Home / Browse projects / Satara, Maharashtra / RAJMEET RESIDENCY
RAJMEET RESIDENCY
RG-MH-22465 · RERA P52700031280 · Last updated on MahaRERA portal: 20 Jul 2024
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves.
See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
RAJMEET RESIDENCY is a Residential / Group Housing project by RAJMEET DEVELOPERS in Satara, Maharashtra, registered with MahaRERA as P52700031280 on 15 Oct 2021. The registration is recorded completed; possession was promised by 25 Dec 2025.
At a glance
Project
- NameRAJMEET RESIDENCY
- TypeResidential / Group Housing
- Location
- GODOLI
- Godoli (CT)
- Satara
- 415001
- Pincode415001
- RERA no.P52700031280
- ReraGenie IDRG-MH-22465
Builder
- NameRAJMEET DEVELOPERS
- Entity typePartnership
- PartnersMANIKRAO SADASHIV JAGTAP, SWATI PRABHAKAR WALEKAR
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on15 Oct 2021
- Promised completion25 Dec 2025
- Revised completionNone
- Buildings1 building record
- Documents filed37 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| RAJMEET RESIDENCY | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 20 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
RAJMEET RESIDENCY: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 20 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed12
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MR SHANKAR KUMBHAR |
| Engineer | BHASKAR MAHAJAN |
| Chartered Accountant | MR SACHIN SWAMI |
| Partner | Role in project |
|---|---|
| RAJMEET DEVELOPERS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Oct 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 Oct 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 Oct 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 20 Jul 2024
Documents filed37
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.PDF | 20 Jul 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: oc.pdf | 20 Jul 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4.PDF | 20 Jul 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: SOCIETY FORMATION CERTIFICATE.PDF | 13 Jul 2024 |
| Status of ConveyanceFile: CONVENCE DEED.PDF | 13 Jul 2024 |
| Details of encumbrances concerned to FinanceFile: DEC LEGAL.pdf | 12 May 2023 |
| Details of encumbrances concerned to LegalFile: DEC LEGAL.pdf | 12 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH.pdf | 12 May 2023 |
| CERSAI detailsFile: DEC CERSAI.PDF | 12 May 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DEC INT.pdf | 12 May 2023 |
| Proforma of Allotment letterFile: ALLOTMENT.pdf | 12 May 2023 |
| Proforma of Agreement for saleFile: model form of agreement ind BLANK.pdf | 12 May 2023 |
| Deviation Report with respect to Allotment letterFile: DEC DEVI ALLOTMENT.PDF | 12 May 2023 |
| Deviation Report with respect to model copy of AgreementFile: DEC DEVI AGREEMENT.PDF | 12 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch.pdf | 18 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca.pdf | 18 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch sept.pdf | 20 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca sept.pdf | 20 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5.pdf | 20 Feb 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK ACCOUNT.PDF | 21 Sep 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch.pdf | 7 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf | 7 Jul 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA F.pdf | 7 Jul 2022 |
| Building plan approvalFile: PLAN F.pdf | 9 Oct 2021 |
| Layout approvalFile: plan.pdf | 9 Oct 2021 |
| Copy of Layout Approval (in case of layout)File: plan.pdf | 9 Oct 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: PLAN F.pdf | 9 Oct 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 9 Oct 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA NEW.pdf | 9 Oct 2021 |
| PAN CardFile: PAN.pdf | 3 Oct 2021 |
| Copy of the legal title reportFile: SEARCH 1.pdf | 3 Oct 2021 |
| Copy of the legal title reportFile: LEGAL TITLE FINAL.pdf | 3 Oct 2021 |
| Details of encumbrancesFile: ENCCU.pdf | 3 Oct 2021 |
| Declaration about Commencement CertificateFile: DEC.pdf | 3 Oct 2021 |
| Declaration in FORM BFile: FORM B FINAL.pdf | 3 Oct 2021 |
| Proforma of Allotment letterFile: ALLOTMENT.pdf | 3 Oct 2021 |
| Proforma of Allotment letterFile: rera agriment.pdf | 3 Oct 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Satara
Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- All 37 filed documents as one ZIP, foldered, with a manifest
Keep RAJMEET RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near GODOLI1,100+ in Satara
PRADHAN MANTRI AWAS YOJANA SATARA PHASE I
SATARA MUNICIPAL COUNCIL SATARA
LANDMARK TOWERS
KANGRALKAR INFRASTRUCTURE
Bhuvi Commercia
LAXMI NARAYAN INDUSTRIES
SAMARVEER SKYLINE
SHRI MANGALMURTI BUILDERS
Mathura
Balkrishna Pandurang Jadhav
BAJIRAO EMPIRE
SHREE SHESHACHAL DEVELOPERS
See every Satara project, with the district possession charts
Builder: RAJMEET DEVELOPERS
RAJMEET DEVELOPERS has 1 registration on MahaRERA, including RAJMEET RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.
Frequently asked questions
What are my rights if RAJMEET RESIDENCY is delayed beyond 25 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of RAJMEET RESIDENCY?
The registered promoter entity is RAJMEET DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in RAJMEET RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for RAJMEET RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at RAJMEET RESIDENCY?
The professionals named in the filing: Architect: MR SHANKAR KUMBHAR; Engineer: BHASKAR MAHAJAN; Chartered Accountant: MR SACHIN SWAMI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in RAJMEET RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback