Home / Browse projects / Yavatmal, Maharashtra / R M Dhariwal Greens Yavatmal Phase - 2

Registration lapsed No litigation declared Residential / Group Housing project

R M Dhariwal Greens Yavatmal Phase - 2

By Dhariwal And Chhoriya Developers LLP

RG-MH-00605 · RERA P51000012173 · Last updated on MahaRERA portal: 22 May 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date
  • Completion date moved by 30 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Yavatmal registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
12 of 44Construction stages doneacross 4 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 120 documents Report an error

R M Dhariwal Greens Yavatmal Phase - 2 is a Residential / Group Housing project by Dhariwal And Chhoriya Developers LLP in Yavatmal, Maharashtra, registered with MahaRERA as P51000012173 on 1 Sep 2017. Possession was promised by 31 Dec 2023 and is now 34 months past that date. The completion date has moved by 30 months from the original filing.

At a glance

Project

  • NameR M Dhariwal Greens Yavatmal Phase - 2
  • TypeResidential / Group Housing
  • Location
    • Dhamangaon Road Bye - Pass
    • Yavatmal
    • Yavatmal (M Cl)
    • 445001
  • Pincode445001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51000012173
  • ReraGenie IDRG-MH-00605

Builder

  • NameDhariwal And Chhoriya Developers LLP
  • Entity typePartnership
  • PartnerAnmol Kanhaiyalal Chhoriya
  • Other registrations10 more →
  • Completed2 of 11
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

34 months past promisethis monthRegisteredSep 2017First promiseJun 2021Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on1 Sep 2017
  • Promised completion31 Dec 2023
  • Revised completionRevised to 31 Dec 2023 (originally 30 Jun 2021)
  • Buildings4 building records
  • Documents filed120 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
R H 54 To 59NA20000
R H 83 To 86NA20000
R H 99 And 100NA20000
P B 101NA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 22 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Podiums (if any), at 0%.

R H 54 To 5982%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
R H 83 To 860%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
R H 99 And 1000%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
P B 10127%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities17

As on 22 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%
Ent Gate and Compound WallYes100%
CCTV Camera For Layout SecurityYes100%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,775 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityYavatmal Municipal Corporation
Permissible FSI1673.93
Proposed, not sanctioned1,674 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchYavatmal

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Kunal P Patil
ArchitectANAND JAIN & ASSOCIATES
EngineerRAKESH JAIN & ASSOCIATES
EngineerAvinash Wadgaonkar
Chartered AccountantAyush Kankariya
PartnerRole in project
Dhariwal And Chhoriya Developers LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51000010252Jun 2021 → Jun 2022

Reason as filed by the promoterNote for State of development work - a) Proposed infrastructure in this proposed Phase-2 like Concrete Road, Drainage, STP, water line, Transformer and street light, Entrance gate, Compound wall, Security cabin, Garden and landscaping, Children Play Park, Vermiculture Pit, Rainwater harvesting, Solid Waste Management System etc are completed and amenities like Yoga hall, Garden are completed. Only amenities like CCTV surveillance system, EPbex telephone system, Cricket Pitch, Skating Ring, Basket Ball Court are in progress and shall be completed soon. b) Out of Total proposed units of 13 Nos (

EXT51000017223Jun 2021 → Dec 2023

Reason as filed by the promoterAs of now construction is completed but Occupation Certificate is not received.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Apr 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Feb 2024

Documents filed120

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 120 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: Yawatmal P2 Form 3 March 2025_compressed.pdf22 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Yawatmal P2 Form 1 March 2025.pdf20 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Yawatmal P2 Form 1 March 2025.pdf20 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Yawatmal P2 Form 2 March 2025.pdf20 May 2025
Certificates of CA (Form 3)File: Yawatmal Phase 2 Form 3 Dec 2024.pdf7 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Yawatmal Phase 2 Form 1 Dec 2024.pdf31 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Yawatmal Phase 2 Form 2 Dec 2024.pdf31 Jan 2025
Architect’s Certificate on Completion of Project (Form 4)File: Yawatmal Phase 2 Form 4.pdf3 Dec 2024
Certificates of CA (Form 3)File: CA Dhariwal Yavatmal P2 Sept24.pdf26 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Yawatmal Phase 2 Form 1.pdf25 Nov 2024
Architect’s Certificate on Completion of Project (Form 4)File: Yawatmal Phase 2 Form 4.pdf25 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Yawatmal Phase 2 Form 2.pdf25 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AR Dhariwal Yavatmal P2 June24.pdf12 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ER Dhariwal Yavatmal P2 June24.pdf12 Aug 2024
Certificates of CA (Form 3)File: CA Dhariwal Yavatmal P2 June24.pdf12 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AR Dhariwal Greens Yavatmal P2 March24.pdf5 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ER Dhariwal Greens Yavatmal P2 March24.pdf5 Jun 2024
Certificates of CA (Form 3)File: CA Dhariwal Greens Yavatmal P2 March24.pdf5 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: F5 CA Yawatmal (P2) 22-23.pdf5 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: F5 CA Yawatmal (P2) 23-24.pdf5 Jun 2024
Disclosure of sold/ booked inventoryFile: Yavatmal Phase 2.pdf7 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ar Dahriwal Green P2 Dec23.pdf20 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ER Dhariwal Green P2 Dec23.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Yavatmal Phase 2.pdf17 Apr 2024
Certificates of CA (Form 3)File: CA yavatmal P2 Dec23_compressed.pdf14 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AR Dhariwal Greens Phase 2 Sep23.pdf27 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ER Dhariwal Greens Phase 2 Sep23.pdf27 Feb 2024
Certificates of CA (Form 3)File: CA Yavatmal P2 Sep23.pdf27 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AR Dhariwal Greens Phase 2 Sep23.pdf23 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ER Dhariwal Greens Phase 2 Sep23.pdf23 Feb 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Yavatmal ph2 completion letter.pdf7 Feb 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: indemnity letter Ph2.pdf7 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AR Yawatmal P2 March 2023.pdf26 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Yawatmal P2 AR June 2023.pdf26 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Er Yavatmal P2 March2023.pdf26 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Yawatmal P2 ER June2023.pdf26 Sep 2023
Certificates of CA (Form 3)File: CA Yawatmal P2 March 2023.pdf26 Sep 2023
Disclosure of sold/ booked inventoryFile: Yavatmal Phase 2.pdf1 Sep 2023
Disclosure of sold/ booked inventoryFile: Yavatmal Phase 2.pdf1 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Er 2A Yavatmal P2 21-22.pdf31 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Er 2A Yavatmal P2 22-23.pdf31 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dhariwal greens phase 2 Architect's certificate.PDF23 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: phase 2 Engineer's Certificate.PDF23 Aug 2023
Certificates of CA (Form 3)File: CA Yawatmal phase 2.pdf23 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Y2 20-21.pdf1 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Y2 21-22.pdf1 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ar yavatmal p2 site11.pdf31 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Er yavatmal phase 2.pdf31 Dec 2022
Certificates of CA (Form 3)File: CA Yavatmal p2_11zon.pdf31 Dec 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Yavatmal Letter OC.pdf31 Dec 2022
Disclosure of sold/ booked inventoryFile: Yavatmal Phase 2.pdf28 Dec 2022
Certificates of CA (Form 3)File: CA Yavatmal p2_11zon.pdf28 Sep 2022
Disclosure of sold/ booked inventoryFile: Yavatamal Phase 2.pdf27 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ar yavatmal p2_11zon.pdf23 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: er yavatmal p2_11zon.pdf23 Sep 2022
Disclosure of sold/ booked inventoryFile: Yavatmal Phase2.pdf16 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Yavatmal Phase 2.pdf6 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ER R M Dhariwal greens phase 2.pdf6 Jul 2022
Certificates of CA (Form 3)File: CA R M Dhariwal greens yavatmal phase 2.pdf6 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 yavatmal phase 2 jan 22.pdf1 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 yavatmal phase 2 jan 22.pdf1 Apr 2022
Certificates of CA (Form 3)File: Yavatmal P2 CA certificate_compressed.pdf1 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 YAVATMAL PH 2_compressed.pdf10 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 YAVATMAL PH 2_compressed.pdf10 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Certificate Phase - 2 - FY March 2020 to March 2021 11_compressed.pdf12 Jan 2022
Disclosure of sold/ booked inventoryFile: YAVATMAL PHASE 2.pdf10 Jan 2022
Certificates of CA (Form 3)File: FORM 3 CA YAVATMAL PHASE 2_compressed.pdf30 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate Phase - 2 - FY March 2020 to March 2021 11_compressed.pdf27 Nov 2021
Declaration about Commencement CertificateFile: YAVATMAL PH 2 DECLARATION.pdf22 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 YAVATMAL PHASE 2 2018.pdf27 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 YAVATMAL PHASE 2 2019.pdf27 Oct 2021
Declaration about Commencement CertificateFile: Yavatmal phase - 2 Dclaration Of Camesment.pdf3 Sep 2021
Disclosure of sold/ booked inventoryFile: Yavatmal Phase - 2 - Sold And unsold Unventory 1.pdf3 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: yavatmal Phase -2 Arch Up to - Dec 2019.pdf6 Jul 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: yavatmal Phase -2 Eng Up to - Dec 2019.pdf6 Jul 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate - Dec - 19.pdf6 Jul 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Yavatmal Archi Certificate Up To - June 19.pdf21 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Yavatmal 2 Architect certi.pdf21 Jan 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Yavatmal Eng Certificate Up To - June 19.pdf21 Jan 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: yavatmal 2 engineer certi.pdf21 Jan 2020

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
R M Dhariwal Township Tembhurni PlottingPost - Tembhurni Tal - madha Dist - solapur193CompletedDec 2019Dec 2019

How this compares with Yavatmal

11%of Yavatmal projects moved their completion datethis one moved by 30 months
32%of Yavatmal registrations have lapsed or been cancelledthis one is among them

Computed across the 67 Yavatmal projects on ReraGenie, from their own filings.

Keep R M Dhariwal Greens Yavatmal Phase - 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Yavatmal67 in Yavatmal

2 kmR M Dhariwal Greens YavaCompleted 3Lapsed / revoked 3Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 8 registered projects within 2 km.

Builder: Dhariwal And Chhoriya Developers LLP

Dhariwal And Chhoriya Developers LLP has 11 registrations on MahaRERA, including R M Dhariwal Greens Yavatmal Phase 1 and R M Dhariwal Greens Yavatmal Phase - 2. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Yavatmal district page.

Frequently asked questions

What does it mean that R M Dhariwal Greens Yavatmal Phase - 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if R M Dhariwal Greens Yavatmal Phase - 2 is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of R M Dhariwal Greens Yavatmal Phase - 2?

The registered promoter entity is Dhariwal And Chhoriya Developers LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in R M Dhariwal Greens Yavatmal Phase - 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for R M Dhariwal Greens Yavatmal Phase - 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at R M Dhariwal Greens Yavatmal Phase - 2?

The professionals named in the filing: Architect: Mr Kunal P Patil; Architect: ANAND JAIN & ASSOCIATES; Engineer: RAKESH JAIN & ASSOCIATES; Engineer: Avinash Wadgaonkar; Chartered Accountant: Ayush Kankariya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in R M Dhariwal Greens Yavatmal Phase - 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About R M Dhariwal Greens Yavatmal Phase - 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save R M Dhariwal Greens Yavatmal Phase - 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.