Home / Browse projects / Nagpur, Maharashtra / Pyramid Blossom

Registration lapsed No litigation declared Residential / Group Housing project

Pyramid Blossom

By Pyramid Ventures India Pvt. Ltd

RG-MH-42416 · RERA P50500022475 · Last updated on MahaRERA portal: 7 Sep 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
50 of 66Construction stages doneacross 6 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

Pyramid Blossom is a Residential / Group Housing project by Pyramid Ventures India Pvt. Ltd in Nagpur, Maharashtra, registered with MahaRERA as P50500022475 on 25 Sep 2019. Possession was promised by 25 Dec 2025 and is now 10 months past that date.

At a glance

Project

  • NamePyramid Blossom
  • TypeResidential / Group Housing
  • Location
    • Besa Pipla
    • Pipla
    • Nagpur (Rural)
    • Nagpur
    • 440034
  • Pincode440034
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500022475
  • ReraGenie IDRG-MH-42416

Builder

  • NamePyramid Ventures India Pvt. Ltd
  • Entity typeCompany
  • DirectorSunil Charandas Somkumar
  • Other registrations3 more →
  • Completed2 of 4
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

10 months past promisethis monthRegisteredSep 2019PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on25 Sep 2019
  • Promised completion25 Dec 2025
  • Revised completionNone
  • Buildings6 building records
  • Documents filed56 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower ANA130000
Tower BNA130000
Tower CNA130000
Tower DNA130000
Tower ENA130000
Tower FNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building6

As on 7 Sep 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

50 of 66 construction stages are filed complete across 6 buildings. The stage furthest along is Podiums (if any), at 0%.

Tower A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tower B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tower C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tower D91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tower E91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tower F0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities16

As on 7 Sep 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes75%
Water SupplyYes70%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes70%
Street LightingYes50%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes90%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes75%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes75%
Electrical meter room, sub-station, receiving stationYes75%
Aggregate area of recreational Open SpaceYes50%
Open ParkingNoNot applicable
swimming poolYes0%

Parking filed221

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots221
Closed/Covered221
BuildingClosed/CoveredTotal
Tower A4444
Tower B4444
Tower C4444
Tower D4444
Tower E4444
Tower F11

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,100 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI11906.23
Proposed, not sanctioned9,774 sq m
Buildings approved7
Buildings sanctioned6

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJaiprakash Nagar Nagpur

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSanjay soni
EngineerVinod Mahato
Chartered AccountantChandak & Chandak
PartnerRole in project
Pyramid Ventures India Pvt. Ltd-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Jun 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Sep 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Jul 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Sep 2022

