Completed Litigation declared Residential / Group Housing project

R M Dhariwal Greens Yavatmal Phase 1

By Dhariwal And Chhoriya Developers LLP

RG-MH-00366 · RERA P51000009219 · Last updated on MahaRERA portal: 16 Feb 2023

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Yavatmal registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
400 of 528Construction stages doneacross 48 buildings; furthest along: Slabs of Super Structure, 50%
1Complaints at MahaRERAon this registration
Jump to the 70 documents Report an error

R M Dhariwal Greens Yavatmal Phase 1 is a Residential / Group Housing project by Dhariwal And Chhoriya Developers LLP in Yavatmal, Maharashtra, registered with MahaRERA as P51000009219 on 22 Aug 2017. The registration is recorded completed; possession was promised by 30 Dec 2021. The completion date has moved by 24 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameR M Dhariwal Greens Yavatmal Phase 1
  • TypeResidential / Group Housing
  • Location
    • Dhamangaon Road Bye - Pass
    • Yavatmal
    • Yavatmal (M Cl)
    • 445001
  • Pincode445001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51000009219
  • ReraGenie IDRG-MH-00366

Builder

  • NameDhariwal And Chhoriya Developers LLP
  • Entity typePartnership
  • PartnerAnmol Kanhaiyalal Chhoriya
  • Other registrations10 more →
  • Completed2 of 11
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseDec 2019Revised toDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on22 Aug 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
  • Buildings48 building records
  • Documents filed70 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PB -2NA20000
PB -3NA20000
PB -4NA20000
PB - 5NA20000
LV - 6NA20000
LV - 7NA20000
LV - 8NA20000
LV - 9NA20000
R H No - 10 to 14NA20000
RH No - 15 To 20NA20000
R H 21 To 26NA20000
R H No - 27 To 31NA20000
R H No - 43 To 48NA20000
R H No - 49 To 53NA20000
L V - 65NA20000
L V - 66NA20000
L V - 67NA20000
L V - 68NA20000
L V - 69NA20000
L V - 70NA20000
L V - 71NA20000
L V - 72NA20000
L V - 73NA20000
L V - 74NA20000
L V - 75NA20000
L V - 76NA20000
R H No - 77 To 82NA20000
L V - 118NA20000
L V - 119NA20000
L V - 120NA20000
L V - 121NA20000
L V - 122NA20000
L V - 123NA20000
P B -124NA20000
PB - 125NA20000
P B - 126NA20000
P B - 127NA20000
P B - 128NA20000
P B - 129NA20000
L V - 153NA20000
L V - 154NA20000
L V - 155NA20000
L V - 156NA20000
L V - 157NA20000
L V - 158NA20000
L V - 159NA20000
Central BuildingNA30000
PB1NA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 16 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 48 buildings; the table lists the first 20.

400 of 528 construction stages are filed complete across 48 buildings. The stage furthest along is Slabs of Super Structure, at 50%.

PB -273%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
PB -382%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
PB -433%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
PB - 573%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
LV - 682%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
LV - 782%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
LV - 882%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
LV - 982%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
R H No - 10 to 1482%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
RH No - 15 To 2082%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
R H 21 To 2682%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
R H No - 27 To 3182%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
R H No - 43 To 4882%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
R H No - 49 To 5382%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
L V - 6582%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
L V - 6682%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
L V - 6782%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
L V - 6882%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
L V - 6982%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
L V - 7082%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities17

As on 16 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%
CCTV Camera For Layout SecurityYes100%
Ent Gate and Compound WallYes100%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area32,335 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityMunicipal Corporation
Permissible FSI13067.74
Proposed, not sanctioned13,068 sq m
Buildings approved48
Buildings sanctioned48

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchYavatmal

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Kunal P Patil
ArchitectANAND JAIN & ASSOCIATES
EngineerRAKESH JAIN & ASSOCIATES
PartnerRole in project
Dhariwal And Chhoriya Developers LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51000003999Dec 2019 → Dec 2020

Reason as filed by the promoterNote for State of development work - a) Proposed infrastructure in this proposed Phase-1 like Concrete Road, Drainage, STP, water line, Transformer and street light, Entrance gate, Compound wall, Security cabin, Garden and landscaping, Children Play Park, Vermiculture Pit, Rainwater harvesting, Solid Waste Management System etc are completed and amenities like Yoga hall, Garden-2 are almost 85%+ completed and work in progress. Only amenities like CCTV surveillance system, EPbex telephone system, Cricket Pitch, Skating Ring, Basket Ball Court are in progress and shall be completed soon. b) Out

