
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - 2019-20.pdf | 26 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - 2020-21.pdf | 26 Jul 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 20 Jul 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 20 Jul 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 20 Jul 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate.pdf | 20 Jul 2021 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf | 20 Jul 2021 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Completion Certificate.pdf | 20 Jul 2021 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Declaration of Apartment 1.pdf | 20 Jul 2021 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Declaration of Apartment 2.pdf | 20 Jul 2021 |
| Layout approvalFile: Layout original scan copy-compressed.pdf | 21 Nov 2019 |
| Copy of Layout Approval (in case of layout)File: Layout original scan copy-compressed.pdf | 21 Nov 2019 |
| PAN CardFile: Murlidhar more pan.pdf | 19 Oct 2019 |
| PAN CardFile: Sejal Buildcon pan card.pdf | 16 Oct 2019 |
| Proforma of Allotment letterFile: allotment letter 1.pdf | 15 Oct 2019 |
| Building plan approvalFile: S Plan.PDF | 5 Oct 2019 |
| Copy of the legal title reportFile: title certificate.pdf | 5 Oct 2019 |
| Details of encumbrancesFile: Non Encumbarance certificate.pdf | 5 Oct 2019 |
| Building Plan Approval / NA Order for plotted developmentFile: S Plan.PDF | 5 Oct 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate.pdf | 5 Oct 2019 |
| Declaration in FORM BFile: Affidavit.pdf | 5 Oct 2019 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A certificate.pdf | 5 Oct 2019 |
| Proforma of Allotment letterFile: Draft agreement.pdf | 5 Oct 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- All 23 filed documents as one ZIP, foldered, with a manifest
Keep Reshmanand Park on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Shantinagar
THE PLATINUM MALL BY PARKSYDE
JAIKUMAR CONSTRUCTIONS LTD
AVADH UTOPIA
DHATRAK CONSTRUWELL
ROONGTA ELEGANTE APARTMENT
ROONGTA LANDMARKS LLP
Siddhivinayak Trade Center
Dhatrak Constructions
G SQUARE
GIRI ASSOCIATE CONSTRUCTION
SADGURU HOMES
SHREE SADGURU HOMES
Builder: Sejal buildcon Pvt ltd and Murlidhar A More
Sejal buildcon Pvt ltd and Murlidhar A More has 1 registration on MahaRERA, including Reshmanand Park. Its filings disclose no earlier MahaRERA projects. Read the full track record.
Frequently asked questions
What are my rights if Reshmanand Park is delayed beyond 3 Oct 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Reshmanand Park?
The registered promoter entity is Sejal buildcon Pvt ltd and Murlidhar A More, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Reshmanand Park?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Reshmanand Park?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Reshmanand Park?
The professionals named in the filing: Architect: Ramesh Wagh; Engineer: Ramesh B Wagh; Chartered Accountant: Aditi Saraf & co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Reshmanand Park?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback