ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Rajal - Veer Abhimanyu CHS Ltd

Completed No litigation declared Residential / Group Housing project

Rajal - Veer Abhimanyu CHS Ltd

By Nisar Properties Pvt. Ltd.

RG-MH-08773 · RERA P51800006097 · Last updated on MahaRERA portal: 23 Oct 2020

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2023Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
2Complaints at MahaRERAon this registration
Jump to the 17 documents Report an error

Rajal - Veer Abhimanyu CHS Ltd is a Residential / Group Housing project by Nisar Properties Pvt. Ltd. in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800006097 on 14 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2023. 2 complaints are on record with the regulator.

At a glance

Project

  • NameRajal - Veer Abhimanyu CHS Ltd
  • TypeResidential / Group Housing
  • Location
    • Shimpoli Road
    • Borivali West
    • Borivali
    • Mumbai Suburban
    • 400092
  • Pincode400092
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800006097
  • ReraGenie IDRG-MH-08773

Builder

  • NameNisar Properties Pvt. Ltd.
  • Entity typeCompany
  • CINU70100MH2008PTC184074
  • GSTIN27AACCN8181A1ZL
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • Managing DirectorChetan Nisar
  • DirectorKalpana Nisar
  • Other registrations6 more →
  • Completed3 of 7
  • No longer live2 lapsed, de-registered or revoked

Key dates

this monthRegisteredAug 2017PromisedJun 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on14 Aug 2017
  • Promised completion30 Jun 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed17 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RajalNA190000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Oct 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Rajal: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 23 Oct 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed21

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots21
Closed/Covered19
Open Space2

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area527 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Veer Abhimanyu CHS Ltd.BorivaliMumbai Suburban

Approvals and building plan

Permissible FSI1699.94
Proposed, not sanctioned1,277 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSaket, Gulmohar Road, Juhu, Vile Parle West, Mumbai - 400049

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSandeep Kangutkar
PartnerRole in project
Nisar Properties Private Limited-

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000396210PRAKASH VITTHAL SAMELNisar Properties Pvt. Ltd.14/06/2023
CC12603948Nisar Properties Private LimitedPrakash V Samel25/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 23 Oct 2020

Documents filed17

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate.pdf23 Oct 2020
Status of ConveyanceFile: Property Card.pdf23 Oct 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Annual Audit Report of Statutory CA (Form 5) (FY 2017-18).pdf19 Dec 2019
Building plan approvalFile: IOD Veer Abhimanyu Compressed.pdf10 Aug 2017
Building plan approvalFile: IOD Plans Veer Abhimanyu Compressed.pdf10 Aug 2017
Building Plan Approval (IOD)File: IOD Veer Abhimanyu Compressed.pdf10 Aug 2017
Building Plan Approval (IOD)File: IOD Plans Veer Abhimanyu Compressed.pdf10 Aug 2017
Declaration in FORM BFile: Form B New Veer Abhimanyu.pdf10 Aug 2017
Layout approvalFile: Layout Plan Veer Abhimanyu.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Plan Veer Abhimanyu.pdf28 Jul 2017
Copy of the legal title reportFile: Title Certificate Veer Abhimanyu.pdf26 Jul 2017
Details of encumbrancesFile: Encumbrance Certificate Veer Abhimanyu.pdf26 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC Veer Abhimanyu.pdf26 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Veer Abhimanyu.pdf26 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Veer Abhimanyu.pdf26 Jul 2017
Certificates of CA (Form 3)File: CA Certificate Veer Abhimanyu.pdf26 Jul 2017
Proforma of Allotment letterFile: MOFA RERA Draft Veer Abhimanyu.PDF26 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Rajal - Veer Abhimanyu CHS Ltd on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Borivali West6,700+ in Mumbai Suburban

2 kmRajal - Veer Abhimanyu CCompleted 134Lapsed / revoked 76Other 212Dot size: filed unitsN

Filed coordinates, straight-line distance. 422 registered projects within 2 km.

Builder: Nisar Properties Pvt. Ltd.

Nisar Properties Pvt. Ltd. has 7 registrations on MahaRERA, including Rajal and Rajal - Veer Abhimanyu CHS Ltd. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Rajal - Veer Abhimanyu CHS Ltd is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Rajal - Veer Abhimanyu CHS Ltd?

The registered promoter entity is Nisar Properties Pvt. Ltd., a company as per the filing. Its CIN U70100MH2008PTC184074 and GSTIN 27AACCN8181A1ZL can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Rajal - Veer Abhimanyu CHS Ltd?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Rajal - Veer Abhimanyu CHS Ltd?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Rajal - Veer Abhimanyu CHS Ltd?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Rajal - Veer Abhimanyu CHS Ltd?

The professionals named in the filing: Architect: Sandeep Kangutkar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Rajal - Veer Abhimanyu CHS Ltd?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Rajal - Veer Abhimanyu CHS Ltd. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Rajal - Veer Abhimanyu CHS Ltd to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.