Litigation declared1

CaseCourtStatus
Rev4715/Case No5/J-9/Case No 102-10-/2015/2015Principal Secretary Executive Officer Revenue And Forest Department Mantralay MumbaiCase Dismissed with Cost dated thirteenth June two thousand seventeen

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC002000000010047Rajesh Janraoji KhadseDhariwal and Chhoriya Developers LLP03/05/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Apr 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 16 Feb 2023

Documents filed70

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Form 4 R M Dhariwal Greens Yavatmal Phase 1.pdf16 Feb 2023
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 R M Dhariwal Greens Yavatmal Phase 1.pdf16 Feb 2023
OtherFile: Yavatmal Aminities Completed RERA Upload_11zon.pdf5 Sep 2022
CERSAI detailsFile: CERSAI YAVATMAL PH-1.pdf13 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Yavatmal phase 1 Ca certificate(3)_compressed.pdf21 Mar 2022
Certificates of CA (Form 3)File: Yavatmal phase 1 Ca certificate(3)_compressed.pdf21 Mar 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Yavatmal phase 1 Jan 22_compressed.pdf19 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: YAVATMAL PHASE 1 FORM I ARC CERTIFICATE.pdf8 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: YAVATMAL PHASE 1 FORM 2 ENG CERTIFICATE.pdf8 Feb 2022
Disclosure of sold/ booked inventoryFile: Yavatmal Phase 1 sold unsold sep 2021.pdf31 Dec 2021
Certificates of CA (Form 3)File: Form 3 CA Yavatmal phase 1 CA certificate.pdf31 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 YAVATMAL PHASE 1 2018.pdf27 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 YAVATMAL PHASE 1 2019.pdf27 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archi Certificate Up To June - 19 (Part - 1).pdf21 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archi Certificate Up To June - 19 (Part - 2).pdf21 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Yavatmal Archi certi_ Part 2 Sep - 19.pdf21 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Yavatmal Archi certi_part 1 Sep - 19.pdf21 Jan 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Certificate Up To June - 19 1.pdf21 Jan 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Yavatmal engineer certi.pdf21 Jan 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance June - 19.pdf21 Jan 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certi Yavatmal Ph - 1.pdf21 Jan 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate -Sep - 19.pdf21 Jan 2020
Certificates of CA (Form 3)File: CA Certificate Up To June - 19.pdf21 Jan 2020
Certificates of CA (Form 3)File: Yavatmal CA certificate.pdf21 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Phase -1 Up To Dec -18 Part - 1.pdf23 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Phase -1 Up To Dec -18 Part - 2.pdf23 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Up March - 19 Part - 1.pdf23 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Up March - 19 Part - 2.pdf23 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Certi yavatmal ph 1 Up to Dec - 18.pdf23 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certi Yavatmal Ph - 1.pdf23 Aug 2019
Certificates of CA (Form 3)File: Ca Certi yavatmal ph 1 Up to Dec - 18.pdf23 Aug 2019
Certificates of CA (Form 3)File: Ca Certificate Up March - 19.pdf23 Aug 2019
Certificates of CA (Form 5)File: Yavatmal Phase 1 - Form -5.pdf19 Apr 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg certificate Yavatmal Ph 1 up To Sep - 18.pdf11 Jan 2019
Certificates of CA (Form 3)File: Ca certificate Yavatmal Ph 1 up To Jun - 18.pdf11 Jan 2019
Certificates of CA (Form 3)File: Ca certificate Yavatmal Ph 1 up To Sep - 18.pdf11 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cer Yavatmal Phase - 1 Up To Dec - 2018.pdf5 Jul 2018
Certificates of CA (Form 3)File: CA Cer Yavatmal Phase - 1 Up To Dec - 2018.pdf5 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archi Cer Yavatmal Phase - 1 Up To Dec - 2017 (1).pdf25 Jun 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archi Cer Yavatmal Phase - 1 Up To Dec - 2017 (2).pdf25 Jun 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cer Yavatmal Phase - 2 Up To Dec - 2017.pdf25 Jun 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cer Yavatmal Phase - 1 Up To Dec - 2017.pdf25 Jun 2018
Certificates of CA (Form 3)File: CA Cer Yavatmal Phase - 1 Up To Dec - 2017.pdf23 Jun 2018
Building plan approvalFile: Layout Phase - 3 Updated Changes 1.pdf3 Apr 2018
Building Plan Approval (IOD)File: Layout Phase - 3 Updated Changes 1.pdf3 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: Camensment Phase - 3.pdf3 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: yavatmal -NA order.pdf27 Mar 2018
Layout approvalFile: Yavatmal Phase Wise layout - date- 1-7-17-Model.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: Yavatmal Phase Wise layout - date- 1-7-17-Model.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ar Cer Yevatmal Phase 1 1.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ar Cer Yevatmal Phase 1 2.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ar Cer Yevatmal Phase 1 3.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ar Cer Yevatmal Phase 1 4.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ar Cer Yevatmal Phase 1 5.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cer Yevatmal Phase 1.pdf30 Jul 2017
Certificates of CA (Form 3)File: Ca Yevatmal Phase - 1.pdf30 Jul 2017
Layout approvalFile: YAWATMAL Dem.pdf22 Jul 2017
Building plan approvalFile: LAYOUT PLAN PLOT NO 1 SHEET NO 1.pdf22 Jul 2017
Building plan approvalFile: P B L V R H MD PLOT NO 1 SHEET NO 2.pdf22 Jul 2017
Building plan approvalFile: CENTER CLUB HOUSE PLOT NO 1 SHEET NO 3.pdf22 Jul 2017
PAN CardFile: D and C LLP Pan Card.pdf22 Jul 2017
Copy of the legal title reportFile: Yewatmal Ploted Search Report.pdf22 Jul 2017
Details of encumbrancesFile: Yewatmal Encumbrance Certificate.pdf22 Jul 2017
Copy of Layout Approval (in case of layout)File: YAWATMAL Dem.pdf22 Jul 2017
Building Plan Approval (IOD)File: LAYOUT PLAN PLOT NO 1 SHEET NO 1.pdf22 Jul 2017
Building Plan Approval (IOD)File: P B L V R H MD PLOT NO 1 SHEET NO 2.pdf22 Jul 2017
Building Plan Approval (IOD)File: CENTER CLUB HOUSE PLOT NO 1 SHEET NO 3.pdf22 Jul 2017
Declaration in FORM BFile: yevatmal p1 Declerartion Form - B.pdf22 Jul 2017
Proforma of Allotment letterFile: ATS and Allotment Yawatmal.pdf22 Jul 2017
OtherFile: yavatmal -NA order.pdf22 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
R M Dhariwal Township Tembhurni PlottingPost - Tembhurni Tal - madha Dist - solapur193CompletedDec 2019Dec 2019

