Home / Browse projects / Raigarh, Maharashtra / Rajhans Evana Phase 1

Registered No litigation declared Residential / Group Housing project

Rajhans Evana Phase 1

By Joydale Infracon LLP

RG-MH-19436 · RERA P52000077719 · Last updated on MahaRERA portal: 19 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 4 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Apr 2030Possession promisedmoved 4 months from the original
231 of 283Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 126 documents Report an error

Rajhans Evana Phase 1 is a Residential / Group Housing project by Joydale Infracon LLP in Raigarh, Maharashtra, registered with MahaRERA as P52000077719 on 23 Oct 2024. Possession is promised by 30 Apr 2030. The completion date has moved by 4 months from the original filing. 52 of the 283 units on this registration are recorded sold or booked.

At a glance

Project

  • NameRajhans Evana Phase 1
  • TypeResidential / Group Housing
  • Location
    • Khopoli Pali Road
    • Village Sangade
    • Sangade
    • Khalapur
    • Raigarh
    • 410203
  • Pincode410203
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000077719
  • ReraGenie IDRG-MH-19436

Builder

  • NameJoydale Infracon LLP
  • Entity typePartnership
  • PartnersJayeshkumar Desai, Shivlal Jain

Key dates

this monthRegisteredOct 2024First promiseDec 2029Revised toApr 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Oct 2024
  • Promised completion30 Apr 2030
  • Revised completionRevised to 30 Apr 2030 (originally 31 Dec 2029)
  • Buildings283 building records
  • Documents filed126 files