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate.PDF7 Sep 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate.PDF7 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: CA Certificate for FY - 2019-20.pdf26 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CA Certificate for FY - 2019-20.pdf26 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA certificate for FY 2020-21.pdf26 Aug 2021
Building plan approvalFile: Revised 01.pdf7 Jul 2021
Building plan approvalFile: Revised 02.pdf7 Jul 2021
Building plan approvalFile: Revised 03.pdf7 Jul 2021
Building plan approvalFile: Revised 04.pdf7 Jul 2021
Building plan approvalFile: Revised 05.pdf7 Jul 2021
Building plan approvalFile: Revised 06.pdf7 Jul 2021
Building plan approvalFile: Revised 07.pdf7 Jul 2021
Building plan approvalFile: Revised 08.pdf7 Jul 2021
Building plan approvalFile: Revised 09.pdf7 Jul 2021
Building plan approvalFile: Revised 10.pdf7 Jul 2021
Building plan approvalFile: Revised 11.pdf7 Jul 2021
Building Plan Approval / NA Order for plotted developmentFile: Revised 01.pdf7 Jul 2021
Building Plan Approval / NA Order for plotted developmentFile: Revised 02.pdf7 Jul 2021
Building Plan Approval / NA Order for plotted developmentFile: Revised 03.pdf7 Jul 2021
Building Plan Approval / NA Order for plotted developmentFile: Revised 04.pdf7 Jul 2021
Building Plan Approval / NA Order for plotted developmentFile: Revised 05.pdf7 Jul 2021
Building Plan Approval / NA Order for plotted developmentFile: Revised 06.pdf7 Jul 2021
Building Plan Approval / NA Order for plotted developmentFile: Revised 07.pdf7 Jul 2021
Building Plan Approval / NA Order for plotted developmentFile: Revised 08.pdf7 Jul 2021
Building Plan Approval / NA Order for plotted developmentFile: Revised 09.pdf7 Jul 2021
Building Plan Approval / NA Order for plotted developmentFile: Revised 10.pdf7 Jul 2021
Building Plan Approval / NA Order for plotted developmentFile: Revised 11.pdf7 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: Revised Commencement Certificate.pdf7 Jul 2021
Proforma of Allotment letterFile: Agreement to sell.pdf17 Sep 2019
Layout approvalFile: Sanction Layout plan.pdf5 Sep 2019
Building plan approvalFile: Drawing 1.pdf5 Sep 2019
Building plan approvalFile: Drawing 2.pdf5 Sep 2019
Building plan approvalFile: Drawing 3.pdf5 Sep 2019
Building plan approvalFile: Drawing 4.pdf5 Sep 2019
Building plan approvalFile: Drawing 5.pdf5 Sep 2019
Building plan approvalFile: Drawing 6.pdf5 Sep 2019
Building plan approvalFile: Drawing 7.pdf5 Sep 2019
Building plan approvalFile: Drawing 8.pdf5 Sep 2019
Building plan approvalFile: Drawing 9.pdf5 Sep 2019
Copy of Layout Approval (in case of layout)File: Sanction Layout plan.pdf5 Sep 2019
Building Plan Approval / NA Order for plotted developmentFile: Drawing 1.pdf5 Sep 2019
Building Plan Approval / NA Order for plotted developmentFile: Drawing 2.pdf5 Sep 2019
Building Plan Approval / NA Order for plotted developmentFile: Drawing 3.pdf5 Sep 2019
Building Plan Approval / NA Order for plotted developmentFile: Drawing 4.pdf5 Sep 2019
Building Plan Approval / NA Order for plotted developmentFile: Drawing 5.pdf5 Sep 2019
Building Plan Approval / NA Order for plotted developmentFile: Drawing 6.pdf5 Sep 2019
Building Plan Approval / NA Order for plotted developmentFile: Drawing 7.pdf5 Sep 2019
Building Plan Approval / NA Order for plotted developmentFile: Drawing 8.pdf5 Sep 2019
Building Plan Approval / NA Order for plotted developmentFile: Drawing 9.pdf5 Sep 2019
Commencement Certificates / NA Order for plotted developmentFile: Building permit.pdf5 Sep 2019
Proforma of Allotment letterFile: Proforma of Allotment Letter.pdf5 Sep 2019
PAN CardFile: PAN Card.pdf14 Jun 2019
Copy of the legal title reportFile: Legal Title report.pdf14 Jun 2019
Details of encumbrancesFile: Decleration.PDF14 Jun 2019
Declaration in FORM BFile: Affidavit cum declaration.pdf14 Jun 2019
Certificates of CA (Form 3)File: CA Cirtificate Form 3.pdf14 Jun 2019

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Pyramid city 3Besa pipla road186CompletedFeb 2018Late, Apr 2018

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is among them

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Pyramid Blossom on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pipla2,800+ in Nagpur

2 kmPyramid BlossomCompleted 21Lapsed / revoked 13Other 30Dot size: filed unitsN

Filed coordinates, straight-line distance. 64 registered projects within 2 km.

Builder: Pyramid Ventures India Pvt. Ltd

Pyramid Ventures India Pvt Ltd has 4 registrations on MahaRERA, including Pyramid City 3 and Pyramid City 4. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What does it mean that Pyramid Blossom shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Pyramid Blossom is delayed beyond 25 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Pyramid Blossom?

The registered promoter entity is Pyramid Ventures India Pvt. Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Pyramid Blossom?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Pyramid Blossom?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Pyramid Blossom?

The professionals named in the filing: Architect: Sanjay soni; Engineer: Vinod Mahato; Chartered Accountant: Chandak & Chandak. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Pyramid Blossom?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Pyramid Blossom. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Pyramid Blossom to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.