ReraGenieLog inGet a buyer report

Home / Browse projects / Solapur, Maharashtra / Rastratej Atal Project

Registered No litigation declared Residential / Group Housing project

Rastratej Atal Project

By ajan homes private limited

RG-MH-03468 · RERA P52600019892 · Last updated on MahaRERA portal: 27 Apr 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 48 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Solapur registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 48 months from the original
321 of 2420Construction stages doneacross 220 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 118 documents Report an error

Rastratej Atal Project is a Residential / Group Housing project by ajan homes private limited in Solapur, Maharashtra, registered with MahaRERA as P52600019892 on 11 Mar 2019. Possession is promised by 31 Dec 2027. The completion date has moved by 48 months from the original filing.

At a glance

Project

  • NameRastratej Atal Project
  • TypeResidential / Group Housing
  • Location
    • Dahitne
    • solapur
    • Solapur (M Corp.)
    • Solapur North
    • 413002
  • Pincode413002
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52600019892
  • ReraGenie IDRG-MH-03468

Builder

  • Nameajan homes private limited
  • Entity typeCompany
  • DirectorsSaurabh V Manglekar, Deepak M Sawant

Key dates

this monthRegisteredMar 2019First promiseDec 2023Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Mar 2019
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Dec 2023)
  • Buildings220 building records
  • Documents filed118 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
92/2-A15NA30000
92/2-A16NA30000
83/1B AND 86/3B-B1NA30000
86/1B AND 86/3B-B2NA30000
86/1B AND 86/3B-B3NA30000
86/1B AND 86/3B-B4NA30000
86/1B AND 86/3B-B5NA30000
86/1B AND 86/3B-B6NA30000
86/1B AND 86/3B-B7NA30000
86/1B AND 86/3B-B8NA30000
86/1B AND 86/3B-B9NA30000
86/1B AND 86/3B-B10NA30000
86/1B AND 86/3B-B11NA30000
86/1B AND 86/3B-B12NA30000
86/1B AND 86/3B-B13NA30000
86/1B AND 86/3B-B14NA30000
86/1B AND 86/3B-B15NA30000
86/1B AND 86/3B-B16NA30000
86/1B AND 86/3B-B17NA30000
86/1B AND 86/3B-B18NA30000
86/1B AND 86/3B-B19NA30000
86/1B AND 86/3B-B20NA30000
86/1B AND 86/3B-B21NA30000
86/1B AND 86/3B-B22NA30000
86/1B AND 86/3B-B23NA30000
86/1B AND 86/3B-B24NA30000
86/1B AND 86/3B-B25NA30000
86/1B AND 86/3B-B26NA30000
L3-C18NA30000
L3-C19NA30000
L3-C20NA30000
L3-C21NA30000
L3-C22NA30000
L3-C23NA30000
L4-D1NA30000
L4-D2NA30000
L4-D3NA30000
L4-D4NA30000
L4-D5NA30000
L4-D6NA30000
L4-D7NA40000
L4-D8NA30000
L4-D9NA30000
L4-D10NA30000
L4-D11NA30000
L4-D12NA30000
L4-D13NA30000
L4-D14NA30000