Current status

18%52 of 283 units booked

Figures as on 19 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Plot No 18 Stella C18NA22101
Plot No 19 Stella C19NA22101
Plot No 20 Stella C20NA22101
Plot No 21 Stella C21NA22101
Plot No 22 Stella C22NA22101
Plot No 23 Stella C23NA22101
Plot No 24 Stella C24NA22101
Plot No 25 Stella C25NA22101
Plot No 26 Stella C26NA22101
Plot No 27 Stella C27NA22101
Plot No 28 Stella C28NA22101
Plot No 29 Stella C29NA22101
Plot No 30 Stella C30NA22101
Plot No 37 Stella C31NA22101
Plot No 38 Stella C32NA22101
Plot No 39 Stella C33NA22101
Plot No 40 Stella C34NA22101
Plot No 41 Stella C35NA22101
Plot No 42 Stella C36NA22101
Plot No 43 Stella C37NA22101
Plot No 44 Stella C38NA22101
Plot No 45 Stella C39NA22101
Plot No 94 Stella C64NA22101
Plot No 95 Stella C65NA22101
Plot No 96 Stella C66NA22101
Plot No 97 Stella C67NA22101
Plot No 98 Stella C68NA22101
Plot No 99 Stella C69NA22101
Plot No 100 Stella C70NA22101
Plot No 101 Stella C71NA22101
Plot No 102 Stella C72NA22101
Plot No 103 Stella C73NA22101
Plot No 104 Stella C74NA22101
Plot No 105 Stella C75NA22101
Plot No 106 Stella C76NA22101
Plot No 107 Stella C77NA22101
Plot No 108 Stella C78NA22101
Plot No 109 Stella C79NA22101
Plot No 110 Stella C80NA22101
Plot No 111 Stella C81NA22101
Plot No 112 Stella C82NA22101
Plot No 113 Stella C83NA22101
Plot No 114 Stella B45NA22101
Plot No 179 Stella C90NA22101
Plot No 180 Stella C89NA22101
Plot No 181 Stella C88NA22101
Plot No 182 Stella C87NA22101
Plot No 183 Stella C86NA22101
Plot No 184 Stella C85NA22101
Plot No 185 Stella C84NA22101
Plot No 256 Stella B7NA22101
Plot No 257 Stella B6NA22101
Plot No 263 Stella B100NA22101
Plot No 31 Mastero B27NA33101
Plot No 32 Mastero B28NA33101
Plot No 33 Mastero B29NA33101
Plot No 34 Mastero B30NA33101
Plot No 35 Mastero B31NA33101
Plot No 36 Mastero B32NA33101
Plot No 49 Mastero B15NA33101
Plot No 50 Mastero B16NA33101
Plot No 51 Mastero B17NA33101
Plot No 52 Mastero B18NA33101
Plot No 118 Mastero B49NA33101
Plot No 119 Mastero B50NA33101
Plot No 120 Mastero B51NA33101
Plot No 121 Mastero B52NA33101
Plot No 122 Mastero B53NA33101
Plot No 123 Mastero B54NA33101
Plot No 124 Mastero B55NA33101
Plot No 125 Mastero B56NA33101
Plot No 126 Mastero B57NA33101
Plot No 127 Mastero B58NA33101
Plot No 128 Mastero B59NA33101
Plot No 129 Mastero B60NA33101
Plot No 130 Mastero B61NA33101
Plot No 131 Mastero B62NA33101
Plot No 132 Mastero B63NA33101
Plot No 133 Mastero B64NA33101
Plot No 134 Mastero B65NA33101
Plot No 135 Mastero B66NA33101
Plot No 136 Mastero B67NA33101
Plot No 137 Mastero B68NA33101
Plot No 138 Mastero B69NA33101
Plot No 140 Mastero B71NA33101
Plot No 141 Mastero B72NA33101
Plot No 142 Mastero B73NA33101
Plot No 143 Mastero B74NA33101
Plot No 144 Mastero B75NA33101
Plot No 145 Mastero B76NA33101
Plot No 146 Mastero B77NA33101
Plot No 147 Mastero B78NA33101
Plot No 148 Mastero 79NA33101
Plot No 149 Mastero B80NA33101
Plot No 150 Mastero B81NA33101
Plot No 151 Mastero B82NA33101
Plot No 152 Mastero B83NA33101
Plot No 153 Mastero B84NA33101
Plot No 154 Mastero B85NA33101
Plot No 172 Mastero B98NA33101
Plot No 173 Mastero B99NA33101
Plot No 186 Mastero B86NA33101
Plot No 187 Mastero B87NA33101
Plot No 155 Stella C96NA22101
Plot No 156 Stella C97NA22101
Plot No 157 Stella C98NA22101
Plot No 158 Stella C99NA22101
Plot No 159 Stella C100NA22101
Plot No 160 Stella C101NA22101
Plot No 161 Stella C102NA22101
Plot No 162 Stella C103NA22101
Plot No 163 Stella C104NA22101
Plot No 164 Stella C105NA22101
Plot No 165 Stella C106NA22101
Plot No 166 Stella C107NA22101
Plot No 167 Stella C108NA22101
Plot No 168 Stella C109NA22101
Plot No 169 Stella C110NA22101
Plot No 170 Stella C111NA22101
Plot No 171 Stella C112NA22101
Plot No 174 Stella C95NA22101
Plot No 175 Stella C94NA22101
Plot No 176 Stella C93NA22101
Plot No 177 Stella C92NA22101
Plot No 178 Stella C91NA22101
Plot No 188 Mastero B88NA33101
Plot No 189 Mastero B89NA33101
Plot No 190 Mastero B90NA33101
Plot No 191 Mastero B91NA33101
Plot No 192 Mastero B92NA33101
Plot No 193 Mastero B93NA33101
Plot No 194 Mastero B94NA33101
Plot No 195 Mastero B95NA33101
Plot No 196 Mastero B96NA33101
Plot No 197 Mastero B97NA33101
Plot No 250 Mastero B12NA33101
Plot No 251 Mastero B13NA33101
Plot No 152 Mastero B11NA33101
Plot No 253 Mastero B10NA33101
Plot No 254 Mastero B9NA33101
Plot No 255 Mastero B8NA33101
Plot No 258 Mastero B104NA33101
Plot No 259 Mastero B105NA33101
Plot No 260 Mastero B106NA33101
Plot No 261 Mastero B14NA33101
Plot No 262 Mastero B101NA33101
Plot No 212 Icon A42NA33101
Plot No 213 Icon A41NA33101
Plot No 214 Icon A40NA33101
Plot No 215 Icon A39NA33101
Plot No 216 Icon A38NA33101
Plot No 217 Icon A37NA33101
Plot No 218 Icon A36NA33101
Plot No 219 Icon A35NA33101
Plot No 220 Icon A34NA33101
Plot No 221 Icon A33NA33101
Plot No 222 Icon A32NA33101
Plot No 223 Icon A31NA33101
Plot No 224 Icon A30NA33101
Plot No 225 Icon A29NA33101
Plot No 226 Icon A28NA33101
Plot No 227 Icon A27NA33101
Plot No 228 Icon A26NA33101
Plot No 229 Icon A25NA33101
Plot No 230 Icon A24NA33101
Plot No 231 Icon A23NA33101
Plot No 232 Icon A22NA33101
Plot No 233 Icon A21NA44101
Plot No 234 Icon A20NA33101
Plot No 235 Icon A19NA33101
Plot No 236 Icon A18NA33101
Plot No 237 Icon A17NA33101
Plot No 238 Icon A16NA33101
Plot No 239 Icon A15NA33101
Plot No 240 Icon A14NA33101
PLot No 241 Icon A65NA33101
Plot No 242 Icon A66NA33101
Plot No 243 Icon A63NA33101
Plot No 244 Icon A62NA33101
Plot No 245 Icon A61NA33101
Plot No 246 Icon A60NA33101
Plot No 247 Icon A59NA33101
Plot No 248 Icon A58NA33101
Plot No 249 Icon A57NA33101
Plot No 271 Icon A6NA33101
Plot No 272 Icon A5NA33101
Plot No 273 Icon A4NA33101
Plot No 274 Icon A3NA33101
Plot No 275 Icon A2NA33101
