Red flags

  • Possession 1 months past the filed date
  • Completion date moved by 18 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
62 of 77Construction stages doneacross 7 buildings; furthest along: Installation of Lifts, 75%
0 of 1Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 146 documents Report an error

QUEENS VILLA - 2 is a Residential / Group Housing project by SUPER REALTY in Palghar, Maharashtra, registered with MahaRERA as P99000045321 on 12 May 2022. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 18 months from the original filing. 1 of the 1 unit on this registration is recorded sold or booked, and 62 of 77 construction stages are filed complete.

At a glance

Project

  • NameQUEENS VILLA - 2
  • TypeResidential / Group Housing
  • Location
    • OSTWAL WONDER CITY ROAD
    • NEAR OSTWAL WONDER CITY
    • Betegaon
    • Palghar
    • 401501
  • Pincode401501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000045321
  • ReraGenie IDRG-MH-96406

Builder

  • NameSUPER REALTY
  • Entity typePartnership
  • GSTIN27ADYFS6697N1ZI
  • PartnersVIKASH RANCHHOD SHUKLA, VIRENDRA SINGH PRAHLAD SINGH SHEKHAWAT, KULDEEP SINGH PRITHVI KOTHARI

Key dates

1 months past promisethis monthRegisteredMay 2022First promiseMar 2025Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on12 May 2022
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 31 Mar 2025)
  • Buildings7 building records
  • Documents filed146 files

Current status

100%1 of 1 units booked
98.0%Work done, per cost certificate

Figures as on 18 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUNGALOW NO 01, TYPE ANA30101
BUNGALOW NO 2 TYPE A-1NA40000
BUNGALOW NO 3 TYPE BNA30000
BUNGALOW NO 4 TYPE B-1NA30000
BUNGALOW NO 5 TYPE CNA30000
BANGALOW NO 6 TYPE DNA30000
BUNGALOW NO 7 TYPE -ENA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building7

As on 18 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

62 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Installation of Lifts, at 75%.

BUNGALOW NO 01, TYPE A82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO 2 TYPE A-182%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO 3 TYPE B82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO 4 TYPE B-182%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO 5 TYPE C82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BANGALOW NO 6 TYPE D82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO 7 TYPE -E80%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%

Progress on shared amenities15

As on 18 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed11

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots11
Closed/Covered4
Open Space7
BuildingClosed/CoveredOpen SpaceTotal
BUNGALOW NO 01, TYPE A112
BUNGALOW NO 2 TYPE A-1112
BUNGALOW NO 3 TYPE B112
BUNGALOW NO 4 TYPE B-1112
BUNGALOW NO 5 TYPE C011
BANGALOW NO 6 TYPE D011
BUNGALOW NO 7 TYPE -E011

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,792 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Sep 2024
LandownerVillageDistrict
VIKASH RANCHHOD SHUKLABoisarPalghar
VIRENDRA SINGH PRAHLAD SINGH SHEKHAWATBoisarPalghar
KULDEEP SINGH PRITHVI SINGH KOTHARIBoisarPalghar

Approvals and building plan

Sanctioning authorityAssistant Director of Planning Authority Palghar
Permissible FSI2230.1
Proposed, not sanctioned2,230 sq m
Buildings approved7
Buildings sanctioned7

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOSTWAL EMPIRE BOISAR
Estimated costRs 5.04 cr
Cost incurredRs 4.94 cr
Work done98.01%
BuildingWingEstimatedIncurred
BUNGALOW NO 7 TYPE -ENARs 1.01 crRs 90.53 lakh
BUNGALOW NO 01, TYPE ANARs 61.09 lakhRs 61.09 lakh
BUNGALOW NO 2 TYPE A-1NARs 61.09 lakhRs 61.09 lakh
BUNGALOW NO 3 TYPE BNARs 61.09 lakhRs 61.09 lakh
BUNGALOW NO 5 TYPE CNARs 61.09 lakhRs 61.09 lakh
BUNGALOW NO 4 TYPE B-1NARs 59.77 lakhRs 59.77 lakh
BANGALOW NO 6 TYPE DNARs 51.55 lakhRs 51.55 lakh
-NARs 48.03 lakhRs 48.03 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNISHANT P PATIL
ArchitectNishant Patil
EngineerYOGESH D VAJA
Chartered AccountantAJAY SINGH
Chartered AccountantArti Rajesh Yadav
PartnerRole in project
SUPER REALTY-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000027875Mar 2025 → Mar 2026

