RAJ APOORVAM

By CRYSTAL LANDMARK

RG-MH-66020 · RERA P52100016102 · Last updated on MahaRERA portal: 20 Aug 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • 3 complaints at MahaRERA
  • Completion date moved by 52 months
  • 2 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Apr 2028Possession promisedmoved 52 months from the original
7 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 40%
103 of 131Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 182 documents Report an error

RAJ APOORVAM is a Others project by CRYSTAL LANDMARK in Pune, Maharashtra, registered with MahaRERA as P52100016102 on 17 Apr 2018. Possession is promised by 30 Apr 2028. The completion date has moved by 52 months from the original filing. 28 of the 131 units on this registration are recorded sold or booked, and 7 of 33 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameRAJ APOORVAM
  • TypeOthers
  • Location
    • TALEGAON SHIKRAPUR
    • NEAR MEDANKARWADI
    • Chakan (CT)
    • Khed
    • Pune
    • 410501
  • Pincode410501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100016102
  • ReraGenie IDRG-MH-66020

Builder

  • NameCRYSTAL LANDMARK
  • Entity typePartnership
  • PartnersPRAVINBHAI DAYABHAI VEKARIYA, AKSHAYKUMAR VASANTBHAI GANGANI, VIMAL HARSHUKHRAI BOTADRA, Ravi GUNVANTRAY VARU, NARENDRABHAI MOHANBHAI SAKHIYA, MAHENDRA NANDLAL PATEL, Rajan Dineshbhai Hadwani
  • PartnerATULBHAI KHIMJIBHAI MARU

Key dates

this monthRegisteredApr 2018First promiseDec 2023Revised toApr 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Apr 2018
  • Promised completion30 Apr 2028
  • Revised completionRevised to 30 Apr 2028 (originally 30 Dec 2023)
  • Buildings3 building records
  • Documents filed182 files

Current status

21%28 of 131 units booked
9.8%Work done, per cost certificate

Figures as on 20 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA13111090109
COMMERCIALNA2201212
BNA3110010

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 20 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 40%.

A30%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure25%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
COMMERCIAL40%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed96

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots96
Closed/Covered96
BuildingClosed/CoveredTotal
A3232
COMMERCIAL3232
B3232

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area10,250 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on12 May 2025

Approvals and building plan

Sanctioning authorityTown Planning and Valuation Department, Pune
Permissible FSI9973.51
Proposed, not sanctioned5,883 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCHATRABHUJ CHS LTD, SECTOR 21, PLOT 61, KHARGHAR
Estimated costRs 16.75 cr
Cost incurredRs 1.64 cr
Work done9.79%
BuildingWingEstimatedIncurred
ANARs 13.90 crRs 1.50 cr
BNARs 1.20 cr-
COMMERCIALNARs 90.00 lakhRs 13.50 lakh
-NARs 75.00 lakh-

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDinesh Khedkar
ArchitectPrime Architects
EngineerManav Varu
EngineerGaurav Bhise
Chartered AccountantKPGA and Associates
Chartered AccountantJain Pratik and Co.
Chartered AccountantVijay Sawant and Co
PartnerRole in project
CRYSTAL LANDMARK-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P52100016102/WarDec 2023 → Apr 2028

Reason as filed by the promoterNA

EA12052501078Dec 2023 → Dec 2027

Reason as filed by the promoterDue to Covid there was a long stoppage of work on site. The project is situated in Chakan Industrial area. Post Covid many of the industries closed down and there was no demand for real estate. The feasibility of the project came into difficulties and the partners could not arrange financial closure of the project. The partners have now made adequate financial arrangements to ensure that the project can be completed successfully.