How this compares with Yavatmal

11%of Yavatmal projects moved their completion datethis one moved by 24 months
32%of Yavatmal registrations have lapsed or been cancelledthis one is completed

Computed across the 67 Yavatmal projects on ReraGenie, from their own filings.

Keep R M Dhariwal Greens Yavatmal Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Yavatmal67 in Yavatmal

2 kmR M Dhariwal Greens YavaCompleted 2Lapsed / revoked 4Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 8 registered projects within 2 km.

Builder: Dhariwal And Chhoriya Developers LLP

Dhariwal And Chhoriya Developers LLP has 11 registrations on MahaRERA, including R M Dhariwal Greens Yavatmal Phase 1 and R M Dhariwal Greens Yavatmal Phase - 2. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Yavatmal district page.

Frequently asked questions

What are my rights if R M Dhariwal Greens Yavatmal Phase 1 is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of R M Dhariwal Greens Yavatmal Phase 1?

The registered promoter entity is Dhariwal And Chhoriya Developers LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in R M Dhariwal Greens Yavatmal Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against R M Dhariwal Greens Yavatmal Phase 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for R M Dhariwal Greens Yavatmal Phase 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at R M Dhariwal Greens Yavatmal Phase 1?

The professionals named in the filing: Architect: Mr Kunal P Patil; Architect: ANAND JAIN & ASSOCIATES; Engineer: RAKESH JAIN & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in R M Dhariwal Greens Yavatmal Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About R M Dhariwal Greens Yavatmal Phase 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save R M Dhariwal Greens Yavatmal Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.