Reason as filed by the promoterThe primary reason for this delay is the extended time required to procure and install high-quality furnishings that meet the standards expected by our buyers. Despite our best efforts to expedite the process, several factors, including supply chain disruptions and labor shortages, shortages of quality material have contributed to this delay. We are committed to delivering the project as per the revised timeline and ensuring that all flats are furnished to the highest standards. We have taken the following steps to address the delay: 1. Engaged additional suppliers to expedite the delivery of

EA25032620372Mar 2025 → Sep 2026

Reason as filed by the promoterThe primary reason for delay in project completion is a) extended time required for procurement and installation of lifts, which are essential to meet safety and quality standards. Despite our best efforts, supply chain disruptions, and material unavailability have contributed to this delay. b) Time required to get the OC from the Relevant Authority Thank you for your understanding and consideration of our request. We look forward to your positive response. moreover , in portal the option of updating the unit detail (sold or Booked ) is not avilable due to which, we are not able to upadte any

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Apr 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Apr 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Apr 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed146

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 146 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf18 Jul 2026
Withdrawal Update Form 2File: Form 1.pdf18 Jul 2026
Withdrawal Update Form 3File: FORM 3 1 Q FY 26-27.pdf18 Jul 2026
Withdrawal Update Form 1File: ARCHITECTS CERTIFICATE 31 3 2026.pdf20 Apr 2026
Withdrawal Update Form 1File: ARCHITECTS CERTIFICATE 31 3 2026.pdf20 Apr 2026
Withdrawal Update Form 2File: ENGINEERS CERTIFICATE 31 3 2026.pdf20 Apr 2026
Withdrawal Update Form 2File: ENGINEERS CERTIFICATE 31 3 2026.pdf20 Apr 2026
Withdrawal Update Form 3File: Form 3.pdf20 Apr 2026
Withdrawal Update Form 3File: Form 3.pdf20 Apr 2026
Form 5 (FY 2022-2023)File: super realty form 5.pdf30 Mar 2026
Withdrawal Update Form 1File: Architect certificate Dec 2025 (1) (1).pdf25 Mar 2026
Withdrawal Update Form 2File: Engineers Certificate Dec 2025.pdf25 Mar 2026
Withdrawal Update Form 3File: Form 3.pdf25 Mar 2026
Withdrawal Update Form 1File: ARCHITECT CERTIFICATE SEP 2025.pdf28 Jan 2026
Withdrawal Update Form 1File: Architect certificate Dec 2025 (1) (1).pdf28 Jan 2026
Withdrawal Update Form 2File: ENGINEER ERTIFICATE SEP 25.pdf28 Jan 2026
Withdrawal Update Form 2File: Engineers Certificate Dec 2025.pdf28 Jan 2026
Withdrawal Update Form 3File: Form 3.pdf28 Jan 2026
Withdrawal Update Form 3File: Form 3 Quater 3.pdf28 Jan 2026
Withdrawal Update Form 1File: Architect certificate Dec 2025 (1) (1).pdf27 Jan 2026
Withdrawal Update Form 2File: Engineers Certificate Dec 2025.pdf27 Jan 2026
Withdrawal Update Form 3File: Form 3.pdf27 Jan 2026
Withdrawal Update Form 1File: Architect certificate Dec 2025 (1) (1).pdf21 Jan 2026
Withdrawal Update Form 1File: Architect certificate Dec 2025 (1) (1).pdf21 Jan 2026
Withdrawal Update Form 2File: Engineers Certificate Dec 2025.pdf21 Jan 2026
Withdrawal Update Form 2File: Engineers Certificate Dec 2025.pdf21 Jan 2026
Withdrawal Update Form 3File: Form 3.pdf21 Jan 2026
Withdrawal Update Form 3File: Form 3.pdf21 Jan 2026
Withdrawal Update Form 1File: Architect certificate Dec 2025 (1) (1).pdf20 Jan 2026
Withdrawal Update Form 2File: Engineers Certificate Dec 2025.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3.pdf20 Jan 2026
Form 5 (FY 2024-2025)File: RERA form 5 scan FY 2024-25.pdf30 Sep 2025
Form 1File: ARCHITECT'S CERTIFICATE RERA.pdf17 Jul 2025
Form 2File: ENGINEERS'S CERTIFICATE RERA.pdf17 Jul 2025
Form 3File: CA CERTIFICATE FORM 3.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: recent sold booked inventory Q1 FY 22-23.pdf17 Jul 2025
Form 1File: Architech Certificate Q2 22-23.pdf17 Jul 2025
Form 2File: Engineers Certificate Q2 22-23.pdf17 Jul 2025
Form 3File: CA CERTIFICATE FORM 3 Q2 22-23.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: recent sold booked inventory Q2 FY 22-23.pdf17 Jul 2025
Form 1File: Architech Certificate.pdf17 Jul 2025
Form 2File: engineer certificate.pdf17 Jul 2025
Form 3File: FORM 3.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: recent sold booked inventory Q3 FY 22-23.pdf17 Jul 2025
Form 1File: ARCHITECTS CERTIFICATE.pdf17 Jul 2025
Form 2File: ENGINEER'S CERTIFICATE Q4.pdf17 Jul 2025
Form 3File: CA CERTIFICATE Form 3 Q4.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: recent sold booked inventory Q4 FY 22-23.pdf17 Jul 2025
Form 1File: ARCHITECT CRETIFICATE.pdf17 Jul 2025
Form 2File: ENGINEER'S CERTIFICATE.pdf17 Jul 2025
Form 3File: signed form 3.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: recent sold booked inventory Q1 FY 23-24.pdf17 Jul 2025
Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf17 Jul 2025
Form 2File: FORM 2 ENGINEERS CERTIFICATE.pdf17 Jul 2025
Form 3File: FORM 3 CA CERTIFICATE.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: recent sold booked inventory Q2 FY 23-24.pdf17 Jul 2025
Form 1File: Form 1 Architect Certificate.pdf17 Jul 2025
Form 2File: Form 2 Engineer's certificate.pdf17 Jul 2025
Form 3File: Form 3 CA Certificate.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: recent sold booked inventory Q3 FY 23-24.pdf17 Jul 2025
Form 1File: Super Realty Rera ARCHITECT CERTIFACATE.pdf17 Jul 2025
Form 2File: RERA NEW FORMAT ENGINEERS.pdf17 Jul 2025
Form 3File: FORM 3 Q4_Sign.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: recent sold booked inventory Q4 FY 23-24.pdf17 Jul 2025
Form 1File: Architect Certificate form 1.pdf17 Jul 2025
Form 2File: Engineer certificate form 2.pdf17 Jul 2025
Form 3File: RERA Form 3 Q1 FY 2024-25.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: recent sold booked inventory Q1 FY 24-25.pdf17 Jul 2025
Form 1File: form 1 architect.pdf17 Jul 2025
Form 2File: form 2 ENGINEER'S CERTIFICATE.pdf17 Jul 2025
Form 3File: rera form 3 super realty.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: recent sold booked inventory Q2 FY 24-25.pdf17 Jul 2025
Form 1File: fORM 1ARCHITECT CERTIFICATE 03112024.pdf17 Jul 2025
Form 2File: fORM 2ENGINEERS CERTIFECATE31122024.pdf17 Jul 2025
Form 3File: FORM 3.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: recent sold booked inventory Q3 FY 24-25.pdf17 Jul 2025
Form 1File: Form 1 Architect Certificate.pdf17 Jul 2025
Form 2File: Form 2 Engineer Certificate.pdf17 Jul 2025
Form 3File: Form 3.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: recent sold booked inventory Q4 FY 24-25.pdf17 Jul 2025

How this compares with Palghar

100%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 18 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep QUEENS VILLA - 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR OSTWAL WONDER CITY3,200+ in Palghar

2 kmQUEENS VILLA - 2Completed 6Lapsed / revoked 20Other 32Dot size: filed unitsN

Filed coordinates, straight-line distance. 58 registered projects within 2 km.

Builder: SUPER REALTY

SUPER REALTY has 1 registration on MahaRERA, including QUEENS VILLA - 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if QUEENS VILLA - 2 is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of QUEENS VILLA - 2?

The registered promoter entity is SUPER REALTY, a partnership as per the filing. Its GSTIN 27ADYFS6697N1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in QUEENS VILLA - 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for QUEENS VILLA - 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at QUEENS VILLA - 2?

The professionals named in the filing: Architect: NISHANT P PATIL; Architect: Nishant Patil; Engineer: YOGESH D VAJA; Chartered Accountant: AJAY SINGH; Chartered Accountant: Arti Rajesh Yadav. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in QUEENS VILLA - 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About QUEENS VILLA - 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save QUEENS VILLA - 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.