Home / Browse projects / Nagpur, Maharashtra / Rachana Sahira Wing A
Rachana Sahira Wing A
By Rachana construction Co. (Nagpur) Pvt. Ltd.
RG-MH-00751 · RERA P50500001307 · Last updated on MahaRERA portal: 27 May 2021
Source: official MahaRERA filing
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Rachana Sahira Wing A is a Residential / Group Housing project by Rachana construction Co. (Nagpur) Pvt. Ltd. in Nagpur, Maharashtra, registered with MahaRERA as P50500001307 on 27 Jul 2017. The registration is recorded completed; possession was promised by 31 Oct 2019. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameRachana Sahira Wing A
- TypeResidential / Group Housing
- Location
- Nagpur (M Corp.)
- Nagpur (Urban)
- Nagpur
- 440005
- Pincode440005
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50500001307
- ReraGenie IDRG-MH-00751
Builder
- NameRachana construction Co. (Nagpur) Pvt. Ltd.
- Entity typeCompany
- CINU45201MH2001PTC131790
- GSTIN27AACCR1666C1ZL
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- Managing DirectorShishir Shanakarrao Diote
- DirectorsRonak Shishir Diote, Nilima Shishir Diote
- Other registrations6 more →
- Completed5 of 7
- Declared earlier projects3 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on27 Jul 2017
- Promised completion31 Oct 2019
- Revised completionRevised to 31 Oct 2019 (originally 31 Oct 2018)
- Buildings1 building record
- Documents filed38 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing A | NA | 12 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 27 May 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
Wing A: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 27 May 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 10% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 10% |
Parking filed42
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ulhas Mude & Associates |
| Engineer | P S Patankar & Associates |
| Partner | Role in project |
|---|---|
| Rachana construction Co. (Nagpur) Pvt. Ltd. | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterScheme Completed and application made for Occupancy Certificate which would be received after the concerned competent authority completing all formalities
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC004000000020124 | SANGITA SINHA | Shishir Shankar Rao Diote | 17/09/2019 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 22 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 22 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 27 May 2021
Documents filed38
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC SAHIRA A WING.pdf | 27 May 2021 |
| OtherFile: Pvt Ltd Certificate.pdf | 22 Jan 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch SA 311218.pdf | 18 Oct 2019 |
| Certificates of CA (Form 3)File: CA SA 311218_compressed.pdf | 18 Oct 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng SA 311218.pdf | 17 Oct 2019 |
| Certificates of CA (Form 5)File: sahira A Form 5.pdf | 30 Sep 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sahira A Form 1 301218.pdf | 14 Sep 2019 |
| Certificates of Architect (Form 4)File: ARCHITECHS CERTIFICATE PR 4.pdf | 30 Jul 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Sahira A March 18.pdf | 2 Feb 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Sahira A Jun 18.pdf | 2 Feb 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Sahira A Sept 18.pdf | 2 Feb 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Sahira A March 18.pdf | 2 Feb 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Sahira A Jun 18.pdf | 2 Feb 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Sahira A Sept 18.pdf | 2 Feb 2019 |
| Certificates of CA (Form 3)File: Sahira A CA March 18.pdf | 2 Feb 2019 |
| Certificates of CA (Form 3)File: Sahira CA Jun 18.pdf | 2 Feb 2019 |
| Certificates of CA (Form 3)File: Sahira A CA Sept 18.pdf | 2 Feb 2019 |
| Certificates of CA (Form 5)File: sahira.pdf | 29 Sep 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: commencement certificate.pdf | 29 Mar 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch.pdf | 17 Mar 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer.pdf | 17 Mar 2018 |
| Certificates of CA (Form 3)File: ca.pdf | 17 Mar 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT'S CERTIFICATE (2).pdf | 7 Dec 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate.pdf | 7 Dec 2017 |
| Certificates of CA (Form 3)File: CHARTER ACCOUNT CERTIFICATE.pdf | 7 Dec 2017 |
| Layout approvalFile: layout sanction plan.pdf | 22 Jul 2017 |
| Building plan approvalFile: sanction plan.pdf | 22 Jul 2017 |
| Copy of the legal title reportFile: legal title report.pdf | 22 Jul 2017 |
| Details of encumbrancesFile: encumbrances certificate.pdf | 22 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: layout sanction plan.pdf | 22 Jul 2017 |
| Building Plan Approval (IOD)File: sanction plan.pdf | 22 Jul 2017 |
| Declaration in FORM BFile: 4B.pdf | 22 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certiifcate.pdf | 22 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate.pdf | 22 Jul 2017 |
| Certificates of CA (Form 3)File: CA certiifcate.pdf | 22 Jul 2017 |
| Proforma of Allotment letterFile: letter of allot and undertaking.pdf | 22 Jul 2017 |
| OtherFile: additional declaration.pdf | 22 Jul 2017 |
| PAN CardFile: RCCNPL PAN CARD.pdf | 20 Jul 2017 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Rachana Nitya | Rachana Nitya mouza bhamti landon street road nagpur 440022 | 46 | Completed | Sep 2017 | Jun 2017 |
| Rachana Meghsparsh | Rachana Meghsparsh mouza bhamti london street road Nagpur 440022 | 146 | Completed | Mar 2016 | Late, Apr 2016 |
| Rachana Madhukosh B | Rachana Madhukosh Apartment Plot no 1 to 5 Patil Layout Indraprastha nagar Jaitala Road nagpur 440022 | 24 | Completed | May 2014 | Late, Jun 2014 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 6 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 38 filed documents as one ZIP, foldered, with a manifest
Keep Rachana Sahira Wing A on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Nagpur (M Corp.)2,800+ in Nagpur
Filed coordinates, straight-line distance. 19 registered projects within 2 km.
One Rise
MAHALAXMI INFRAPROJECTS PRIVATE LIMITED
Construction of 288 EWS & 36 LIG Flats at Belt
MHADA(Nagpur Board)
FORTUNE SIRI
Radiance Erectors Pvt. Ltd
Harmony Spaces
VAS ASSOCIATES AND BUILDERS
PIONEER TAMARIND COURT- PLOT NO.3
Tarangan Infraventures Private Limited
SHIVTHIRTH NAGAR 3
ASHISH KALODE & OTHERS
See every Nagpur project, with the district possession charts
Builder: Rachana construction Co. (Nagpur) Pvt. Ltd.
Rachana construction Co. (Nagpur) Pvt. Ltd. has 7 registrations on MahaRERA, including Rachana 24 Carat and Rachana Sahira Wing A. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What are my rights if Rachana Sahira Wing A is delayed beyond 31 Oct 2019?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Rachana Sahira Wing A?
The registered promoter entity is Rachana construction Co. (Nagpur) Pvt. Ltd., a company as per the filing. Its CIN U45201MH2001PTC131790 and GSTIN 27AACCR1666C1ZL can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Rachana Sahira Wing A?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Rachana Sahira Wing A?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Rachana Sahira Wing A?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Rachana Sahira Wing A?
The professionals named in the filing: Architect: Ulhas Mude & Associates; Engineer: P S Patankar & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Rachana Sahira Wing A?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback