ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / QN GREENS PHASE 3

Registration lapsed No litigation declared Residential / Group Housing project

QN GREENS PHASE 3

By QUALITAS NAMAN HOME MAKERS LLP

RG-MH-73064 · RERA P52000018224 · Last updated on MahaRERA portal: 31 Dec 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 46 months past the filed date
  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2022Possession promised46 months past this date
9 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 80%
1Complaints at MahaRERAon this registration
Jump to the 28 documents Report an error

QN GREENS PHASE 3 is a Residential / Group Housing project by QUALITAS NAMAN HOME MAKERS LLP in Raigarh, Maharashtra, registered with MahaRERA as P52000018224 on 16 Oct 2018. Possession was promised by 30 Dec 2022 and is now 46 months past that date. 1 complaint is on record with the regulator.

At a glance

Project

  • NameQN GREENS PHASE 3
  • TypeResidential / Group Housing
  • Location
    • Ghotkamp
    • Taloja Phase 2
    • Koyana Velhe
    • Panvel
    • Raigarh
    • 410208
  • Pincode410208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000018224
  • ReraGenie IDRG-MH-73064

Builder

  • NameQUALITAS NAMAN HOME MAKERS LLP
  • Entity typePartnership
  • PartnerSANJAY BAKLIWAL
  • Other registrations3 more →
  • Completed2 of 4
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

46 months past promisethis monthRegisteredOct 2018PromisedDec 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on16 Oct 2018
  • Promised completion30 Dec 2022
  • Revised completionNone
  • Buildings3 building records
  • Documents filed28 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building 5 - Wing k, L, MNA50000
Building 6 Wing N, O, PNA50000
Building No 7 Wing Q, R, S, T, UNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 31 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 80%.

Building 5 - Wing k, L, M41%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor50%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building 6 Wing N, O, P46%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor50%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 7 Wing Q, R, S, T, U43%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor50%
Slabs of Super Structure60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 31 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed19

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots19
Open Space19
BuildingOpen SpaceTotal
Building 6 Wing N, O, P99
Building No 7 Wing Q, R, S, T, U1010

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,180 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI5640.63
Proposed, not sanctioned5,641 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchEllora, Plot No 27, Sector 11 CBD Belapur

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectOSeven Associates
EngineerAgharkar Consulting Engg Pvt Ltd
PartnerRole in project
QUALITAS NAMAN HOME MAKERS LLP-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000396224Kamalakar Govind ShindeQualitas Naman Home Makers LLP16/01/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Oct 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Oct 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Oct 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Oct 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 22 May 2023

Documents filed28

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: QNG 3 FORM 4.pdf31 Dec 2024
Architect’s Certificate on Completion of Project (Form 4)File: QN Greens Form 4.pdf20 Dec 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: QN Greens - Society Registration Certificate.pdf1 Jun 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: QNG-PHASE-3-OC COPY.pdf22 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: QNG P3 Form5 31032020.pdf23 Jul 2021
PAN CardFile: QualitasNama-Pan Card.pdf20 Jul 2021
Declaration about Commencement CertificateFile: QNG P3 CC DCLRN FormB.pdf20 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QNG P3 Engg Cert 31032020.pdf20 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QNG QLTY CERT PHASE-3 31072021r.pdf20 Jul 2021
Disclosure of sold/ booked inventoryFile: soldInvQNGp310072021.pdf20 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect cert 130721 QNG P3o.pdf14 Jul 2021
Certificates of CA (Form 3)File: RERA CA CERT FORM2 QNG P3 10072021.pdf14 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - 2018-19 - QNG P3.pdf4 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: QNGREENS_P3_ARC_CERT_300919r.pdf22 Nov 2019
Certificates of CA (Form 3)File: CA_CERTI_p3_FORM3_30092019.pdf22 Nov 2019
Certificates of CA (Form 5)File: CA_FORM5_2018_phase3.pdf28 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS O7 opt.pdf16 Oct 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase 3 Engineers Certificate (Gopal K).pdf16 Oct 2018
Layout approvalFile: Project Layout Master Plan ( Drawing No -A, Sheet no - 01 )opt.pdf12 Oct 2018
Building plan approvalFile: QN Greens Phase - 3 CC.pdf12 Oct 2018
Copy of the legal title reportFile: TITLE CERTIFICATE 13480.pdf12 Oct 2018
Details of encumbrancesFile: Encumbrance certificate-Phase3.pdf12 Oct 2018
Copy of Layout Approval (in case of layout)File: Project Layout Master Plan ( Drawing No -A, Sheet no - 01 )opt.pdf12 Oct 2018
Building Plan Approval (IOD)File: QN Greens Phase - 3 CC.pdf12 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: QN Greens Phase - 3 CC.pdf12 Oct 2018
Declaration in FORM BFile: Phase 3 Form B.pdf12 Oct 2018
Certificates of CA (Form 3)File: CA CERTIFICATES-Phase3.pdf12 Oct 2018
Proforma of Allotment letterFile: QN Green (RERA) Ageement for Sale Draft v01a.pdf12 Oct 2018

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
QN GREENS PHASE 1GAT 1-3 1-4 1-5 1-7 Koyanavelhe Taloja Panvel 410208154CompletedDec 2019Dec 2019

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep QN GREENS PHASE 3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Taloja Phase 25,900+ in Raigarh

2 kmQN GREENS PHASE 3Completed 91Lapsed / revoked 22Other 72Dot size: filed unitsN

Filed coordinates, straight-line distance. 185 registered projects within 2 km.

Builder: QUALITAS NAMAN HOME MAKERS LLP

QUALITAS NAMAN HOME MAKERS LLP has 4 registrations on MahaRERA, including QN GREENS PHASE 1 and QN GREENS PHASE 2. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that QN GREENS PHASE 3 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if QN GREENS PHASE 3 is delayed beyond 30 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of QN GREENS PHASE 3?

The registered promoter entity is QUALITAS NAMAN HOME MAKERS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in QN GREENS PHASE 3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against QN GREENS PHASE 3?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for QN GREENS PHASE 3?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at QN GREENS PHASE 3?

The professionals named in the filing: Architect: OSeven Associates; Engineer: Agharkar Consulting Engg Pvt Ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in QN GREENS PHASE 3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About QN GREENS PHASE 3. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save QN GREENS PHASE 3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.