Litigation declared1

CaseCourtStatus
557/2022/2022Civil Judge Senior Division Court, KhedOngoing

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC12502584MUHAMMAD ARZAAN YADAVCRYSTAL LANDMARK27/07/2025
CC12600317Nagesh Haribhau FulavareCRYSTAL LANDMARK16/01/2026
CC12606293Ganpat Singh Mithu Singh ChouhanCRYSTAL LANDMARK28/09/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Mar 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Apr 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Apr 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2028

Documents filed182

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 182 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 June 2026.pdf20 Aug 2026
Withdrawal Update Form 2File: Form 2 June 2026.pdf20 Aug 2026
Withdrawal Update Form 3File: Form 3 June 2026- Crystal.pdf20 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A Mar 26.pdf20 Aug 2026
Form 5 (FY 2024-2025)File: Form 5 24-25 Crystal .pdf20 Aug 2026
Form 5 (FY 2025-2026)File: Form 5 Mar 26.pdf20 Aug 2026
Withdrawal Update Form 1File: Form 1 June 2024.pdf8 Jul 2026
Withdrawal Update Form 1File: Form 1 Sep 25.pdf8 Jul 2026
Withdrawal Update Form 1File: Form 1 Dec 25.pdf8 Jul 2026
Withdrawal Update Form 1File: Form 1 March 26.pdf8 Jul 2026
Withdrawal Update Form 2File: Form 2 June 2024.pdf8 Jul 2026
Withdrawal Update Form 2File: Form 2 -Sep 25.pdf8 Jul 2026
Withdrawal Update Form 2File: Form 2- Dec 25.pdf8 Jul 2026
Withdrawal Update Form 2File: Form 2- Mar 26.pdf8 Jul 2026
Withdrawal Update Form 3File: Form 3 June 25 Crystal.pdf8 Jul 2026
Withdrawal Update Form 3File: Crystal Form 3 Sep 25.pdf8 Jul 2026
Withdrawal Update Form 3File: Crystal Landmark Form 3 Dec 25.pdf8 Jul 2026
Withdrawal Update Form 3File: Crystal Landmark - Form 3 Mar-26 signed.pdf8 Jul 2026
Form 1File: Form 1 March 2024.pdf6 Jul 2026
Form 2File: Form 2 March 2024.pdf6 Jul 2026
Form 3File: Form 3 March 24.pdf6 Jul 2026
Disclosure of Sold and Booked InventoryFile: Diclosure of Sold_Booked Inventory March 2024.pdf6 Jul 2026
Form 3File: Form 3 June 2024.pdf6 Jul 2026
Form 1File: Form 1 June 2024.pdf6 Jul 2026
Form 2File: Form 2 June 2024.pdf6 Jul 2026
Disclosure of Sold and Booked InventoryFile: Diclosure of Sold_Booked Inventory June 2024.pdf6 Jul 2026
Form 1File: Form 1 Sep 2024.pdf6 Jul 2026
Form 2File: Form 2 Sep 2024.pdf6 Jul 2026
Form 3File: Form 3 sep 2024.pdf6 Jul 2026
Disclosure of Sold and Booked InventoryFile: Diclosure of Sold_Booked Inventory Sep 2024.pdf6 Jul 2026
Form 1File: Form 1 December 2024.pdf6 Jul 2026
Form 2File: Form 2 December 2024.pdf6 Jul 2026
Form 3File: Form 3 Dec 24.pdf6 Jul 2026
Disclosure of Sold and Booked InventoryFile: Diclosure of Sold_Booked Inventory Dec 2024.pdf6 Jul 2026
Disclosure of Sold and Booked InventoryFile: Diclosure of Sold_Booked Inventory Mar 25.pdf6 Jul 2026
Form 1File: Form 1 Mar 25.pdf6 Jul 2026
Form 2File: Form 2- Mar 25.pdf6 Jul 2026
Form 3File: Form 3 March 25 Crystal.pdf6 Jul 2026
Withdrawal Update Form 1File: Form 1 June 2024.pdf6 Jul 2026
Withdrawal Update Form 2File: Form 2 June 2024.pdf6 Jul 2026
Withdrawal Update Form 3File: Form 3 June 2024.pdf6 Jul 2026
Form 1File: Form 1 June 2019.pdf30 Jul 2025
Form 2File: Form 2 jun 19.pdf30 Jul 2025
Form 3File: Form 3 June 2019.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Diclosure of Sold_Booked Inventory June 2019.pdf30 Jul 2025
Form 1File: Form 1 Sep 2019.pdf30 Jul 2025
Form 2File: Form 2 sep 19.pdf30 Jul 2025
Form 3File: Form 3 Sep 2019.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Diclosure of Sold_Booked Inventory Sep 2019.pdf30 Jul 2025
Form 1File: Form 1 December 2019.pdf30 Jul 2025
Form 2File: Form 2 dec19.pdf30 Jul 2025
Form 3File: Form 3 Dec 19.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Diclosure of Sold_Booked Inventory Dec 2019.pdf30 Jul 2025
Form 1File: Form 1 March 2020.pdf30 Jul 2025
Form 2File: Form 2 mar 19.pdf30 Jul 2025
Form 3File: Form 3 March 2019.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Diclosure of Sold_Booked Inventory March 2019.pdf30 Jul 2025
Form 1File: Form 1 June 2020.pdf30 Jul 2025
Form 2File: Form 2 June 2020.pdf30 Jul 2025
Form 3File: Form 3 June 2020.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Diclosure of Sold_Booked Inventory June 2020.pdf30 Jul 2025
Form 1File: Form 1 Sep 2020.pdf30 Jul 2025
Form 2File: Form 2 Sep 2020.pdf30 Jul 2025
Form 3File: Form 3 sep 2020.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Diclosure of Sold_Booked Inventory Sep 2020.pdf30 Jul 2025
Form 1File: Crystal_Form 1 - Dec 20.pdf30 Jul 2025
Form 2File: Form 2 December 2020.pdf30 Jul 2025
Form 3File: Form 3 Dec 2020.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Diclosure of Sold_Booked Inventory Dec 2020.pdf30 Jul 2025
Form 1File: Form 1 March 2021.pdf30 Jul 2025
Form 2File: Form 2 March 2021.pdf30 Jul 2025
Form 3File: Form 3 March 2021.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Diclosure of Sold_Booked Inventory March 2021.pdf30 Jul 2025
Form 1File: Form 1 June 2021.pdf30 Jul 2025
Form 2File: Form 2 June 2021.pdf30 Jul 2025
Form 3File: Form 3 June 2021.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Diclosure of Sold_Booked Inventory June 2021.pdf30 Jul 2025
Form 1File: Form 1 Sep 2021.pdf30 Jul 2025
Form 2File: Form 2 Sep 2021.pdf30 Jul 2025
Form 3File: Form 3 sep 2021.pdf30 Jul 2025

How this compares with Pune

21%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 52 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep RAJ APOORVAM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR MEDANKARWADI13,700+ in Pune

2 kmRAJ APOORVAMCompleted 14Lapsed / revoked 20Other 27Dot size: filed unitsN

Filed coordinates, straight-line distance. 61 registered projects within 2 km.

Builder: CRYSTAL LANDMARK

CRYSTAL LANDMARK has 1 registration on MahaRERA, including RAJ APOORVAM. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if RAJ APOORVAM is delayed beyond 30 Apr 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RAJ APOORVAM?

The registered promoter entity is CRYSTAL LANDMARK, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RAJ APOORVAM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against RAJ APOORVAM?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for RAJ APOORVAM?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RAJ APOORVAM?

The professionals named in the filing: Architect: Dinesh Khedkar; Architect: Prime Architects; Engineer: Manav Varu; Engineer: Gaurav Bhise; Chartered Accountant: KPGA and Associates; Chartered Accountant: Jain Pratik and Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RAJ APOORVAM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RAJ APOORVAM. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RAJ APOORVAM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.