Home / Browse projects / Nagpur, Maharashtra / PUSHKAR SIGNATURE

Registration lapsed No litigation declared Residential / Group Housing project

PUSHKAR SIGNATURE

By Pushkar Homes Private Limited

RG-MH-01964 · RERA P50500009067 · Last updated on MahaRERA portal: 24 Sep 2020

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 69 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 14 earlier projects delivered on promise

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
4 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 70%
1Complaints at MahaRERAon this registration
Jump to the 22 documents Report an error

PUSHKAR SIGNATURE is a Residential / Group Housing project by Pushkar Homes Private Limited in Nagpur, Maharashtra, registered with MahaRERA as P50500009067 on 19 Aug 2017. Possession was promised by 31 Dec 2024 and is now 22 months past that date. The completion date has moved by 69 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NamePUSHKAR SIGNATURE
  • TypeResidential / Group Housing
  • Location
    • Nagpur (M Corp.)
    • Nagpur (Urban)
    • Nagpur
    • 440015
  • Pincode440015
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500009067
  • ReraGenie IDRG-MH-01964

Builder

  • NamePushkar Homes Private Limited
  • Entity typeCompany
  • Managing DirectorsVishal Rajeshkumar Agrawal, Kartik Balakrishnan Iyer, Neeraj Pravin Agrawal
  • Other registrations5 more →
  • Completed2 of 6
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects14 →

Key dates

22 months past promisethis monthRegisteredAug 2017First promiseMar 2019Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on19 Aug 2017
  • Promised completion31 Dec 2024
  • Revised completionRevised to 31 Dec 2024 (originally 31 Mar 2019)
  • Buildings2 building records
  • Documents filed22 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PUSHKAR SIGNATURE-BLDG 1NA70000
PUSHKAR SIGNATURE-BLDG 2NA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 24 Sep 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 70%.

PUSHKAR SIGNATURE-BLDG 143%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
PUSHKAR SIGNATURE-BLDG 20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Sep 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed56

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots56
Closed/Covered15
Open Space41
BuildingClosed/CoveredOpen SpaceTotal
PUSHKAR SIGNATURE-BLDG 1151530
PUSHKAR SIGNATURE-BLDG 202626

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,621 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3792.91
Proposed, not sanctioned2,025 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHindustan Colony Wardha Road Nagpur

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPooja Jaiswal
PartnerRole in project
Pushkar Homes Private Limited-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50500002489Mar 2019 → Apr 2020

Reason as filed by the promoterNo Specific Reason

EXT50500008712Mar 2019 → Dec 2021

Reason as filed by the promoterDue COVID - 19 & Lock down we faced the shortage of labour, hence applied for extension.

EXT50500015076Mar 2019 → Dec 2024

Reason as filed by the promoterOC is pending with the Nagpur muncipal corporation for Phase -1. Phase-2 not yet started.

Litigation declared1

CaseCourtStatus
514/2016/2016Nagpur Courtawaiting service of summons of other respondents

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC004000000030407Minita Rajendra BhattPushkar Signature24/07/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed22

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: fs.pdf24 Sep 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: iar_compressed (1).pdf24 Sep 2020
Certificates of CA (Form 5)File: RERA FORM5 SIGNATURE.pdf9 Oct 2019
Certificates of CA (Form 5)File: PHPL-Form-5-(Signature).pdf19 Oct 2018
Building plan approvalFile: Somalwada Map 1.pdf31 Jul 2017
Building plan approvalFile: Somalwada Map 2.pdf31 Jul 2017
Building plan approvalFile: Somalwada Map 3.pdf31 Jul 2017
Layout approvalFile: RL Somalwada.pdf31 Jul 2017
Copy of the legal title reportFile: compressed_Legal Search singture.pdf31 Jul 2017
Details of encumbrancesFile: Encumbrance.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: RL Somalwada.pdf31 Jul 2017
Building Plan Approval (IOD)File: Somalwada Map 1.pdf31 Jul 2017
Building Plan Approval (IOD)File: Somalwada Map 2.pdf31 Jul 2017
Building Plan Approval (IOD)File: Somalwada Map 3.pdf31 Jul 2017
Declaration in FORM BFile: Form B Somalwada-i.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Signature B1-Form 1-min.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Signature B2-Form 1-min.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Cert Form2-Signature min-i.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA Certificate-min-i.pdf31 Jul 2017
Proforma of Allotment letterFile: Allotment Letter - Signature.pdf31 Jul 2017
Proforma of Allotment letterFile: Final Draft Agreement to Sale.pdf31 Jul 2017
PAN CardFile: PAN PHPL.pdf30 Jul 2017