L4-D15NA30000
L4-D16NA30000
L4-D17NA30000
L4-D18NA30000
L4-D19NA30000
L4-D20NA30000
L4-D21NA30000
L4-D22NA30000
92/2-A1NA30000
92/2-A2NA30000
92/2-A3NA30000
92/2-A4NA30000
92/2-A5NA30000
92/2-A6NA30000
92/2-A7NA30000
92/2-A8NA30000
92/2-A9NA30000
92/2-A10NA30000
92/2-A11NA30000
92/2-A12NA30000
92/2-A13NA30000
92/2-A14NA30000
86/1B AND 86/3B-B27NA30000
86/1B AND 86/3B-B28NA30000
86/1B AND 86/3B-B29NA30000
86/1B AND 86/3B-B30NA30000
86/1B AND 86/3B-B31NA30000
86/1B AND 86/3B-B32NA30000
86/1B AND 86/3B-B33NA30000
86/1B AND 86/3B-B34NA30000
L2-B24NA30000
L2-B25NA30000
L2-B26NA30000
L3-C1NA30000
L3-C2NA30000
L3-C3NA30000
L3-C4NA30000
L3-C5NA30000
L3-C6NA30000
L3-C7NA30000
L3-C8NA30000
L3-C9NA30000
L3-C10NA30000
L3-C11NA30000
L3-C12NA30000
L3-C13NA30000
L3-C14NA30000
L3-C15NA30000
L3-C16NA30000
L3-C17NA30000
L4-D23NA30000
L4-D24NA30000
L4-D25NA30000
L4-D26NA30000
L5-E1NA30000
L5-E2NA30000
L5-E3NA30000
L5-E4NA30000
L5-E5NA30000
L5-E6NA30000
L5-E7NA30000
L5-E8NA30000
L5-E9NA30000
L5-E10NA30000
L5-E11NA30000
L5-E12NA30000
L5-E13NA30000
L5-E14NA30000
L5-E15NA30000
L5-E16NA30000
L5-E17NA30000
L5-E18NA30000
L5-E19NA30000
L5-E20NA30000
L5-E21NA30000
L5-E22NA30000
L5-E23NA30000
L5-E24NA30000
L5-E25NA30000
L5-E26NA30000
L5-E27NA30000
L6-F1NA30000
L6-F2NA30000
L6-F3NA30000
L6-F4NA30000
L6-F5NA30000
L6-F6NA30000
L6-F7NA30000
L6-F8NA30000
L6-F9NA30000
L6-F10NA30000
L6-F11NA30000
L7-G1NA30000
L7-G2NA30000
L7-G3NA30000
L7-G4NA30000
L7-G5NA30000
L7-G6NA30000
L7-G7NA30000
L7-G8NA30000
L7-G9NA30000
L7-G10NA30000
L7-G11NA30000
L7-G12NA30000
L7-G13NA30000
L8-H1NA30000
L8-H2NA30000
L8-H3NA30000
L8-H4NA30000
L8-H5NA30000
L8-H6NA30000
L8-H7NA30000
L8-H8NA30000
L8-H9NA30000
L8-H10NA30000
L8-H11NA30000
L8-H12NA30000
L8-H13NA30000
L8-H14NA30000
L8-H15NA30000
L8-H16NA30000
L8-H17NA30000
L8-H18NA30000
L8-H19NA30000
L8-H20NA30000
L8-H21NA30000
L8-H22NA30000
L9-I1NA30000
L9-I2NA30000
L9-I3NA30000
L9-I4NA30000
L9-I5NA30000
L9-I6NA30000
L9-I7NA30000
L9-I8NA30000
L9-I9NA30000
L9-I10NA30000
L9-I11NA30000
L9-I12NA30000
L9-I13NA30000
L9-I14NA30000
L9-I15NA30000
L9-I16NA30000
L9-I17NA30000
L9-I18NA30000
L9-I19NA30000
L9-I20NA30000
L9-I21NA30000
L9-I22NA30000
L10-J1NA30000
L10-J2NA30000
L10-J3NA30000
L10-J4NA30000
L10-J5NA30000
L10-J6NA30000
L10-J7NA30000
L10-J8NA30000
L10-J9NA30000
L10-J10NA30000
L10-J11NA30000
L10-J12NA30000
L10-J13NA30000
L10-J14NA30000
L10-J15NA30000
L10-J16NA30000
L10-J17NA30000
L10-J18NA30000
L10-J19NA30000
L10-J20NA30000
L10-J21NA30000
L10-J22NA30000
L10-J23NA00000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 27 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 220 buildings; the table lists the first 20.

321 of 2420 construction stages are filed complete across 220 buildings. The stage furthest along is Podiums (if any), at 0%.

92/2-A1573%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
92/2-A1673%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
83/1B AND 86/3B-B19%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
86/1B AND 86/3B-B29%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
86/1B AND 86/3B-B39%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
86/1B AND 86/3B-B436%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
86/1B AND 86/3B-B536%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
86/1B AND 86/3B-B636%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
86/1B AND 86/3B-B736%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
86/1B AND 86/3B-B873%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
86/1B AND 86/3B-B973%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
86/1B AND 86/3B-B1073%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
86/1B AND 86/3B-B1173%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
86/1B AND 86/3B-B1273%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
86/1B AND 86/3B-B1373%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
86/1B AND 86/3B-B1473%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
86/1B AND 86/3B-B1573%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
86/1B AND 86/3B-B1673%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
86/1B AND 86/3B-B1773%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
86/1B AND 86/3B-B1873%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 27 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed5223

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots5,223
Open Space5,223
BuildingOpen SpaceTotal
92/2-A152424
92/2-A162424
83/1B AND 86/3B-B12424
86/1B AND 86/3B-B22424
86/1B AND 86/3B-B32424
86/1B AND 86/3B-B42424
86/1B AND 86/3B-B52424
86/1B AND 86/3B-B62424
86/1B AND 86/3B-B72424
86/1B AND 86/3B-B82424
86/1B AND 86/3B-B92424
86/1B AND 86/3B-B102424
86/1B AND 86/3B-B112424
86/1B AND 86/3B-B122424
86/1B AND 86/3B-B132424
86/1B AND 86/3B-B142424
86/1B AND 86/3B-B152424
86/1B AND 86/3B-B162424
86/1B AND 86/3B-B172424
86/1B AND 86/3B-B182424
86/1B AND 86/3B-B192424
86/1B AND 86/3B-B202424
86/1B AND 86/3B-B212424
86/1B AND 86/3B-B222424
86/1B AND 86/3B-B232424
86/1B AND 86/3B-B242424
86/1B AND 86/3B-B252424
86/1B AND 86/3B-B262424
L3-C182424
L3-C192424
L3-C202424
L3-C212424
L3-C222424
L3-C232424
L4-D12424
L4-D22424
L4-D32424
L4-D42424
L4-D52424
L4-D62424
L4-D72424
L4-D82424
L4-D92424
L4-D102424
L4-D112424
L4-D122424
L4-D132424
L4-D142424
L4-D152424
L4-D162424
L4-D172424
L4-D182424
L4-D192424
L4-D202424
L4-D212424
L4-D222424
92/2-A12424
92/2-A22424
92/2-A32424
92/2-A42424
92/2-A52424
92/2-A62424
92/2-A72424
92/2-A82424
92/2-A92424
92/2-A102424
92/2-A112424
92/2-A122424
92/2-A132424
92/2-A142424
86/1B AND 86/3B-B272424
86/1B AND 86/3B-B282424
86/1B AND 86/3B-B292424
86/1B AND 86/3B-B302424
86/1B AND 86/3B-B312424
86/1B AND 86/3B-B322424
86/1B AND 86/3B-B332424
86/1B AND 86/3B-B342424
L2-B242424
L2-B252424
L2-B262424
L3-C12424
L3-C22424
L3-C32424
L3-C42424
L3-C52424
L3-C62424
L3-C72424
L3-C82424
L3-C92424
L3-C102424
L3-C112424
L3-C122424
L3-C132424
L3-C141414
L3-C152424
L3-C162424
L3-C172424
L4-D232424
L4-D242424
L4-D252424
L4-D262424
L5-E12424
L5-E22424
L5-E32424
L5-E42424
L5-E52424
L5-E62424
L5-E72424
L5-E82424
L5-E92424
L5-E102424
L5-E112424
L5-E122424
L5-E132424
L5-E142424
L5-E152424
L5-E162424
L5-E172424
L5-E182424
L5-E192424
L5-E202424
L5-E212424
L5-E222424
L5-E232424
L5-E242424
L5-E252424
L5-E262424
L5-E272424
L6-F12424
L6-F22424
L6-F32424
L6-F42424
L6-F52424
L6-F62424
L6-F72424
L6-F82424
L6-F92424
L6-F102424
L6-F112424
L7-G111
L7-G22424
L7-G32424
L7-G42424
L7-G52424
L7-G62424
L7-G72424
L7-G82424
L7-G92424
L7-G102424
L7-G112424
L7-G122424
L7-G132424
L8-H12424
L8-H22424
L8-H32424
L8-H42424
L8-H52424
L8-H62424
L8-H72424
L8-H82424
L8-H92424
L8-H102424
L8-H112424
L8-H122424
L8-H132424
L8-H142424
L8-H152424
L8-H162424
L8-H172424
L8-H182424
L8-H192424
L8-H202424
L8-H212424
L8-H222424
L9-I12424
L9-I22424
L9-I32424
L9-I42424
L9-I52424
L9-I62424
L9-I72424
L9-I82424
L9-I92424
L9-I102424
L9-I112424
L9-I122424
L9-I132424
L9-I142424
L9-I152424
L9-I162424
L9-I172424
L9-I182424
L9-I192424
L9-I202424
L9-I212424
L9-I222424
L10-J12424
L10-J22424
L10-J32424
L10-J42424
L10-J52424
L10-J62424
L10-J72424
L10-J82424
L10-J92424
L10-J102424
L10-J112424
L10-J122424
L10-J132424
L10-J142424
L10-J152424
L10-J162424
L10-J172424
L10-J182424
L10-J192424
L10-J202424
L10-J212424
L10-J222424

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area261,400 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
Ajan Homes Private LimitedSolapur (M Corp.)Solapur
niyojit rastratej atal kamgar sah gruh sansthaSolapur (M Corp.)Solapur

Approvals and building plan

Sanctioning authorityMaharashtra Housing and Area Development Authority, Building Permission Cell, MHADA Mumbai
Permissible FSI191045.58
Proposed, not sanctioned32 sq m
Buildings approved220
Buildings sanctioned220

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSolapur

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSantosh Mote
EngineerShriniwas Moholkar
EngineerAnant Chaitanya Consultancy Services
Chartered AccountantDinesh Anand Tulshigar
Chartered AccountantDPMK & Associates
PartnerRole in project
Anukarati Homes Private Limited (Formerly Known as ajan homes private limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52600019076Dec 2023 → Dec 2027

Reason as filed by the promoter1) Unexpected delay in confirmation from Mathadi Kamgar and others in Solapur for availing PMAY scheme 2) Delay in geotagging and beneficiary validation as most of the beneficiaries are working in unorganized sector and couldnt be available at day time for geotagging. 3) Delay due to lockdown caused by COVID-19.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Mar 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Mar 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Mar 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed118

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 118 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: RASHTRATEJ ARCHITECTS CERTIFICATE_31 MARCH 2026.pdf27 Apr 2026
Form 2File: RASHTRATEJ ENGINEERS CERTIFICATE_31 MARCH 2026.pdf27 Apr 2026
Form 3File: RASHTRATEJ _CA CERTIFICATE_31 MARCH 2026.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: RASHTRATEJ SOLD UNSOLD_31 MARCH 2026.pdf27 Apr 2026
Form 2A (FY 2025-2026)File: RASHTRATEJ QUALITY ASSURANCE_31 MARCH 2026.pdf27 Apr 2026
Form 1File: RERA RASHTRATEJ ARCHITECTS CERTIFICATE_31 DEC 2025.pdf29 Jan 2026
Form 2File: RERA ENGG CERTIFICATE RASHTRATEJ_31 DEC 2025.pdf29 Jan 2026
Form 3File: RERA CA CERTIFICATE RASHTRATEJ_31 DEC 2025FINAL.pdf29 Jan 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD RASHTRATEJ_31 DEC 2025FINAL.pdf29 Jan 2026
Form 5 (FY 2024-2025)File: Rashtratej Atal RERA Form 5 FY 24-25.pdf24 Dec 2025
Form 1File: FORM 1 R TEJ ARCHITECT CERTIFICATE 30 SEP 2025.pdf1 Dec 2025
Form 2File: FORM 2 R TEJ ENGINEER CERTIFICATE 30 SEP 2025.pdf1 Dec 2025
Form 3File: FORM 3 R TEJ CA CERTIFICATE 30 SEP 2025.pdf1 Dec 2025
Disclosure of Sold and Booked InventoryFile: R JEJ SOLD UNSOLD INVENTORY 30 SEP 2025.pdf1 Dec 2025
Form 1File: FORM 1.pdf28 Jul 2025
Form 2File: FORM 2.pdf28 Jul 2025
Form 3File: FORM 3.pdf28 Jul 2025
Disclosure of Sold and Booked InventoryFile: RTEJ SOLD UNSOLD INVENTORY 30 JUNE 2025_11zon.pdf28 Jul 2025
Disclosure of sold/ booked inventoryFile: RASHTRATEJ SOLD UNSOLD 31 March 2025.pdf17 May 2025
Certificates of CA (Form 3)File: RASHTRATEJ _FORM 3_March 25.pdf16 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA RASHTRATEJ ARCHITECT CERTIFICATE MARCH25.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA RASHTRATEJ ATAL ENGG CERTIFICATE MARCH25.pdf19 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: RERA RASHTRATEJ ATAL ENGG CERTIFICATE QAC MARCH25.pdf19 Apr 2025
Certificates of CA (Form 3)File: RASHTRATEJ CA CERTIFICATE FORM3 DEC 2024.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RASHTRATEJ ATAL ARCHITECT CERTIFICATE 31 DEC 2024.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RASHTRATEJ ATAL ENGINEERS CERTIFICATE 31 DEC 2024.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: RASHTRATEJ ATAL SOLD UNSOLD 31 DEC 2024.pdf18 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RASHTRATEJ_FORM 5 March 24.pdf5 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RTEJ ARCHITECT CERTIFCATE JUNE 24.pdf26 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RASHTRATEJ ATAL ARCHITECTS CERTIFICATE SEP 24.pdf26 Nov 2024
Certificates of CA (Form 3)File: RASHTRATEJ CA CERTIFICATE JUNE 24.pdf26 Nov 2024
Certificates of CA (Form 3)File: RASHTRATEJ CA CERTIFICATE FORM 3 SEP 24.pdf26 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RTEJ ENGINEER CERTIFCATE JUNE 24.PDF26 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RASHTRATEJ ATAL ENGINEERS CERTIFICATE SEP 24.pdf26 Nov 2024
Disclosure of sold/ booked inventoryFile: RASHTRATEJ ATAL SOLD UNSOLD MAR 24.pdf26 Nov 2024
Disclosure of sold/ booked inventoryFile: RASHTRATEJ ATAL SOLD UNSOLD JUNE 24.pdf26 Nov 2024
