Home / Browse projects / Dakshina Kannada, Karnataka / REDBRICKS PALM HILLS BLOCK A
REDBRICKS PALM HILLS BLOCK A
By Redbricks Dwellings & Infraprojects Pvt Ltd
RG-KA-19015 · RERA PRM/KA/RERA/1257/334/PR/171214/001428
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
REDBRICKS PALM HILLS BLOCK A is a Mixed Development project by Redbricks Dwellings & Infraprojects Pvt Ltd in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/171214/001428 on 14 Dec 2017. Possession is promised by 30 Jun 2019. The completion date has moved by 12 months from the original filing.
At a glance
Project
- NameREDBRICKS PALM HILLS BLOCK A
- TypeMixed Development
- Location
- Mangalore
- Dakshina Kannada
- PincodeNot stated
- RERA no.PRM/KA/RERA/1257/334/PR/171214/001428
- ReraGenie IDRG-KA-19015
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on14 Dec 2017
- Promised completion30 Jun 2019
- Revised completionRevised to 30 Jun 2019 (originally 30 Jun 2018)
- Buildings1 building record
- Documents filed56 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| REDBRICKS PALM HILL BLOCK A | - | - | - | - | - | 58 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | No | Not applicable |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | Yes | - |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | No | Not applicable |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Engineer | K. ANIL HEGDE |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterShortage of Building Materials, Concrete, Jalli etc
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed56
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/171214/001428 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: 2017 Trade license v1.jpg | - |
| Architect Certificate for Work Completion Schedule till DateFile: ARCHTCT CRTFCT-COMPLTD WRK-PALMHILLS 001.jpg | - |
| Engineer Certificate for Work Completion Schedule till DateFile: ENG CRTFCT-COMPLTD WRK-PALMHLLS 001.jpg | - |
| CA Certificate for Funds UtilizationFile: CA- FUND UTILISATION- PALM HILLS.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: ARCHTCT-PENDING WRK-PALMHILLS 001.jpg | - |
| Engineer Certificate for Pending Work Completion Schedule.File: ENG CRTFCT-PENDING WRK-PALM HILLS 001.jpg | - |
| CA Certificate for Funds required for Project CompletionFile: CA- FUND REQUIRED PALM HILLS.pdf | - |
| AffidavitFile: Form B Ext Small.pdf | - |
| Latest Encumbrance CertificateFile: EC 18.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.pdf | - |
| Document 1File: Consent letter cust.pdf | - |
| Document 2File: Aug 2017 to June 2019.pdf | - |
| Document 3File: Consent letter cust New.pdf | - |
| Document 4File: Affidavit Section 18.pdf | - |
| PH Commencement Certificate | - |
| Block A Approved plan | - |
| Layout NA | - |
| INDENTURE OF SALE - PALM HILLS v1 | - |
| Palm Hills - Draft | - |
| PH Sale deed RTC Conversion | - |
| Block A Approved plan | - |
| PH Dev plan SMALL | - |
| Allotment Letter PH | - |
| PH 1 | - |
| PH NOC | - |
| SPECIFICATION | - |
| EC Palm Hills | - |
| Khata | - |
| Collaboration Agreement | - |
| Conversion Order | - |
| FIRE NOC | - |
| KSPCB | - |
| Balance Sheet 2015 - 2016File: BALANCE SHEET 2015-16.pdf | - |
| Balance Sheet 2014 - 2015File: BALANCE SHEET 2014-15.pdf | - |
| Balance Sheet 2013 - 2014File: BALANCE SHEET 2013-14.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: PROFIT AND LOSS 2015-16.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: PROFIT AND LOSS 2014-15.pdf | - |
| Audited Profit and Loss Statement 2013 - 2014File: PROFIT AND LOSS 2013-14.pdf | - |
| Director's Report 2015 - 2016File: Directors report.pdf | - |
| Director's Report 2014 - 2015File: Directors Report.pdf | - |
| Director's Report 2013 - 2014File: Directors Report 2013-14.pdf | - |
| Cash Flow Statement 2015 - 2016File: CASH FLOW 2015-16.pdf | - |
| Cash Flow Statement 2014 - 2015File: CASH FLOW 2014-15.pdf | - |
| Auditor's Report 2015 - 2016File: AUDITORS REPORT 2015-16.pdf | - |
| Auditor's Report 2014 - 2015File: AUDITOR REPORT 2014-15.pdf | - |
| Auditor's Report 2013 - 2014File: AUDITOR REPORT 2013-14.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ACKNOWLEDGEMENT 2015-16.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: ACKNOWLEDGEMENT 2014-15.pdf | - |
| Income Tax Return Acknowledgement 2013 - 2014File: ACKNOWLEDGEMENT 2013-14.pdf | - |
| Form B PH | - |
| Prospectus/BrochureFile: page-1-4(logo color).jpg | - |
| Tower Excel SheetFile: PRM_KA_RERA_1257_334_PR_171214_001428.xlsx | - |
| Occupancy CertificateFile: PALM HILLS BLOCK A OC_CC.jpeg | - |
| Completion certificateFile: PALM HILLS BLOCK A OC_CC.jpeg | - |
| Registered Agreement of SaleFile: PH Sale deed.pdf | - |
| Registered conveyance deed for an individual unitFile: Sale Deed Conveyance.pdf | - |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| Redbrick Village Phase 3 WING A | - | Completed | Aug 2017 | No date filed |
| Redbrick Village Phase 2 | - | Completed | Aug 2017 | No date filed |
| Redbrick Village Phase 1 | - | Completed | Aug 2017 | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dakshina Kannada
Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.
Keep REDBRICKS PALM HILLS BLOCK A on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dakshina Kannada620+ in Dakshina Kannada
ROHAN CITY
ROHAN CORPORATION INDIA PRIVATE LIMITED
Bearys Turning Point
Bearys Properties and Developments Private
YAMUNA SKY CITY
YAMUNA HOMES AND DESIGN PRIVATE LIMITED
The Marian Park
Marian Projects Pvt Ltd
Sai Matha Garden
Matha Developers Pvt Ltd
ROHAN MARINA ONE
ROHAN PLAZA PRIVATE LIMITED
See every Dakshina Kannada project, with the district possession charts
Builder: Redbricks Dwellings & Infraprojects Pvt Ltd
Redbricks Dwellings & Infraprojects Pvt Ltd has 2 registrations on RERA Karnataka, including REDBRICKS PALM HILLS BLOCK A and Redbrick Village Phase 3 WING B. Its filings declare 3 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.
Frequently asked questions
What are my rights if REDBRICKS PALM HILLS BLOCK A is delayed beyond 30 Jun 2019?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of REDBRICKS PALM HILLS BLOCK A?
The registered promoter entity is Redbricks Dwellings & Infraprojects Pvt Ltd, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in REDBRICKS PALM HILLS BLOCK A?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at REDBRICKS PALM HILLS BLOCK A?
The professionals named in the filing: Engineer: K. ANIL HEGDE. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in REDBRICKS PALM HILLS BLOCK A?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback