Home / Browse projects / Sindhudurg, Maharashtra / RAMESHWAR COMPLEX
RAMESHWAR COMPLEX
RG-MH-28648 · RERA P52900027238 · Last updated on MahaRERA portal: 30 Sep 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 2 complaints at MahaRERA
- Completion date moved by 30 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Sindhudurg registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
RAMESHWAR COMPLEX is a Others project by RAMESHWAR CONSTRUCTIONS in Sindhudurg, Maharashtra, registered with MahaRERA as P52900027238 on 25 Nov 2020. Possession is promised by 31 Dec 2026. The completion date has moved by 30 months from the original filing. 2 complaints are on record with the regulator.
At a glance
Project
- NameRAMESHWAR COMPLEX
- TypeOthers
- Location
- DEVGAD SINDHUDURG
- BEHIND NIKHIL LUNCH HOME
- Jamsande
- Devgad
- Sindhudurg
- 416613
- Pincode416613
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52900027238
- ReraGenie IDRG-MH-28648
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on25 Nov 2020
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2024)
- Buildings5 building records
- Documents filed62 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| RAMESHWAR COMPLEX - A | NA | 2 | 0 | 0 | 0 | 0 |
| RAMESHWAR COMPLEX - B | NA | 2 | 0 | 0 | 0 | 0 |
| RAMESHWAR COMPLEX - C | NA | 2 | 0 | 0 | 0 | 0 |
| RAMESHWAR COMPLEX - D | NA | 2 | 0 | 0 | 0 | 0 |
| RAMESHWAR COMPLEX - E | NA | 2 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 30 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
15 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Internal walls, at 80%.
RAMESHWAR COMPLEX - A48%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 69% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RAMESHWAR COMPLEX - B43%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 45% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 45% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RAMESHWAR COMPLEX - C43%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 45% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 45% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RAMESHWAR COMPLEX - D38%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 20% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RAMESHWAR COMPLEX - E34%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 30 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 24% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 30% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PRASAD S KULKARNI |
| Engineer | PRASAD KULKARNI |
| Chartered Accountant | NEHALI AND CO |
| Partner | Role in project |
|---|---|
| Pukar | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to shortage of material and labour we are not able to complete project on time. Please grant us extension of 1 year till 29 June 2025.
Reason as filed by the promoterProviso of section 7(3) of the RERA Act gives the Authority the power to approve necessary extensions under reasonable circumstances, based upon the reasons and facts provided by the promoter. The difficulties we have faced have been meticulously i.e. shortage of labour and heavy rain fall. Construction industry is based on labours only and in our rural village lots of works are ongoing but labourers are short. Our labours are coming as per their wish and spare time so this is the major drawback of our project also our project is sea facing and due to heavy rain fall we could not work up to 5
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000591267 | DEVENDRA PANDURANG DAHIBAWKAR | Pukar Dhoke ( Proprietor of Rameshwar Constructions) | 22/07/2024 |
| CC12503935 | Pukar Suresh Dhoke | Devendra P Dahibawkar | 09/11/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Oct 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Oct 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 14 Nov 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 Oct 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed62
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2024-2025)File: Form 2 annexture B 310325.pdf | 30 Sep 2025 |
| Declaration and undertaking (Annexure A)File: Pdf_file_1753024889401 - converted.pdf | 20 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ANNX A.pdf | 8 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ANNX B.pdf | 8 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ANNX B.pdf | 8 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf | 8 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf | 8 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1A 8-47 PM.pdf | 2 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 8-48 PM.pdf | 2 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 8-48 PM.pdf | 2 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 20250430_234746-compressed-compressed.pdf | 30 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Pdf_file_1738336266867-compressed (1).pdf | 31 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 20250127_111304 - converted.pdf | 27 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Pdf_file_1737957459646_compressed (1).pdf | 27 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 20250127_111733 - converted.pdf | 27 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 20241031_141107_compressed.pdf | 31 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA FY 2024-25 Q2-images-0.pdf | 31 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 20241031_231121 (1).pdf | 31 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: page_1.pdf | 31 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 20241031_141705.pdf | 31 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT FORM 1.pdf | 2 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER FORM 2.pdf | 2 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: ENGINEER FORM 2A.pdf | 2 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA FORM 3.pdf | 2 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 13 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 13 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 22-23.pdf | 13 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21).pdf | 14 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21).pdf | 14 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA form 5 20-21 and 21-22.pdf | 10 Jun 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate form 1.pdf | 5 May 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate form 2.pdf | 5 May 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer's Certificate form 2A.pdf | 5 May 2022 |
| CERSAI detailsFile: Cersai declaration.pdf | 14 Apr 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1_com.pdf | 30 Oct 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_coM.pdf | 30 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM-2A.pdf | 30 Oct 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE (4) (1).pdf | 8 Sep 2021 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf | 31 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: inventory discloser.pdf | 28 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: inventory (2).pdf | 19 Jul 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf | 14 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGINEER FORM 2A.pdf | 14 Jul 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect form 1_compressed.pdf | 30 Jan 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: engineer 2A_compressed.pdf | 30 Jan 2021 |
| Building plan approvalFile: NA ORDER PUKAR.pdf | 14 Nov 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: NA ORDER PUKAR.pdf | 14 Nov 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate-rameshwar construction.pdf | 13 Nov 2020 |
| Proforma of Allotment letterFile: allotment and agreement.pdf | 13 Oct 2020 |
| Declaration in FORM BFile: FORM B_compressed.pdf | 10 Oct 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 6 Oct 2020 |
| Layout approvalFile: PLANS.pdf | 5 Oct 2020 |
| PAN CardFile: pan card.pdf | 5 Oct 2020 |
| Copy of the legal title reportFile: title report 36 pukar dhoke.pdf | 5 Oct 2020 |
| Copy of the legal title reportFile: title report 37 pukar dhoke.pdf | 5 Oct 2020 |
| Copy of the legal title reportFile: title 38 pukar dhoke.pdf | 5 Oct 2020 |
| Copy of the legal title reportFile: title report 46 pukar dhoke.pdf | 5 Oct 2020 |
| Copy of the legal title reportFile: title 47 pukar dhoke.pdf | 5 Oct 2020 |
| Copy of the legal title reportFile: title 48 pukar dhoke.pdf | 5 Oct 2020 |
| Copy of the legal title reportFile: title report 49 pukar dhoke.pdf | 5 Oct 2020 |
| Details of encumbrancesFile: NO ENCUMBRANCE.pdf | 5 Oct 2020 |
| Copy of Layout Approval (in case of layout)File: PLANS.pdf | 5 Oct 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Sindhudurg
Computed across the 530+ Sindhudurg projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 62 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep RAMESHWAR COMPLEX on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BEHIND NIKHIL LUNCH HOME530+ in Sindhudurg
Filed coordinates, straight-line distance. 7 registered projects within 2 km.
DEVDURG ELITES
OMTECH ASSOCIATES
DwarkaMai
Om Shakti Builders & Developers
MANGALMURTI ARCADE
MANGALA & ASSOCIATES
NAYSHA HEIGHTS
JAY KIRIT SANGHRAJKA
ROOPRAJ RESIDENCY
RAMESHWAR CONSTRUCTIONS
SEAGREENS
RARA REALTY
See every Sindhudurg project, with the district possession charts
Builder: RAMESHWAR CONSTRUCTIONS
RAMESHWAR CONSTRUCTIONS has 4 registrations on MahaRERA, including RAJ RESIDENCY and RAMESHWAR COMPLEX. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Sindhudurg district page.
Frequently asked questions
What are my rights if RAMESHWAR COMPLEX is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of RAMESHWAR COMPLEX?
The registered promoter entity is RAMESHWAR CONSTRUCTIONS, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in RAMESHWAR COMPLEX?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against RAMESHWAR COMPLEX?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for RAMESHWAR COMPLEX?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at RAMESHWAR COMPLEX?
The professionals named in the filing: Architect: PRASAD S KULKARNI; Engineer: PRASAD KULKARNI; Chartered Accountant: NEHALI AND CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in RAMESHWAR COMPLEX?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback