Home / Browse projects / Aurangabad, Maharashtra / PUKHARAJ RESIDENCY

Registered No litigation declared Residential / Group Housing project

PUKHARAJ RESIDENCY

By PUKHRAJ BUILDERS AND DEVELOPERS

RG-MH-30935 · RERA P51500079269 · Last updated on MahaRERA portal: 13 Feb 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Feb 2027Possession promisedno revision filed
1 of 11Construction stages donefurthest along: Basement (if any), 10%
0Complaints at MahaRERAon this registration
Jump to the 40 documents Report an error

PUKHARAJ RESIDENCY is a Residential / Group Housing project by PUKHRAJ BUILDERS AND DEVELOPERS in Aurangabad, Maharashtra, registered with MahaRERA as P51500079269 on 25 Feb 2025. Possession is promised by 28 Feb 2027.

At a glance

Project

  • NamePUKHARAJ RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • PLOT NO 1
    • 2
    • 3 AND 4
    • GUT NO 90/1
    • MAUJE SATARA TQ AND DISTRICT Chh Sambhajinagar
    • Satara (CT)
    • Aurangabad
    • 431011
  • Pincode431011
  • RERA no.P51500079269
  • ReraGenie IDRG-MH-30935

Builder

  • NamePUKHRAJ BUILDERS AND DEVELOPERS
  • Entity typePartnership

Key dates

this monthRegisteredFeb 2025PromisedFeb 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Feb 2025
  • Promised completion28 Feb 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed40 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PUKHARAJ RESIDENCYNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 10%.

PUKHARAJ RESIDENCY: 11% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)10%
Podiums (if any)0%
Plinth10%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 13 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,006 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
JASMEETKAUR SARTAJSINGH CHAHALAurangabad (M Corp.)Aurangabad
PARMINDAR KAUR HARVNDERSINGH RATANAurangabad (M Corp.)Aurangabad

Approvals and building plan

Permissible FSI3305.11
Proposed, not sanctioned3,305 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGAJANAN MAHARAJ MANDIR CHOWK, AURANGABAD

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNIKHIL MANOJ CHOPADA
EngineerN G KARKHANE
Chartered AccountantTUSHAR DESARDA
PartnerRole in project
PUKHRAJ BUILDERS AND DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Dec 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Dec 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Dec 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 28 Feb 2027

Documents filed40

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A Bank from Builder.pdf13 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A - Declaration for account not opening signed.pdf1 Feb 2025
Details of encumbrances concerned to FinanceFile: DETAILS OF ENCUMBRANCES CONCERNED TO LEGAL.pdf21 Jan 2025
Details of encumbrances concerned to FinanceFile: CERTIFICATE 1.pdf21 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificte.pdf21 Jan 2025
Details of encumbrances concerned to LegalFile: CERTIFICATE 1.pdf21 Jan 2025
Details of encumbrances concerned to LegalFile: DETAILS OF ENCUMBRANCES CONCERNED TO LEGAL.pdf21 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: Gmail - Fwd_ 66 02 SANTION BP POROPSAL 16012025.pdf16 Jan 2025
Details of encumbrances concerned to FinanceFile: DETAILS OF ENCUMBRANCES CONCERNED TO LEGAL.pdf13 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: FORMAT D.pdf13 Jan 2025
Deviation Report with respect to Allotment letterFile: DEVIATION REPORT WITH RESPECT TO ALLOTMENT LETTER.pdf13 Jan 2025
Details of encumbrances concerned to LegalFile: DETAILS OF ENCUMBRANCES CONCERNED TO LEGAL.pdf13 Jan 2025
Deviation Report with respect to model copy of AgreementFile: DEVIATION REPORT WITH RESPECT TO MODEL COPY OF AGREEMENT .pdf13 Jan 2025
Proforma of Agreement for saleFile: ATS DRAFT.pdf13 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHETECH CERTIFICATE.pdf16 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG ERTIFICATE.pdf16 Dec 2024
Disclosure for secured/unsecured finance availed for the projectFile: DISCLUORE UNSECURED LOAN.pdf16 Dec 2024
Details of encumbrances concerned to FinanceFile: encumbrance legal.pdf12 Dec 2024
Details of encumbrances concerned to FinanceFile: NO ENCUMBRANCE CERTIFICATE.pdf12 Dec 2024
Details of encumbrances concerned to FinanceFile: DETAILS OF ENCUMBRANCES CONCERNED TO LEGAL.pdf12 Dec 2024
Declaration in FORM BFile: FORM B developer.pdf12 Dec 2024
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf12 Dec 2024
CERSAI detailsFile: CERTIFICATE cresai.pdf12 Dec 2024
CERSAI detailsFile: CERSAI_Search_Report.pdf12 Dec 2024
Details of encumbrances concerned to LegalFile: DETAILS OF ENCUMBRANCES CONCERNED TO LEGAL.pdf12 Dec 2024
Details of encumbrances concerned to LegalFile: NO ENCUMBRANCE CERTIFICATE.pdf12 Dec 2024
Details of encumbrances concerned to LegalFile: encumbrance legal.pdf12 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A DISCLOSURE OF INTEREST IN OTHER REAL ESTATE ORGANIZATIONS.pdf12 Dec 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: FORMAT b.pdf12 Dec 2024
Layout approvalFile: LAYOUT.pdf11 Dec 2024
Building plan approvalFile: NA ORDER.pdf11 Dec 2024
Building plan approvalFile: permission plan.pdf11 Dec 2024
PAN CardFile: Pan Card Page.pdf11 Dec 2024
Copy of the legal title reportFile: SEARCH REPORT RERA PUKHRAJ DEVELOPER.pdf11 Dec 2024
Copy of the legal title reportFile: EchallanMH010795263202425U.pdf11 Dec 2024
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf11 Dec 2024
Proforma of Allotment letterFile: allotment.pdf11 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: permission document.pdf11 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: NA ORDER.pdf11 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: permission plan.pdf11 Dec 2024

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep PUKHARAJ RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GUT NO 90/1, MAUJE SATARA TQ AND DISTRICT Chh Sambhajinagar1,400+ in Aurangabad

Builder: PUKHRAJ BUILDERS AND DEVELOPERS

PUKHRAJ BUILDERS AND DEVELOPERS has 1 registration on MahaRERA, including PUKHARAJ RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if PUKHARAJ RESIDENCY is delayed beyond 28 Feb 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PUKHARAJ RESIDENCY?

The registered promoter entity is PUKHRAJ BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PUKHARAJ RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PUKHARAJ RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PUKHARAJ RESIDENCY?

The professionals named in the filing: Architect: NIKHIL MANOJ CHOPADA; Engineer: N G KARKHANE; Chartered Accountant: TUSHAR DESARDA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PUKHARAJ RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PUKHARAJ RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PUKHARAJ RESIDENCY to a free account