Home / Browse projects / Dakshina Kannada, Karnataka / REB PUTTUR HEIGHTS
REB PUTTUR HEIGHTS
By RAI ESTATES AND BUILDERS (PVT) LTD.
RG-KA-82590 · RERA PRM/KA/RERA/1257/335/PR/190215/002375
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 33 months
- 3 extensions taken
Clear
- No complaints on record
- Separate project account declared
Saved.
REB PUTTUR HEIGHTS is a Mixed Development project by RAI ESTATES AND BUILDERS (PVT) LTD. in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/335/PR/190215/002375 on 15 Feb 2019. Possession is promised by 30 Mar 2025. The completion date has moved by 33 months from the original filing.
At a glance
Project
- NameREB PUTTUR HEIGHTS
- TypeMixed Development
- Location
- Puttur
- Dakshina Kannada
- PincodeNot stated
- RERA no.PRM/KA/RERA/1257/335/PR/190215/002375
- ReraGenie IDRG-KA-82590
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on15 Feb 2019
- Promised completion30 Mar 2025
- Revised completionRevised to 30 Mar 2025 (originally 30 Jun 2022)
- Buildings2 building records
- Documents filed53 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | - | - | - | - | - | 70 |
| B | - | - | - | - | - | 38 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | - |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | Yes | - |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | Yes | - |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | No | Not applicable |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | Yes | - |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | K.ANIL HEGDE |
| Engineer | SURESH KUMAR |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Reason as filed by the promoterActivities undertaken by BMRDA, BBPM, BESCOM etc. leading to delay in construction
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed53
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/335/PR/190215/002375 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: co c.PDF | - |
| Project Details | - |
| Architect Certificate for Work Completion Schedule till DateFile: Arch EX1.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Eng EX5.pdf | - |
| CA Certificate for Funds UtilizationFile: ca ex-3.PDF | - |
| Architect Certificate for Pending Work Completion Schedule.File: Ex-2.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Eng - Ex 6.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: ca ex-4.PDF | - |
| AffidavitFile: affidavit.PDF | - |
| Latest Encumbrance CertificateFile: EC.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx | - |
| Document 1File: affidavit cum declaration.PDF | - |
| Document 2File: NOC .pdf | - |
| N A | - |
| Building Plan scan | - |
| singlelayout (1) | - |
| sale deed format | - |
| agreement formet | - |
| sale deed | - |
| Building Plan scan | - |
| Temp01643 (2 TO 5TH ) (1) | - |
| allotment | - |
| broucher | - |
| specification | - |
| EC | - |
| KHATHA | - |
| N A | - |
| convertion new | - |
| relinquishment | - |
| existing single layout site | - |
| Temp01645(a&b) (1) | - |
| convertion 1 | - |
| Balance Sheet 2017 - 2018File: Balance sheet 2017-18.PDF | - |
| Balance Sheet 2016 - 2017File: balance sheet 2016-17.PDF | - |
| Balance Sheet 2015 - 2016File: balance sheet 2015-16.PDF | - |
| Audited Profit and Loss Statement 2017 - 2018File: p& L 2017-18.PDF | - |
| Audited Profit and Loss Statement 2016 - 2017File: P&l 2016-17.PDF | - |
| Audited Profit and Loss Statement 2015 - 2016File: director report 2015-16.PDF | - |
| Director's Report 2017 - 2018File: director report17-18.PDF | - |
| Director's Report 2016 - 2017File: director report 2016-17.PDF | - |
| Director's Report 2015 - 2016File: director report17-18.PDF | - |
| Cash Flow Statement 2017 - 2018File: cash flow2017.PDF | - |
| Cash Flow Statement 2016 - 2017File: cash flow 2016.PDF | - |
| Auditor's Report 2017 - 2018File: Audit report 2017-18.PDF | - |
| Auditor's Report 2016 - 2017File: balance sheet 2016-17.PDF | - |
| Auditor's Report 2015 - 2016File: balance sheet 2015-16.PDF | - |
| Income Tax Return Acknowledgement 2017 - 2018File: ITR-17-18.PDF | - |
| Income Tax Return Acknowledgement 2016 - 2017File: ITR-16-17.PDF | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITR-15-16.PDF | - |
| DECLARATION | - |
| Prospectus/BrochureFile: broch (rera ).pdf | - |
| Advertisement Copy 1File: broch (rera ).pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1257_335_PR_190215_002375 (11).xlsx | - |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| REB CROWN | - | Ongoing | Dec 2019 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dakshina Kannada
Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.
Keep REB PUTTUR HEIGHTS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dakshina Kannada620+ in Dakshina Kannada
ROHAN CITY
ROHAN CORPORATION INDIA PRIVATE LIMITED
Bearys Turning Point
Bearys Properties and Developments Private
YAMUNA SKY CITY
YAMUNA HOMES AND DESIGN PRIVATE LIMITED
The Marian Park
Marian Projects Pvt Ltd
Sai Matha Garden
Matha Developers Pvt Ltd
ROHAN MARINA ONE
ROHAN PLAZA PRIVATE LIMITED
See every Dakshina Kannada project, with the district possession charts
Builder: RAI ESTATES AND BUILDERS (PVT) LTD.
RAI ESTATES AND BUILDERS (PVT) LTD) has 2 registrations on RERA Karnataka, including REB CROWN and REB PUTTUR HEIGHTS. Its filings declare 3 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.
Frequently asked questions
What are my rights if REB PUTTUR HEIGHTS is delayed beyond 30 Mar 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of REB PUTTUR HEIGHTS?
The registered promoter entity is RAI ESTATES AND BUILDERS (PVT) LTD., a company as per the filing. Its CIN U45205KA2011PTC060853 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in REB PUTTUR HEIGHTS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at REB PUTTUR HEIGHTS?
The professionals named in the filing: Architect: K.ANIL HEGDE; Engineer: SURESH KUMAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in REB PUTTUR HEIGHTS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback