Home / Browse projects / Mumbai Suburban, Maharashtra / REDEVLOPMENT OF SUN AND MOON CHS LTD. BLDG NO. 12 AND 13

Completed No litigation declared Others project

REDEVLOPMENT OF SUN AND MOON CHS LTD. BLDG NO. 12 AND 13

By Kaustubh Construction Private Limited

RG-MH-82327 · RERA P51800007374 · Last updated on MahaRERA portal: 7 Oct 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 42 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2023Possession promisedregistration recorded completed
18 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 167 documents Report an error

REDEVLOPMENT OF SUN AND MOON CHS LTD. BLDG NO. 12 AND 13 is a Others project by Kaustubh Construction Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800007374 on 17 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2023. The completion date has moved by 42 months from the original filing.

At a glance

Project

  • NameREDEVLOPMENT OF SUN AND MOON CHS LTD. BLDG NO. 12 AND 13
  • TypeOthers
  • Location
    • Dattapada road
    • Rajendra Nagar
    • Borivali
    • Mumbai Suburban
    • 400066
  • Pincode400066
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800007374
  • ReraGenie IDRG-MH-82327

Builder

  • NameKaustubh Construction Private Limited
  • Entity typeCompany
  • CINU45200MH2007PTC167599
  • GSTIN27AADCK0673R1ZZ
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • DirectorsPRAMOD NARAYAN GAWANKAR, RADHIKA PRAMOD GAWANKAR
  • Other registrations7 more →
  • Completed4 of 8
  • Past their filed date1
  • Declared earlier projects5 →

Key dates

this monthRegisteredAug 2017First promiseDec 2019Revised toJun 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on17 Aug 2017
  • Promised completion30 Jun 2023
  • Revised completionRevised to 30 Jun 2023 (originally 31 Dec 2019)
  • Buildings2 building records
  • Documents filed167 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 12NA230000
BUILDING NO 13NA250000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 7 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.

BUILDING NO 1273%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 1391%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 7 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed141

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots141
Closed/Covered139
Open Space2
BuildingClosed/CoveredOpen SpaceTotal
BUILDING NO 1268068
BUILDING NO 1371273

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,101 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI11069.91
Proposed, not sanctioned10,560 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSubhash Road, Vile Parle E , Mumbai-400057

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCreative Consultants & Designeers (Prop. Vinayak V. Patil)
EngineerK C Shah Consultants (Prop.Kaivant C. Shah)
PartnerRole in project
Kaustubh Construction Private Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800009734Dec 2019 → Dec 2022

Reason as filed by the promoterMahaRERA has, vide its notification no. 14/2020 dated 18 May 2020 passed an order to extend the completion date automatically by 6 (six) months, with effect from 15 March 2020, in our case being 30 December 2020 earlier which now expires on 30 June 2021. Since the expiry of the previous extension date is near, we hereby request further extension on the following grounds. This is a Redevelopment Project ‘Sun-Moon CHSL’ consisting of 2 buildings namely Building no. 12 and 13 which is under the guidelines of Maharashtra Housing and Area Development Authority (MHADA), a statutory housing authority

EXT51800001779Dec 2019 → Dec 2020

Reason as filed by the promoterThe MHADA redevelopment project ‘Sun-Moon Co-op Hsg. Soc. Ltd.’ consists of 2 buildings namely Building no. 12 and 13 on sub divided plot situated at Rajendra Nagar, Datta Pada Road, Borivali (East), Mumbai - 400 066. Both the buildings are proposed for 22 floors. Currently the building is completed up to 10th floor of Building no. 12 and 15th floor of building no. 13 consuming the entire FSI availed till date under V.P. Quota. For additional floors, we had purchased the additional FSI on 26.09.2017 and received NOC for same from MHADA on 15.01.2018. The project got delayed due to: 1. Delay in

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jul 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 28 Mar 2024

Documents filed167

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 167 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form-05 FY23-24- Sun Moon.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form-05 FY23-24- Sun Moon.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form-05 FY23-24- Sun Moon.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form-05 FY23-24- Sun Moon.pdf7 Oct 2024
Disclosure of sold/ booked inventoryFile: 12.pdf5 Apr 2024
Disclosure of sold/ booked inventoryFile: 13.pdf5 Apr 2024
Architect’s Certificate on Completion of Project (Form 4)File: 12.pdf4 Apr 2024
Architect’s Certificate on Completion of Project (Form 4)File: 13.pdf4 Apr 2024
Layout approvalFile: Plan 1.pdf28 Mar 2024
Layout approvalFile: Plan 2.pdf28 Mar 2024
Layout approvalFile: Plan 3.pdf28 Mar 2024
Layout approvalFile: Plan 4.pdf28 Mar 2024
Layout approvalFile: Plan 5.pdf28 Mar 2024
Layout approvalFile: Plan 6_compressed.pdf28 Mar 2024
Layout approvalFile: Plan 7_compressed.pdf28 Mar 2024
Layout approvalFile: Plan 1.pdf28 Mar 2024
Layout approvalFile: Plan 2.pdf28 Mar 2024
Layout approvalFile: Plan 3.pdf28 Mar 2024
Layout approvalFile: Plan 4.pdf28 Mar 2024
Layout approvalFile: Plan 5.pdf28 Mar 2024
Layout approvalFile: Plan 6.pdf28 Mar 2024
Copy of Layout Approval (in case of layout)File: Plan 1.pdf28 Mar 2024
Copy of Layout Approval (in case of layout)File: Plan 2.pdf28 Mar 2024
Copy of Layout Approval (in case of layout)File: Plan 3.pdf28 Mar 2024
Copy of Layout Approval (in case of layout)File: Plan 4.pdf28 Mar 2024
Copy of Layout Approval (in case of layout)File: Plan 5.pdf28 Mar 2024
Copy of Layout Approval (in case of layout)File: Plan 6.pdf28 Mar 2024
Copy of Layout Approval (in case of layout)File: Plan 1.pdf28 Mar 2024
Copy of Layout Approval (in case of layout)File: Plan 2.pdf28 Mar 2024
Copy of Layout Approval (in case of layout)File: Plan 3.pdf28 Mar 2024
Copy of Layout Approval (in case of layout)File: Plan 4.pdf28 Mar 2024
Copy of Layout Approval (in case of layout)File: Plan 5.pdf28 Mar 2024
Copy of Layout Approval (in case of layout)File: Plan 6_compressed.pdf28 Mar 2024
Copy of Layout Approval (in case of layout)File: Plan 7_compressed.pdf28 Mar 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Letter.pdf28 Mar 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Letter.pdf28 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: SM2022-23FORM5.pdf22 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 23 Certificates of Architect (Form 1)(Mandatory for only ongoing project) (1).pdf20 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 24 Certificates of Architect (Form 1)(Mandatory for only ongoing project) (1).pdf20 Mar 2024
Certificates of CA (Form 3)File: Signed_CA Certificate- Sun Moon Dec '23.pdf25 Jan 2024
Disclosure of sold/ booked inventoryFile: SM-12.pdf23 Jan 2024
Disclosure of sold/ booked inventoryFile: SM-13.pdf23 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SM12.pdf18 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SM13.pdf18 Jan 2024
Disclosure of sold/ booked inventoryFile: SM12.pdf23 Oct 2023
Disclosure of sold/ booked inventoryFile: SM13.pdf23 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1RERA Certificate 12.pdf20 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1RERA Certificate 13.pdf20 Oct 2023
Certificates of CA (Form 3)File: 01Signed CA Certificate- Sun Moon Sept'23.pdf20 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Bldg 12.pdf22 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Bldg 13.pdf22 Jul 2023
Certificates of CA (Form 3)File: Signed CA Certificate- sun moon march'23 April.pdf9 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Bldg 12.pdf21 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Bldg 13.pdf21 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA SM Form 2 (Irfan Sir).pdf17 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A (2021-2022).pdf17 Apr 2023
Certificates of CA (Form 3)File: Signed CA Certificate.pdf4 Apr 2023
Proforma of Agreement for saleFile: Agreement for Sale-F.pdf3 Feb 2023
Status of ConveyanceFile: SM Lease Deed_compressed_compressed (1)-1-8.pdf3 Feb 2023
Status of ConveyanceFile: SM Lease Deed_compressed_compressed (1)-9-16.pdf3 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Bldg 12.pdf21 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Bldg 13.pdf21 Jan 2023
Details of encumbrancesFile: Final No Encumbrance Cert.pdf19 Jan 2023
Details of encumbrances concerned to FinanceFile: Final No Encumbrance Cert.pdf19 Jan 2023
Details of encumbrances concerned to LegalFile: Final No Encumbrance Cert.pdf19 Jan 2023
Declaration about Commencement CertificateFile: CC Declaration.pdf19 Jan 2023
Declaration about Commencement CertificateFile: CC Declaration.pdf19 Jan 2023
Declaration about Commencement CertificateFile: Full CC Declaration.pdf19 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seperate Bank Account.pdf19 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Building-12.pdf5 Nov 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Building 13.pdf5 Nov 2022
CERSAI detailsFile: Cersai Declaration.pdf25 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: KCPL SM Form -5 Mar-21.pdf14 Apr 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: 2022_0222_Final Legal Entity Letter.PDF23 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20220210_Building 12.pdf14 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20220210_Building 13.pdf14 Feb 2022
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOKED INVENTORY SM 12.PDF7 Oct 2021
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOKED INVENTORY SM 13.PDF7 Oct 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2021_0930_Part OC SM 12.PDF5 Oct 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2021_0924_ Part OC SM 13.PDF5 Oct 2021

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 delivered late1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
VANRAIP51800046638KANDIVALI EAST, Mumbai Suburban87Aug 2022OngoingJul 2026Not delivered
Redevelopment of Vasishtha Krupa Co-operative Housing Society Ltd.P51800030271Kandivali East, Mumbai Suburban88Aug 2021CompletedAug 2024Apr 2024
00--CompletedJun 2021Late, Dec 2022
RAJENDRA NAGAR SHREE GANESH CHSLRajendra Nagar Shree Ganesh CHSL Off Dattapada Road Rajendra Nagar Borivali East Mumbai 400066172-CompletedDec 2018Late, Jan 2020

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 42 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep REDEVLOPMENT OF SUN AND MOON CHS LTD. BLDG N on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Rajendra Nagar6,700+ in Mumbai Suburban

2 kmREDEVLOPMENT OF SUN AND Completed 134Lapsed / revoked 74Other 192Dot size: filed unitsN

Filed coordinates, straight-line distance. 400 registered projects within 2 km.

Builder: Kaustubh Construction Private Limited

Kaustubh Construction Private Limited has 8 registrations on MahaRERA, including REDEVLOPMENT OF RAJENDRA NAGAR - SHREE GANESH CHS LTD. and REDEVLOPMENT OF SUN AND MOON CHS LTD. BLDG NO. 12 AND 13. Its filings disclose 5 earlier MahaRERA projects: declares 1 of 4 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if REDEVLOPMENT OF SUN AND MOON CHS LTD. BLDG NO. 12 AND 13 is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of REDEVLOPMENT OF SUN AND MOON CHS LTD. BLDG NO. 12 AND 13?

The registered promoter entity is Kaustubh Construction Private Limited, a company as per the filing. Its CIN U45200MH2007PTC167599 and GSTIN 27AADCK0673R1ZZ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in REDEVLOPMENT OF SUN AND MOON CHS LTD. BLDG NO. 12 AND 13?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for REDEVLOPMENT OF SUN AND MOON CHS LTD. BLDG NO. 12 AND 13?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at REDEVLOPMENT OF SUN AND MOON CHS LTD. BLDG NO. 12 AND 13?

The professionals named in the filing: Architect: Creative Consultants & Designeers (Prop. Vinayak V. Patil); Engineer: K C Shah Consultants (Prop.Kaivant C. Shah). Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in REDEVLOPMENT OF SUN AND MOON CHS LTD. BLDG NO. 12 AND 13?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About REDEVLOPMENT OF SUN AND MOON CHS LTD. BLDG NO. 12 AND 13. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save REDEVLOPMENT OF SUN AND MOON CHS LTD. BLDG N to a free account