Home / Browse projects / Nagpur, Maharashtra / Pyramid City 2

Registration lapsed No litigation declared Residential / Group Housing project

Pyramid City 2

By Pyramid Ventures India Pvt Ltd

RG-MH-01060 · RERA P50500003311 · Last updated on MahaRERA portal: 31 May 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 106 months past the filed date
  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2017Possession promised106 months past this date
60 of 66Construction stages doneacross 6 buildings; furthest along: Podiums (if any), 0%
1Complaints at MahaRERAon this registration
Jump to the 66 documents Report an error

Pyramid City 2 is a Residential / Group Housing project by Pyramid Ventures India Pvt Ltd in Nagpur, Maharashtra, registered with MahaRERA as P50500003311 on 5 Aug 2017. Possession was promised by 31 Dec 2017 and is now 106 months past that date. 1 complaint is on record with the regulator.

At a glance

Project

  • NamePyramid City 2
  • TypeResidential / Group Housing
  • Location
    • Gawasi Manapur
    • Nagpur (Rural)
    • Nagpur
    • 441108
  • Pincode441108
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500003311
  • ReraGenie IDRG-MH-01060

Builder

  • NamePyramid Ventures India Pvt Ltd
  • Entity typeCompany
  • Other registrations3 more →
  • Completed2 of 4
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

106 months past promisethis monthRegisteredAug 2017PromisedDec 2017

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Aug 2017
  • Promised completion31 Dec 2017
  • Revised completionNone
  • Buildings6 building records
  • Documents filed66 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower-ANA90000
Tower-BNA90000
Tower-CNA80000
Tower-DNA80000
Tower-ENA80000
Tower-FNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building6

As on 31 May 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

60 of 66 construction stages are filed complete across 6 buildings. The stage furthest along is Podiums (if any), at 0%.

Tower-A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tower-B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tower-C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tower-D91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tower-E91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tower-F91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 31 May 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed156

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots156
Closed/Covered108
Open Space48
BuildingClosed/CoveredOpen SpaceTotal
Tower-A201838
Tower-B20828
Tower-C19423
Tower-D15722
Tower-E15722
Tower-F19423

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area16,100 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI14014.0
Proposed, not sanctioned14,014 sq m
Buildings approved6
Buildings sanctioned6

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMadhav Nagar, Nagpur

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANJAY SONI
PartnerRole in project
Pyramid Ventures India Pvt Ltd-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC004000000110630Subhash Agrawal and othersPyramid Ventures India Pvt Ltd04/07/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jan 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 27 Jan 2023

Documents filed66

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form No 5.pdf31 May 2023
Foreclosure of the ProjectFile: Letter issued for the formation of society to costumer as per DOD.PDF31 May 2023
OtherFile: Release Letter.pdf28 Jan 2023
OtherFile: Form 4 (UT).pdf28 Jan 2023
Building plan approvalFile: scan456.pdf27 Jan 2023
Building plan approvalFile: scan457.pdf27 Jan 2023
Building plan approvalFile: scan458.pdf27 Jan 2023
Building plan approvalFile: scan459.pdf27 Jan 2023
Building plan approvalFile: scan460.pdf27 Jan 2023
Building plan approvalFile: scan461.pdf27 Jan 2023
Building plan approvalFile: scan462.pdf27 Jan 2023
Building plan approvalFile: scan463.pdf27 Jan 2023
Building plan approvalFile: scan464.pdf27 Jan 2023
Building plan approvalFile: scan465.pdf27 Jan 2023
Building plan approvalFile: scan466.pdf27 Jan 2023
Building plan approvalFile: Club House.pdf27 Jan 2023
Building Plan Approval (IOD)File: scan456.pdf27 Jan 2023
Building Plan Approval (IOD)File: scan457.pdf27 Jan 2023
Building Plan Approval (IOD)File: scan458.pdf27 Jan 2023
Building Plan Approval (IOD)File: scan459.pdf27 Jan 2023
Building Plan Approval (IOD)File: scan460.pdf27 Jan 2023
Building Plan Approval (IOD)File: scan461.pdf27 Jan 2023
Building Plan Approval (IOD)File: scan462.pdf27 Jan 2023
Building Plan Approval (IOD)File: scan463.pdf27 Jan 2023
Building Plan Approval (IOD)File: scan464.pdf27 Jan 2023
Building Plan Approval (IOD)File: scan465.pdf27 Jan 2023
Building Plan Approval (IOD)File: scan466.pdf27 Jan 2023
Building Plan Approval (IOD)File: Club House.pdf27 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: Permit.pdf27 Jan 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate.pdf27 Jan 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate.pdf27 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_11zon.pdf13 Aug 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Architect completion Certificate.pdf13 Aug 2021
OtherFile: Revised Building plan Demand Note.pdf13 Aug 2021
OtherFile: Demand paid Slip.pdf13 Aug 2021
OtherFile: Letter.pdf13 Aug 2021
OtherFile: Form No 4.PDF29 Oct 2020
Building plan approvalFile: 2.pdf29 Jul 2017
Building plan approvalFile: 3.pdf29 Jul 2017
Building plan approvalFile: 4.pdf29 Jul 2017
Building plan approvalFile: 5.pdf29 Jul 2017
Building plan approvalFile: 6.pdf29 Jul 2017
Building plan approvalFile: 7.pdf29 Jul 2017
Building plan approvalFile: 1.pdf29 Jul 2017
Building plan approvalFile: 8.pdf29 Jul 2017
Building plan approvalFile: 9.pdf29 Jul 2017
Building plan approvalFile: 10.pdf29 Jul 2017
Details of encumbrancesFile: Encumbrances Certificate.PDF29 Jul 2017
Building Plan Approval (IOD)File: 1.pdf29 Jul 2017
Building Plan Approval (IOD)File: 2.pdf29 Jul 2017
Building Plan Approval (IOD)File: 3.pdf29 Jul 2017
Building Plan Approval (IOD)File: 4.pdf29 Jul 2017
Building Plan Approval (IOD)File: 5.pdf29 Jul 2017
Building Plan Approval (IOD)File: 6.pdf29 Jul 2017
Building Plan Approval (IOD)File: 7.pdf29 Jul 2017
Building Plan Approval (IOD)File: 8.pdf29 Jul 2017
Building Plan Approval (IOD)File: 9.pdf29 Jul 2017
Building Plan Approval (IOD)File: 10.pdf29 Jul 2017
Declaration in FORM BFile: Form B City 2.PDF29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate.PDF29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate.PDF29 Jul 2017
Certificates of CA (Form 3)File: CA Certificate Ventures.PDF29 Jul 2017
Layout approvalFile: Layout plan city2.PDF27 Jul 2017
Copy of the legal title reportFile: Pyramid City-II Title Search-ilovepdf-compressed.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout plan city2.PDF27 Jul 2017
Proforma of Allotment letterFile: Allotment Letter.pdf27 Jul 2017

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is among them

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Pyramid City 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Gawasi Manapur2,800+ in Nagpur

2 kmPyramid City 2Completed 16Lapsed / revoked 1Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 23 registered projects within 2 km.

Builder: Pyramid Ventures India Pvt Ltd

Pyramid Ventures India Pvt Ltd has 4 registrations on MahaRERA, including Pyramid City 3 and Pyramid City 4. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What does it mean that Pyramid City 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Pyramid City 2 is delayed beyond 31 Dec 2017?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Pyramid City 2?

The registered promoter entity is Pyramid Ventures India Pvt Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Pyramid City 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Pyramid City 2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Pyramid City 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Pyramid City 2?

The professionals named in the filing: Architect: SANJAY SONI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Pyramid City 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Pyramid City 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Pyramid City 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.