ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / PYRAMID GLORIA

Registered No litigation declared Residential / Group Housing project

PYRAMID GLORIA

By PYRAMID TAJSHREE LLP

RG-MH-68499 · RERA P50500052196 · Last updated on MahaRERA portal: 4 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Mar 2028Possession promisedno revision filed
8 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 70%
205 of 330Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 94 documents Report an error

PYRAMID GLORIA is a Residential / Group Housing project by PYRAMID TAJSHREE LLP in Nagpur, Maharashtra, registered with MahaRERA as P50500052196 on 31 Jul 2023. Possession is promised by 31 Mar 2028. 125 of the 330 units on this registration are recorded sold or booked, and 8 of 33 construction stages are filed complete.

At a glance

Project

  • NamePYRAMID GLORIA
  • TypeResidential / Group Housing
  • Location
    • KH NO 201/2 (PART) PH NO 38 mouza Pipla
    • tahsil- nagpur (Rural)
    • NAGPUR RURAL
    • Pipla
    • Nagpur (Rural)
    • Nagpur
    • 440034
  • Pincode440034
  • RERA no.P50500052196
  • ReraGenie IDRG-MH-68499

Builder

  • NamePYRAMID TAJSHREE LLP
  • Entity typePartnership
  • PartnersSANJAY NAMDEORAO GOSAVI, PRADIP DINKAR TATAWAR

Key dates

this monthRegisteredJul 2023PromisedMar 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Jul 2023
  • Promised completion31 Mar 2028
  • Revised completionNone
  • Buildings3 building records
  • Documents filed94 files

Current status

38%125 of 330 units booked

Figures as on 4 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower ANA151510418122
Tower BNA15151040104
Tower CNA15151040104

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 4 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 70%.

Tower A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower B46%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower C51%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 4 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes35%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed19

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots19
Closed/Covered19
BuildingClosed/CoveredTotal
Tower A22
Tower B1616
Tower C11

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area11,140 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on16 Jul 2025
LandownerVillageDistrict
NITIN DEVIDAS KIRPANENagpur (M Corp.)Nagpur

Approvals and building plan

Sanctioning authorityNMRDA
Permissible FSI25818.0
Proposed, not sanctioned25,818 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWest High Court Road, Nagpur, Maharashtra, Pin 440015

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr Sanjay soni
Engineervinod mahato
Chartered Accountantca saroj vidhani
PartnerRole in project
PYRAMID TAJSHREE LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Jun 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Jun 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Aug 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2028