Disclosure of sold/ booked inventoryFile: RASHTRATEJ ATAL SOLD UNSOLD SEP 24.pdf26 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 Atal March 2024.pdf2 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 March 2024.PDF2 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 A March 2024.PDF2 May 2024
Certificates of CA (Form 3)File: Form 3 Atal March 2024.pdf2 May 2024
Declaration in FORM BFile: Form B - SM Sir.pdf26 Mar 2024
Declaration in FORM BFile: Form B- Deepak Sawant.pdf26 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - December 2023.pdf21 Mar 2024
Certificates of CA (Form 3)File: RASHTRATEJ_FORM 3_DEC 23Updated.pdf21 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Annexure A Form 1 -December 2021.pdf11 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Annexure A Form 1 - June 22.pdf11 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Annexure A Form 1 - Sept 22.pdf11 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Annexure A Form 1 - Dec 2022.pdf11 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 March 2023.pdf11 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Annexure A Form 1 - June 23.pdf11 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Annexure A Form 1 - Sept 23.pdf11 Mar 2024
Declaration about Commencement CertificateFile: CC Declaration.pdf7 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure in other real estate Saurabh M.pdf7 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest - DMS.pdf7 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: BUILDING PERMISSION RASHTRATEJ.pdf6 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: RERA 2A 2023.PDF6 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RASHTRATJE FORM 5 MARCH 23_Bank (1).PDF6 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - March 23.PDF28 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - March 23.PDF28 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - June 2023.pdf28 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Sept 2023.pdf28 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- December 2023.PDF28 Feb 2024
Certificates of CA (Form 3)File: RASHTRATEJ_FORM 3_MAR 23 (1).PDF28 Feb 2024
Certificates of CA (Form 3)File: RASHTRATEJ_FORM 3_JUN 23 (1).PDF28 Feb 2024
Certificates of CA (Form 3)File: RASHTRATEJ_FORM 3_SEP 23.PDF28 Feb 2024
Certificates of CA (Form 3)File: Form 3 - December 2023.pdf28 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - December 2021.pdf27 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - June 2022.pdf27 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - September 2022.pdf27 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - December 2022.pdf27 Feb 2024
Certificates of CA (Form 3)File: Form 3 -June 2022.pdf27 Feb 2024
Certificates of CA (Form 3)File: Form 3 - Sept 2022.pdf27 Feb 2024
Certificates of CA (Form 3)File: Form 3 - December 2022.pdf27 Feb 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unslod Invetory - Atal.pdf10 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rashtratej_form1_2019.PDF22 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rashtratej_Form1_2020.PDF22 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rashtratej_Form1_2021.PDF22 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rashtratej_Form2_2019.PDF22 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rashtratej_Form2_2020.PDF22 Apr 2023

How this compares with Solapur

15%of Solapur projects moved their completion datethis one moved by 48 months
39%of Solapur registrations have lapsed or been cancelledthis one is on the register

Computed across the 550+ Solapur projects on ReraGenie, from their own filings.

Keep Rastratej Atal Project on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near solapur550+ in Solapur

Builder: ajan homes private limited

ajan homes private limited has 1 registration on MahaRERA, including Rastratej Atal Project. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Solapur district page.

Frequently asked questions

What are my rights if Rastratej Atal Project is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Rastratej Atal Project?

The registered promoter entity is ajan homes private limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Rastratej Atal Project?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Rastratej Atal Project?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Rastratej Atal Project?

The professionals named in the filing: Architect: Santosh Mote; Engineer: Shriniwas Moholkar; Engineer: Anant Chaitanya Consultancy Services; Chartered Accountant: Dinesh Anand Tulshigar; Chartered Accountant: DPMK & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Rastratej Atal Project?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Rastratej Atal Project. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Rastratej Atal Project to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.