Plot No 276 Icon A1NA33101
Plot No 277 Icon A7NA33101
Plot No 278 Icon A8NA33101
Plot No 279 Icon A9NA33101
Plot No 280 Icon A10NA33101
Plot No 281 Icon A11NA33101
Plot No 282 Icon A12NA33101
Plot No 283 Icon A13NA33101
Plot No 139 Stella B70NA22101
Plot No 1-Stella C1NA22101
Plot No 2 Stella C2NA22101
Plot No 3 Stella C3NA22101
Plot No 4 Stella C4NA22101
Plot No 5 Stella C5NA22101
Plot No 6 Stella C6NA22101
Plot No 7 Stella C7NA22101
Plot No 8 Stella C8NA22101
Plot No 9 Stella C9NA22101
Plot No 10 Stella C10NA22101
Plot No 11 Stella 11NA22101
Plot No 12 Stella C12NA22101
Plot No 13 Stella C13NA22101
Plot No 14 Stella C14NA22101
Plot No 15 Stella C15NA22101
Plot No 16 Stella C16NA22101
Plot No 17 Stella C17NA22101
Plot No 46 Stella C40NA22101
Plot No 47 Stella C41NA22101
Plot No 48 Stella C42NA22101
Plot No 73 Stella C43NA22101
Plot No 74 Stella C44NA22101
Plot No 75 Stella C45NA22101
Plot No 76 Stella C46NA22101
Plot No 77 Stella C47NA22101
Plot No 78 Stella C48NA22101
Plot No 79 Stella C49NA22101
Plot No 80 Stella C50NA22101
Plot No 81 Stella C51NA22101
Plot No 82 Stella C52NA22101
Plot No 83 Stella C53NA22101
Plot No 84 Stella C54NA22101
Plot No 85 Stella C55NA22101
Plot No 86 Stella C56NA22101
Plot No 87 Stella C57NA22101
Plot No 88 Stella C58NA22101
Plot No 89 Stella C59NA22101
Plot No 90 Stella C60NA22101
Plot No 91 Stella C61NA22101
Plot No 92 Stella C62NA22101
Plot No 93 Stella C63NA22101
Plot No 264 Mastero B102NA33101
Plot No 265 Mastero B103NA33101
Plot No 266 Mastero B5NA33101
Plot No 267 Mastero B4NA33101
Plot No 268 Mastero B3NA33101
Plot No 269 Mastero B2NA33101
Plot No 270 Mastero B1NA33101
Plot No 198 Icon A56NA33101
Plot No 199 Icon A55NA33101
Plot No 200 Icon A54NA33101
Plot No 201 Icon A53NA33101
Plot No 202 Icon A52NA33101
Plot No 203 Icon A51NA33101
Plot No 204 Icon A50NA33101
Plot No 205 Icon A49NA33101
Plot No 206 Icon A48NA33101
Plot No 207 Icon A47NA33101
Plot No 208 Icon A46NA33101
Plot No 209 Icon A45NA33101
Plot No 210 Icon A44NA33101
Plot No 211 Icon A43NA33101
Plot No 53 Mastero B19NA33101
Plot No 54 Mastero B20NA33101
Plot No 55 Mastero B21NA33101
Plot No 56 Mastero B22NA33101
Plot No 57 Mastero B23NA33101
Plot No 58 Mastero B24NA33101
Plot No 59 Mastero B25NA33101
Plot No 60 Mastero B26NA33101
Plot No 61 Mastero B33NA33101
Plot No 62 Mastero B34NA33101
Plot No 63 Mastero B35NA33101
Plot No 64 Mastero B36NA33101
Plot No 65 Mastero B37NA33101
Plot No 66 Mastero B38NA33101
Plot No 67 Mastero B39NA33101
Plot No 68 Mastero B40NA33101
Plot No 69 Mastero B41NA33101
Plot No 70 Mastero B42NA33101
Plot No 71 Mastero B43NA33101
Plot No 72 Mastero B44NA33101
Plot No 115 Mastero B46NA33101
Plot No 116 Mastero B47NA33101
Plot No 117 Mastero B48NA33101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 19 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 283 buildings; the table lists the first 20.

Plot No 18 Stella C18Not stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Plot No 19 Stella C19Not stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Plot No 20 Stella C20Not stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Plot No 21 Stella C21Not stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Plot No 22 Stella C22Not stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Plot No 23 Stella C23Not stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Plot No 24 Stella C24Not stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Plot No 25 Stella C25Not stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Plot No 26 Stella C26Not stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Plot No 27 Stella C27Not stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Plot No 28 Stella C28Not stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Plot No 29 Stella C29Not stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Plot No 30 Stella C30Not stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Plot No 37 Stella C31Not stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Plot No 38 Stella C32Not stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Plot No 39 Stella C33Not stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Plot No 40 Stella C34Not stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Plot No 41 Stella C35Not stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Plot No 42 Stella C36Not stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Plot No 43 Stella C37Not stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 19 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed532

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots532
Closed/Covered250
Open Space282
BuildingClosed/CoveredOpen SpaceTotal
Plot No 18 Stella C18011
Plot No 19 Stella C19011
Plot No 20 Stella C20011
Plot No 21 Stella C21011
Plot No 22 Stella C22011
Plot No 23 Stella C23011
Plot No 24 Stella C24011
Plot No 25 Stella C25011
Plot No 26 Stella C26011
Plot No 27 Stella C27011
Plot No 28 Stella C28011
Plot No 29 Stella C29011
Plot No 30 Stella C30011
Plot No 37 Stella C31011
Plot No 38 Stella C32011
Plot No 39 Stella C33011
Plot No 40 Stella C34112
Plot No 41 Stella C35112
Plot No 42 Stella C36112
Plot No 43 Stella C37112
Plot No 44 Stella C38112
Plot No 45 Stella C39112
Plot No 94 Stella C64112
Plot No 95 Stella C65112
Plot No 96 Stella C66112
Plot No 97 Stella C67112
Plot No 98 Stella C68112
Plot No 99 Stella C69112
Plot No 100 Stella C70112
Plot No 101 Stella C71112
Plot No 102 Stella C72112
Plot No 103 Stella C73112
Plot No 104 Stella C74112
Plot No 105 Stella C75112
Plot No 106 Stella C76112
Plot No 107 Stella C77112
Plot No 108 Stella C78112
Plot No 109 Stella C79112
Plot No 110 Stella C80112
Plot No 111 Stella C81112
Plot No 112 Stella C82112
Plot No 113 Stella C83112
Plot No 114 Stella B45112
Plot No 179 Stella C90112
Plot No 180 Stella C89112
Plot No 181 Stella C88112
Plot No 182 Stella C87112
Plot No 183 Stella C86112
Plot No 184 Stella C85112
Plot No 185 Stella C84112
Plot No 256 Stella B7112
Plot No 257 Stella B6112
Plot No 263 Stella B100112
Plot No 31 Mastero B27112
Plot No 32 Mastero B28112
Plot No 33 Mastero B29112
Plot No 34 Mastero B30112
Plot No 35 Mastero B31112
Plot No 36 Mastero B32112
Plot No 49 Mastero B15112
Plot No 50 Mastero B16112
Plot No 51 Mastero B17112
Plot No 52 Mastero B18112
Plot No 118 Mastero B49112
Plot No 119 Mastero B50112
Plot No 120 Mastero B51112
Plot No 121 Mastero B52112
Plot No 122 Mastero B53112
Plot No 123 Mastero B54112
Plot No 124 Mastero B55112
Plot No 125 Mastero B56112
Plot No 126 Mastero B57112
Plot No 127 Mastero B58112
Plot No 128 Mastero B59112
Plot No 129 Mastero B60112
Plot No 130 Mastero B61112
Plot No 131 Mastero B62112
Plot No 132 Mastero B63112
Plot No 133 Mastero B64112
Plot No 134 Mastero B65112
Plot No 135 Mastero B66112
Plot No 136 Mastero B67112
Plot No 137 Mastero B68112
Plot No 138 Mastero B69112
Plot No 140 Mastero B71112
Plot No 141 Mastero B72112
Plot No 142 Mastero B73112
Plot No 143 Mastero B74112
Plot No 144 Mastero B75112
Plot No 145 Mastero B76112
Plot No 146 Mastero B77112
Plot No 147 Mastero B78112
Plot No 148 Mastero 79112
Plot No 149 Mastero B80112
Plot No 150 Mastero B81112
Plot No 151 Mastero B82112
Plot No 152 Mastero B83112
Plot No 153 Mastero B84112
Plot No 154 Mastero B85112
Plot No 172 Mastero B98112
Plot No 173 Mastero B99112
Plot No 186 Mastero B86112
Plot No 187 Mastero B87112
Plot No 155 Stella C96112
Plot No 156 Stella C97112
Plot No 157 Stella C98112
Plot No 158 Stella C99112
Plot No 159 Stella C100112
Plot No 160 Stella C101112
Plot No 161 Stella C102112
Plot No 162 Stella C103112
Plot No 163 Stella C104112
Plot No 164 Stella C105112
Plot No 165 Stella C106112
Plot No 166 Stella C107112
Plot No 167 Stella C108112
Plot No 168 Stella C109112
Plot No 169 Stella C110112
Plot No 170 Stella C111112
Plot No 171 Stella C112112
Plot No 174 Stella C95112
Plot No 175 Stella C94112
Plot No 176 Stella C93112
Plot No 177 Stella C92112
Plot No 178 Stella C91112
Plot No 188 Mastero B88112
Plot No 189 Mastero B89112
Plot No 190 Mastero B90112
Plot No 191 Mastero B91112
Plot No 192 Mastero B92112
Plot No 193 Mastero B93112
Plot No 194 Mastero B94112
Plot No 195 Mastero B95112
Plot No 196 Mastero B96112
Plot No 197 Mastero B97112
Plot No 250 Mastero B12112
Plot No 251 Mastero B13112
Plot No 152 Mastero B11112
Plot No 253 Mastero B10112
Plot No 254 Mastero B9112
Plot No 255 Mastero B8112
Plot No 258 Mastero B104112
Plot No 259 Mastero B105112
Plot No 260 Mastero B106112
Plot No 261 Mastero B14112
Plot No 262 Mastero B101112
Plot No 212 Icon A42112
Plot No 213 Icon A41112
Plot No 214 Icon A40112
Plot No 215 Icon A39112
Plot No 216 Icon A38112
Plot No 217 Icon A37112
Plot No 218 Icon A36112
Plot No 219 Icon A35112
Plot No 220 Icon A34112
Plot No 221 Icon A33112
Plot No 222 Icon A32112
Plot No 223 Icon A31112
Plot No 224 Icon A30112
Plot No 225 Icon A29112
Plot No 226 Icon A28112
Plot No 227 Icon A27112
Plot No 228 Icon A26112
Plot No 229 Icon A25112
Plot No 230 Icon A24112
Plot No 231 Icon A23112
Plot No 232 Icon A22112
Plot No 233 Icon A21112
Plot No 234 Icon A20112
Plot No 235 Icon A19112
Plot No 236 Icon A18112
Plot No 237 Icon A17112
Plot No 238 Icon A16112
Plot No 239 Icon A15112
Plot No 240 Icon A14112
PLot No 241 Icon A65112
Plot No 242 Icon A66112
Plot No 243 Icon A63112
Plot No 244 Icon A62112
Plot No 245 Icon A61112
Plot No 246 Icon A60112
Plot No 247 Icon A59112
Plot No 248 Icon A58112
Plot No 249 Icon A57112
Plot No 271 Icon A6112
Plot No 272 Icon A5112
Plot No 273 Icon A4112
Plot No 274 Icon A3112
Plot No 275 Icon A2112
Plot No 276 Icon A1112
Plot No 277 Icon A7112
Plot No 278 Icon A8112
Plot No 279 Icon A9112
Plot No 280 Icon A10112
Plot No 281 Icon A11112
Plot No 282 Icon A12112
Plot No 283 Icon A13112
Plot No 139 Stella B70112
Plot No 1-Stella C1011
Plot No 2 Stella C2011
Plot No 3 Stella C3011
Plot No 4 Stella C4011
Plot No 5 Stella C5011
Plot No 6 Stella C6011
Plot No 7 Stella C7011
Plot No 8 Stella C8011
Plot No 9 Stella C9011
Plot No 10 Stella C10011
Plot No 11 Stella 11011
Plot No 12 Stella C12011
Plot No 13 Stella C13011
Plot No 14 Stella C14011
Plot No 15 Stella C15011
Plot No 16 Stella C16011
Plot No 17 Stella C17011
Plot No 46 Stella C40112
Plot No 47 Stella C41112
Plot No 48 Stella C42112
Plot No 73 Stella C43112
Plot No 74 Stella C44112
Plot No 75 Stella C45112
Plot No 76 Stella C46112
Plot No 77 Stella C47112
Plot No 78 Stella C48112
Plot No 79 Stella C49112
Plot No 80 Stella C50112
Plot No 81 Stella C51112
Plot No 82 Stella C52112
Plot No 83 Stella C53112
Plot No 84 Stella C54112
Plot No 85 Stella C55112
Plot No 86 Stella C56112
Plot No 87 Stella C57112
Plot No 88 Stella C58112
Plot No 89 Stella C59112
Plot No 90 Stella C60112
Plot No 91 Stella C61112
Plot No 92 Stella C62112
Plot No 93 Stella C63112
Plot No 264 Mastero B102112
Plot No 265 Mastero B103112
Plot No 266 Mastero B5112
Plot No 267 Mastero B4112
Plot No 268 Mastero B3112
Plot No 269 Mastero B2112
Plot No 270 Mastero B1112
Plot No 198 Icon A56112
Plot No 199 Icon A55112
Plot No 200 Icon A54112
Plot No 201 Icon A53112
Plot No 202 Icon A52112
Plot No 203 Icon A51112
Plot No 204 Icon A50112
Plot No 205 Icon A49101
Plot No 206 Icon A48112
Plot No 207 Icon A47112
Plot No 208 Icon A46112
Plot No 209 Icon A45112
Plot No 210 Icon A44112
Plot No 211 Icon A43112
Plot No 53 Mastero B19112
Plot No 54 Mastero B20112
Plot No 55 Mastero B21112
Plot No 56 Mastero B22112
Plot No 57 Mastero B23112
Plot No 58 Mastero B24112
Plot No 59 Mastero B25112
Plot No 60 Mastero B26112
Plot No 61 Mastero B33112
Plot No 62 Mastero B34112
Plot No 63 Mastero B35112
Plot No 64 Mastero B36112
Plot No 65 Mastero B37112
Plot No 66 Mastero B38112
Plot No 67 Mastero B39112
Plot No 68 Mastero B40112
Plot No 69 Mastero B41112
Plot No 70 Mastero B42112
Plot No 71 Mastero B43112
Plot No 72 Mastero B44112
Plot No 115 Mastero B46112
Plot No 116 Mastero B47112
Plot No 117 Mastero B48112

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area155,910 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on22 Dec 2025

Approvals and building plan

Sanctioning authorityRaigad Collector
Permissible FSI96259.97
Proposed, not sanctioned96,260 sq m
Buildings approved283
Buildings sanctioned283

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI Bank Ltd., Shantivan Apartment, Lambe Hanuman Road, Varachha, Surat.395006

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAbhijit S Mohite
EngineerRanade & Associates
EngineerVatsal Goshaliya
Chartered AccountantRA Jilhewar & Co
Chartered AccountantK A SANGHAVI AND CO LLP
PartnerRole in project
Joydale Infracon LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P52000077719/WarDec 2029 → Apr 2030

Reason as filed by the promoterNA

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Oct 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Oct 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Oct 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2030

Documents filed126

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 126 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: Form 5 March 2025.pdf19 Sep 2026
Form 2A (FY 2024-2025)File: FORM2A-2025.pdf18 Sep 2026
Form 2A (FY 2025-2026)File: FORM2A-2026.pdf18 Sep 2026
Form 2File: Engineer Certificate 31122024.pdf8 Sep 2026
Form 3File: CA Certificate Form 3 31122024.pdf8 Sep 2026
Disclosure of Sold and Booked InventoryFile: Inventory Details Joydale 31122024.pdf8 Sep 2026
Form 1File: Arhitect Certificate - 31122024.pdf8 Sep 2026
Withdrawal Update Form 1File: FORM 1 30062026.pdf21 Jul 2026
Withdrawal Update Form 2File: FORM 2 30062026.pdf21 Jul 2026
Withdrawal Update Form 3File: Form 3 30062026.pdf21 Jul 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate March 2026.pdf14 May 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate March 2026.pdf14 May 2026
Withdrawal Update Form 3File: Form 3 CA Certificate March 2026.pdf14 May 2026
Withdrawal Update Form 1File: Architects Certificate FORM 1.pdf4 Feb 2026
Withdrawal Update Form 1File: Architects Certificate FORM 1.pdf4 Feb 2026
Withdrawal Update Form 2File: FORM 2 - Engineer Certificate 31122025 Evana.pdf4 Feb 2026
Withdrawal Update Form 2File: FORM 2 - Engineer Certificate 31122025 Evana.pdf4 Feb 2026
Withdrawal Update Form 3File: CA Certificate P1 Form 3 31122025.pdf4 Feb 2026
Withdrawal Update Form 3File: CA Certificate P1 Form 3 31122025.pdf4 Feb 2026
Form 1File: Architect Certificate PG-1.pdf17 Dec 2025
Form 2File: 20251467_FORM 2 - Engineer Certificate 30092025 Evana.pdf17 Dec 2025
Form 3File: CA Certificate - Sept 2025.pdf17 Dec 2025
Disclosure of Sold and Booked InventoryFile: Inventory Details Joydale 30092025.pdf17 Dec 2025
OthersFile: Architect Certificate PG-2.pdf17 Dec 2025
Form 1File: Form 1 Joydale June 2025 P1.pdf13 Oct 2025
OthersFile: Form 1 Joydale June 2025 P2.pdf13 Oct 2025
Form 2File: Form 2 Joydale June 2025.pdf13 Oct 2025
Form 3File: Form 3 Joydale June 2025.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: Inventory Details Joydale 30 June 2025.pdf13 Oct 2025
Form 2File: Form 2 - Engineer Certificate March 2025.pdf22 Jul 2025
Form 3File: Form 3 - CA Certificate March 2025.pdf22 Jul 2025
Form 1File: Architecte Certificate_compressed-1.pdf22 Jul 2025
OthersFile: Architecte Certificate_compressed-2.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Inventory Certificate March 2025.pdf22 Jul 2025
Self-declaration of Quarterly ProgressFile: Architecte Certificate_compressed-3.pdf22 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arhitect Certificate-10.pdf1 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arhitect Certificate-12.pdf1 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arhitect Certificate-11.pdf1 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arhitect Certificate-8.pdf1 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arhitect Certificate-7.pdf1 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arhitect Certificate-6.pdf1 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arhitect Certificate-5.pdf1 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arhitect Certificate-4.pdf1 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arhitect Certificate-3.pdf1 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arhitect Certificate-2.pdf1 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arhitect Certificate-1.pdf1 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arhitect Certificate-9.pdf1 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 31122024.pdf27 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3 31122024.pdf22 Mar 2025
Disclosure of sold/ booked inventoryFile: Inventory Details Joydale 31122024.pdf22 Mar 2025
Copy of the legal title reportFile: Title COmpressed P1.pdf18 Oct 2024
Copy of the legal title reportFile: Part 4.pdf18 Oct 2024
Copy of the legal title reportFile: Part 2.pdf18 Oct 2024
Copy of the legal title reportFile: Part 3.pdf18 Oct 2024
Other - TechnicalFile: 1 B - 16.pdf18 Oct 2024
Other - TechnicalFile: 1 A - 16.pdf18 Oct 2024
Proforma of Allotment letterFile: Allotment Letter - Draft.pdf17 Oct 2024
Other - TechnicalFile: Annexure A.pdf17 Oct 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report Agreement.pdf17 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: Segment 001 of NA order dated 04 September 2024 - Final - Copy_compressed12.pdf16 Oct 2024
Declaration about Commencement CertificateFile: Format D Declaration about Commencement Certificate_compressed.pdf16 Oct 2024
Other - TechnicalFile: Declaration of Total Sanctioned BUA of Project Rajhans Evana Phase 1.pdf15 Oct 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Declaration Concerned To Legal.pdf9 Oct 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Declaration Concerned To Finance.pdf9 Oct 2024
Details of encumbrances concerned to FinanceFile: Disclosure for secured unsecured finance availed for the project.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: REARA Architect Form 1 - P5 09102024.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: REARA Architect Form 1 - P4 09102024.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: REARA Architect Form 1 - P3 09102024.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: REARA Architect Form 1 - P2 09102024.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: REARA Architect Form 1 - P1 09102024.pdf9 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Joydale 09102024.pdf9 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_P1 09102024.pdf9 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_P2 09102024.pdf9 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_P3 09102024.pdf9 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_P4 09102024.pdf9 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_P5 09102024.pdf9 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf9 Oct 2024
CERSAI detailsFile: Encumbrance Delaration concerned to Finance.pdf9 Oct 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: RERA Evana - Format A (Developer Letter).pdf9 Oct 2024
Details of encumbrances concerned to LegalFile: Encumbrance Declaration Concerned To Legal.pdf9 Oct 2024

How this compares with Raigarh

18%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 4 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Rajhans Evana Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Village Sangade5,900+ in Raigarh

2 kmRajhans Evana Phase 1Other 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: Joydale Infracon LLP

Joydale Infracon LLP has 1 registration on MahaRERA, including Rajhans Evana Phase 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Rajhans Evana Phase 1 is delayed beyond 30 Apr 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Rajhans Evana Phase 1?

The registered promoter entity is Joydale Infracon LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Rajhans Evana Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Rajhans Evana Phase 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Rajhans Evana Phase 1?

The professionals named in the filing: Architect: Abhijit S Mohite; Engineer: Ranade & Associates; Engineer: Vatsal Goshaliya; Chartered Accountant: RA Jilhewar & Co; Chartered Accountant: K A SANGHAVI AND CO LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Rajhans Evana Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Rajhans Evana Phase 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Rajhans Evana Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.