Documents filed94

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1.pdf4 May 2026
Form 2File: FORM 2.pdf4 May 2026
Form 3File: FORM 3.pdf4 May 2026
Disclosure of Sold and Booked InventoryFile: disclosure of sold inventory Mar 26.pdf4 May 2026
Form 1File: FORM -1.pdf21 Feb 2026
Form 2File: Form - 2.pdf21 Feb 2026
Form 3File: FORM -3 PYRAMID TAJSHREE LLP_compressed.pdf21 Feb 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE.pdf21 Feb 2026
Form 2File: ENGINEER'S CERTIFICATE PYRAMI TAJSHREE LLP.pdf10 Dec 2025
Form 1File: Architect Certificate P Tajshree.pdf10 Dec 2025
Form 3File: pyramid tajshree form 3_compressed.pdf10 Dec 2025
Disclosure of Sold and Booked InventoryFile: dIS OFSold Unsold.pdf10 Dec 2025
Form 1File: Architect's Certificate Tajshree_0001.pdf31 Jul 2025
Form 2File: Engineer's Certificate Tajshree_0001.pdf31 Jul 2025
Form 3File: Form 3 Taj.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: Dis of sold.pdf31 Jul 2025
Disclosure of sold/ booked inventoryFile: disc.pdf21 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf7 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf7 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf7 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 (2).pdf7 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DocScanner 18-Jan-2025 2-31 pm_compressed.pdf18 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DocScanner 18-Jan-2025 3-51 pm_compressed (2).pdf18 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf16 Oct 2024
Building plan approvalFile: TOWER B REVISED_compressed.pdf10 Aug 2024
Building plan approvalFile: 11_compressed.pdf10 Aug 2024
Building plan approvalFile: 08.pdf10 Aug 2024
Building plan approvalFile: 09_compressed (1).pdf10 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: TOWER B REVISED_compressed.pdf10 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: 11_compressed.pdf10 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: 08.pdf10 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: 09_compressed (1).pdf10 Aug 2024
Disclosure of sold/ booked inventoryFile: Pyramid tajshree Disclosure.pdf7 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf3 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf3 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf3 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate Form-1 Scan_0001.pdf27 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Form-2 Scan_0001.pdf27 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 PYRAMID GLORIA Signed.pdf27 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 FY 22 -23.pdf20 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT'S CERTIFICATE_compressed.pdf15 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_compressed.pdf15 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 PYRAMID GLORIA SEPTEMBER.pdf15 Dec 2023
Details of encumbrances concerned to FinanceFile: DocScanner Jul 24, 2023 16-46.pdf24 Jul 2023
Details of encumbrances concerned to LegalFile: DocScanner Jul 24, 2023 16-46.pdf24 Jul 2023
Declaration about Commencement CertificateFile: DocScanner Jul 24, 2023 18-07.pdf24 Jul 2023
Other - FinanceFile: DocScanner Jul 24, 2023 16-46.pdf24 Jul 2023
Other - TechnicalFile: DocScanner Jul 24, 2023 16-46.pdf24 Jul 2023
Building plan approvalFile: 6_compressed.pdf27 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: 6_compressed.pdf27 Jun 2023
Other - LegalFile: Development Agreement with NMRDA-1-4_compressed.pdf27 Jun 2023
Other - LegalFile: Development Agreement with NMRDA-5-8_compressed.pdf27 Jun 2023
Other - LegalFile: Development Agreement with NMRDA-9-14_compressed (1).pdf27 Jun 2023
Layout approvalFile: Development Agreement with NMRDA-1.pdf13 Jun 2023
Building plan approvalFile: 1.pdf13 Jun 2023
Building plan approvalFile: Original Building Plan-2_compressed.pdf13 Jun 2023
Building plan approvalFile: Original Building Plan-3_compressed.pdf13 Jun 2023
Building plan approvalFile: Original Building Plan-4_compressed (1)-compressed.pdf13 Jun 2023
Building plan approvalFile: Original Building Plan-5_compressed.pdf13 Jun 2023
Building plan approvalFile: Original Building Plan-6_compressed-compressed.pdf13 Jun 2023
Building plan approvalFile: Original Building Plan-7_compressed.pdf13 Jun 2023
Building plan approvalFile: Original Building Plan-8_compressed-compressed.pdf13 Jun 2023
Building plan approvalFile: Original Building Plan-9_compressed.pdf13 Jun 2023
Building plan approvalFile: Original Building Plan-10_compressed-compressed.pdf13 Jun 2023
Building plan approvalFile: Original Building Plan-11_compressed.pdf13 Jun 2023
Building plan approvalFile: Original Building Plan-12_compressed.pdf13 Jun 2023
Copy of Layout Approval (in case of layout)File: Development Agreement with NMRDA-1.pdf13 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: 1.pdf13 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Original Building Plan-2_compressed.pdf13 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Original Building Plan-3_compressed.pdf13 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Original Building Plan-4_compressed (1)-compressed.pdf13 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Original Building Plan-5_compressed.pdf13 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Original Building Plan-6_compressed-compressed.pdf13 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Original Building Plan-7_compressed.pdf13 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Original Building Plan-8_compressed-compressed.pdf13 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Original Building Plan-9_compressed.pdf13 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Original Building Plan-10_compressed-compressed.pdf13 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Original Building Plan-11_compressed.pdf13 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Original Building Plan-12_compressed.pdf13 Jun 2023
Commencement Certificates / NA Order for plotted developmentFile: Development Agreement with NMRDA-1.pdf13 Jun 2023

How this compares with Nagpur

38%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PYRAMID GLORIA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NAGPUR RURAL2,800+ in Nagpur

Builder: PYRAMID TAJSHREE LLP

PYRAMID TAJSHREE LLP has 1 registration on MahaRERA, including PYRAMID GLORIA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if PYRAMID GLORIA is delayed beyond 31 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PYRAMID GLORIA?

The registered promoter entity is PYRAMID TAJSHREE LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PYRAMID GLORIA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PYRAMID GLORIA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PYRAMID GLORIA?

The professionals named in the filing: Architect: Ar Sanjay soni; Engineer: vinod mahato; Chartered Accountant: ca saroj vidhani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PYRAMID GLORIA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PYRAMID GLORIA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PYRAMID GLORIA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.