Promoter's earlier projects14

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

14 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Pushkar FlorencePlot No 19 Padole Layout Dev Nagar Nagpur5CompletedJun 2017Jun 2017
Pushkar Gardens Plot No 15Plot No 15 Khasra No 276 Wanadongari Tahsil Hingna Nagpur8CompletedApr 2017Apr 2017
Pushkar Garden Plot No 5Plot No 5 Khasra No 276 Wanadongari Tahsil Hingna Nagpur1CompletedApr 2017Apr 2017
Pushkar MaplePlot No 2 Kh No 29 Mouza Gadga Near Zenda Chowk Khare Town Dharampeth Nagpur6CompletedSep 2016Sep 2016
Pushkar Gardens Plot No 18Plot No 18 Khasra No 276 Wanadongari Tahsil Hingna Nagpur1CompletedAug 2016Aug 2016
Pushkar Gardens Plot No 8Plot No 8 Khasra No 276 Wanadongari Tahsil Hingna Nagpur1CompletedApr 2016Apr 2016
Pushkar Gardens Plot No 20Plot No 20 Khasra No 276 Wanadongari Tahsil Hingna Nagpur1CompletedMar 2016Mar 2016
Pushkar Garden Plot No 6 and 7Plot No 6 and 7 Khasra No 276 Wanadongari Tahsil Hingna Nagpur1CompletedOct 2015Oct 2015
Pushkar Garden Plot No 9Plot No 9 Khasra No 276 Wanadongari Tahsil Hingna Nagpur1CompletedAug 2015Aug 2015
Pushkar Spring Garden Plot No 3Plot No.3 Khasra No 276 Wanadongari Tahsil Hingna Nagpur1CompletedMar 2015Mar 2015
Pushkar Gardens Plot No 10Plot No 10 Khasra No 276 Wanadongari Tahsil Hingna Nagpur1CompletedMar 2015Mar 2015
Pushkar Garden Plot 4Plot No 4 Khasra No 276 Wanadongari Tahsil Hingna Nagpur1CompletedMar 2015Mar 2015
Pushkar BlossomsPlot No 33-A Ram Mandir Road Swawalambi Nagar Nagpur4CompletedSep 2013Sep 2013
Pushkar ResidencyPlot No 33 Surendra Nagar Nagpur8CompletedSep 2012Sep 2012

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one moved by 69 months
22%of Nagpur registrations have lapsed or been cancelledthis one is among them

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PUSHKAR SIGNATURE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Nagpur (M Corp.)2,800+ in Nagpur

Builder: Pushkar Homes Private Limited

Pushkar Homes Private Limited has 6 registrations on MahaRERA, including Pushkar Orchid Greens Phase I and Pushkar Orchid Greens Phase II. Its filings disclose 14 earlier MahaRERA projects: declares 14 of 14 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What does it mean that PUSHKAR SIGNATURE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PUSHKAR SIGNATURE is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PUSHKAR SIGNATURE?

The registered promoter entity is Pushkar Homes Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PUSHKAR SIGNATURE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against PUSHKAR SIGNATURE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for PUSHKAR SIGNATURE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PUSHKAR SIGNATURE?

The professionals named in the filing: Architect: Pooja Jaiswal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PUSHKAR SIGNATURE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PUSHKAR SIGNATURE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PUSHKAR SIGNATURE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.