Home / Browse projects / Nagpur, Maharashtra / RACHANA EKAA
RACHANA EKAA
By Rachana construction Co. (Nagpur) Pvt. Ltd.
RG-MH-04065 · RERA P50500034119 · Last updated on MahaRERA portal: 4 Apr 2025
Source: official MahaRERA filing
Red flags
- Completion date moved by 10 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
RACHANA EKAA is a Residential / Group Housing project by Rachana construction Co. (Nagpur) Pvt. Ltd. in Nagpur, Maharashtra, registered with MahaRERA as P50500034119 on 24 Mar 2022. The registration is recorded completed; possession was promised by 31 Jan 2025. The completion date has moved by 10 months from the original filing.
At a glance
Project
- NameRACHANA EKAA
- TypeResidential / Group Housing
- Location
- MOUZA CHINCHBHUVAN
- Nagpur (M Corp.)
- Nagpur (Urban)
- Nagpur
- 440010
- Pincode440010
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50500034119
- ReraGenie IDRG-MH-04065
Builder
- NameRachana construction Co. (Nagpur) Pvt. Ltd.
- Entity typeCompany
- CINU45201MH2001PTC131790
- GSTIN27AACCR1666C1ZL
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- Managing DirectorShishir Shanakarrao Diote
- DirectorsRonak Shishir Diote, Nilima Shishir Diote
- Other registrations6 more →
- Completed5 of 7
- Declared earlier projects3 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on24 Mar 2022
- Promised completion31 Jan 2025
- Revised completionRevised to 31 Jan 2025 (originally 31 Mar 2024)
- Buildings1 building record
- Documents filed92 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| RACHANA EKAA | NA | 11 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 4 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.
RACHANA EKAA: 90% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 4 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed199
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MR ULHAS MUDE |
| Engineer | MR PRANIL KACHOLE |
| Chartered Accountant | MR S W BHAGAT |
| Chartered Accountant | Urja Shekhar Jain |
| Partner | Role in project |
|---|---|
| Rachana construction Co. (Nagpur) Pvt. Ltd. | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Heavy Rainfall And Issue In Civil Contractorship
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 23 Mar 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Mar 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 17 Mar 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 4 Apr 2025
Documents filed92
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archirtect Certificate EKAA March 25.pdf | 4 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 4 Architect Completion Certificate- Ekaa March 25.pdf | 4 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: OC EKAA.pdf | 4 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate Ekaa March 2025.pdf | 4 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Ekaa March 25.pdf | 4 Apr 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC EKAA.pdf | 4 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Ekaa March 25.pdf | 4 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer quality certificate Ekaa March 25.pdf | 4 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA EKAA Dec 2024 final.pdf | 11 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Ekaa Dec 2024 final.pdf | 11 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Ekaa Dec 2024.pdf | 10 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect EKAA Dec 2024.pdf | 9 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA EKAA Dec 2024.pdf | 9 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: EKAA sold unsold Dec 2024.pdf | 9 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: quality Ekaa Dec 2024.pdf | 9 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: EKAA sold unsold Sep 2024.pdf | 22 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: EKAA ARchitect Certificate September 2024.pdf | 19 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA EKAA Sep 2024.pdf | 19 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 EKAA Engineer Sep 24.pdf | 19 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A EKAA quality.pdf | 19 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: EKAA Architect Certificate June 2024.pdf | 6 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ekaa Form 2 Engineer Certificate June 2024.pdf | 6 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Ekaa Form 2A Quality Engineer Certificate June 2024.pdf | 6 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Ekaa Sold unsold report June 2024.pdf | 6 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: EKAA CA CERTIFICATE June 2024.pdf | 6 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: EKAA FORM 1 MARCH 2024.pdf | 9 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EKAA FORM 2 MARCH 2024.pdf | 9 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form - 2A EKAA MARCH 2024.pdf | 9 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: EKAA SOLD REPORT MARCH 2024.pdf | 9 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: EKAA FORM 3 MARCH 2024_compressed.pdf | 9 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: c a certificate ekaa.pdf | 8 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: rachana ekaa 2 (1).pdf | 4 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf | 26 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2A.pdf | 26 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: ssd exp006.pdf | 27 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ekka Arch certificate Sept 23_compressed.pdf | 10 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch form 1 Ekaa Sept 2023.pdf | 9 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rachana Ekka.pdf | 9 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EKAA FORM 2_compressed.pdf | 7 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ekaa form 2A.pdf | 7 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: ekaa sold.pdf | 7 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ssd exp082_compressed.pdf | 7 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: EKAA FORM 1.pdf | 27 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EKAA FORM 2.pdf | 27 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: EKAA FORM 2 A.pdf | 27 Jun 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD REPOT EKAA.pdf | 27 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: EKAA FORM 3_compressed.pdf | 27 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Rachana Ekaa.pdf | 11 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: EKAA FORM 1 MARCH 2023.pdf | 7 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Cert.pdf | 7 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: EKAA FORM 2A MARCH 2023 (1).pdf | 7 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: EKAA FORM 2A MARCH 2023 (1).pdf | 7 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: EKAA SOLD REPORT MARCH 2023.pdf | 7 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert.pdf | 6 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 EKAA.pdf | 14 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1EKAA ARCHITECT CERTIFICATE.pdf | 12 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 EKKA ENGINEER CERTIFICATE.pdf | 12 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A EKAA.pdf | 12 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSER OF SOOD EKAA.pdf | 12 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EKKA.pdf | 12 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: EKAA SOLD UNSOLD INVNTERY.pdf | 19 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch form 1 30092022 (1).pdf | 17 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT'S CERTIFICATE EKAA.pdf | 17 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE EKAA_compressed.pdf | 17 Oct 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITY ASSURANCE CERTIFICATE EKAA.pdf | 17 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE RERA EKAA_compressed.pdf | 17 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch form 1 30062022.pdf | 8 Jul 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineers certificate_compressed.pdf | 8 Jul 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: quality assurance certificat.pdf | 8 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: disscloser ekka.pdf | 8 Jul 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate rachana pvt ltd_compressed.pdf | 8 Jul 2022 |
| Copy of the legal title reportFile: LEGAL TITAL REPORT_compressed.pdf | 23 Mar 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: fORM 2 - rACHANAA EKAA.pdf | 19 Mar 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200232824278_For_Asset_Based_Search_19_03_2022_13_57_48_924.pdf | 19 Mar 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE_compressed.pdf | 19 Mar 2022 |
| Layout approvalFile: 1 (1)_compressed_compressed.pdf | 17 Mar 2022 |
| Layout approvalFile: 2_compressed_compressed.pdf | 17 Mar 2022 |
| Building plan approvalFile: 3_compressed_compressed.pdf | 17 Mar 2022 |
| Building plan approvalFile: 4_compressed_compressed.pdf | 17 Mar 2022 |
| PAN CardFile: pan card rachana constructions co pvt ltd.pdf | 17 Mar 2022 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Rachana Nitya | Rachana Nitya mouza bhamti landon street road nagpur 440022 | 46 | Completed | Sep 2017 | Jun 2017 |
| Rachana Meghsparsh | Rachana Meghsparsh mouza bhamti london street road Nagpur 440022 | 146 | Completed | Mar 2016 | Late, Apr 2016 |
| Rachana Madhukosh B | Rachana Madhukosh Apartment Plot no 1 to 5 Patil Layout Indraprastha nagar Jaitala Road nagpur 440022 | 24 | Completed | May 2014 | Late, Jun 2014 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 6 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 92 filed documents as one ZIP, foldered, with a manifest
Keep RACHANA EKAA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MOUZA CHINCHBHUVAN2,800+ in Nagpur
Filed coordinates, straight-line distance. 112 registered projects within 2 km.
AADHAR NAGRI - II
S R INFRA
Metrocity-3
Metrocity Projects
KUKREJA WEST19
TAGSURE HOSPITALITY LLP
IMPERIAL GARDEN
Gaurav Agrawal
SHREERAM SKYLINE
CONCRETE DEVELOPERS
THE RHYTHM
RADHESANDESH REALTORS LLP
See every Nagpur project, with the district possession charts
Builder: Rachana construction Co. (Nagpur) Pvt. Ltd.
Rachana construction Co. (Nagpur) Pvt. Ltd. has 7 registrations on MahaRERA, including Rachana 24 Carat and Rachana Sahira Wing A. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What are my rights if RACHANA EKAA is delayed beyond 31 Jan 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of RACHANA EKAA?
The registered promoter entity is Rachana construction Co. (Nagpur) Pvt. Ltd., a company as per the filing. Its CIN U45201MH2001PTC131790 and GSTIN 27AACCR1666C1ZL can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in RACHANA EKAA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for RACHANA EKAA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at RACHANA EKAA?
The professionals named in the filing: Architect: MR ULHAS MUDE; Engineer: MR PRANIL KACHOLE; Chartered Accountant: MR S W BHAGAT; Chartered Accountant: Urja Shekhar Jain. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in RACHANA EKAA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback