Home / Browse projects / Raigarh, Maharashtra / PRIYANSHI RESIDENCY
PRIYANSHI RESIDENCY
By SHIVKRUPA BUILDERS AND DEVELOPERS
RG-MH-81201 · RERA P52000016200 · Last updated on MahaRERA portal: 5 Jun 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 2 complaints at MahaRERA
- Completion date moved by 54 months
- 3 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PRIYANSHI RESIDENCY is a Others project by SHIVKRUPA BUILDERS AND DEVELOPERS in Raigarh, Maharashtra, registered with MahaRERA as P52000016200 on 23 Apr 2018. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 54 months from the original filing. 2 complaints are on record with the regulator.
At a glance
Project
- NamePRIYANSHI RESIDENCY
- TypeOthers
- Location
- PANVEL
- Usarli Kh
- Raigarh
- 410206
- Pincode410206
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000016200
- ReraGenie IDRG-MH-81201
Builder
- NameSHIVKRUPA BUILDERS AND DEVELOPERS
- Entity typePartnership
- PartnersSURAJ ARJUN JALE, PRADNYESH SANJAY KAMBLE, PAVAN MAHATMA DEVALKAR
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on23 Apr 2018
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2021)
- Buildings4 building records
- Documents filed23 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| PRIYANSHI RESIDENCY BLDG 1 | NA | 5 | 0 | 0 | 0 | 0 |
| PRIYANSHI RESIDENCY BLDG 2 | NA | 5 | 0 | 0 | 0 | 0 |
| PRIYANSHI RESIDENCY BLDG 3 | NA | 4 | 0 | 0 | 0 | 0 |
| PRIYANSHI RESIDENCY BLDG 4 | NA | 4 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 5 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Excavation, at 0%.
PRIYANSHI RESIDENCY BLDG 10%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PRIYANSHI RESIDENCY BLDG 20%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PRIYANSHI RESIDENCY BLDG 30%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PRIYANSHI RESIDENCY BLDG 40%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 5 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed2
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| PRIYANSHI RESIDENCY BLDG 1 | 1 | 1 |
| PRIYANSHI RESIDENCY BLDG 2 | 1 | 1 |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| NEETA RAMESH ADHIKARI | Panvel | Raigarh |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SANDEEP SHINDE |
| Chartered Accountant | KEYUR |
| Partner | Role in project |
|---|---|
| SHIVKRUPA BUILDERS AND DEVELOPERS | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDUE TO SOME PERSONAL ISSUES AND SHORATGE OF FUNDS PROJECT IS YET NOT COMPLETED
Reason as filed by the promoterTHE PROJECT IS DELAYED TO PANADAMIC OF COVID 19 AS LOCKDOWN WAS THERE WORK WAS NOT IN PROGRESS AS REQUIRED SO PLEASE EXTEND THE PROJECT DATE
Reason as filed by the promoterThe delay in project completion is primarily attributable to a combination of unforeseen and unavoidable circumstances. Firstly, an internal dispute with a former partner significantly impacted project progress, causing delays in key decision-making, financial approvals, and overall execution. This dispute has since been amicably resolved, allowing operations to resume smoothly and efficiently. Secondly, the designated project bank account was temporarily frozen due to technical and compliance-related issues, which restricted access to project funds and, in turn, delayed construction activitie
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000408227 | Dhanraj Raman Mhatre | 1.M/s. Shivkrupa Builders & Developers, The partnership Firm | 29/01/2024 |
| CC12602851 | UDAY DATTARAM CHANDURKAR | SHIVKRUPA BUILDERS AND DEVELOPERS | 15/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 16 Apr 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Apr 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Apr 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed23
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: New Form2A supervisor certificate.pdf | 5 Jun 2025 |
| Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE.pdf | 2 Jun 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form_5 (1).pdf | 6 Sep 2022 |
| Declaration about Commencement CertificateFile: DECLARATION.pdf | 8 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: ENGINEER CERTIFICATE.pdf | 8 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGINEER CERTIFICATE.pdf | 8 Sep 2021 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE.pdf | 8 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5 1819.pdf | 8 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 1819.pdf | 8 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 51920.pdf | 8 Sep 2021 |
| Layout approvalFile: FINAL LAYOUT PLAN (1).pdf | 16 Apr 2018 |
| Building plan approvalFile: FINAL LAYOUT PLAN (1).pdf | 16 Apr 2018 |
| Copy of the legal title reportFile: SEARCH REPORT MERGED.pdf | 16 Apr 2018 |
| Details of encumbrancesFile: SEARCH REPORT MERGED.pdf | 16 Apr 2018 |
| Copy of Layout Approval (in case of layout)File: FINAL LAYOUT PLAN (1).pdf | 16 Apr 2018 |
| Building Plan Approval (IOD)File: FINAL LAYOUT PLAN (1).pdf | 16 Apr 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: 001 (10 files merged) (1).pdf | 16 Apr 2018 |
| Declaration in FORM BFile: DECLARATION SURAJ.pdf | 16 Apr 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf | 16 Apr 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf | 16 Apr 2018 |
| Certificates of CA (Form 3)File: CA CERTIFICATE.pdf | 16 Apr 2018 |
| Proforma of Allotment letterFile: ALLOTMENTM LETTER.pdf | 16 Apr 2018 |
| Proforma of Allotment letterFile: SALES AGREMENT-ilovepdf-compressed (2).pdf | 16 Apr 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 23 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep PRIYANSHI RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PANVEL5,900+ in Raigarh
Filed coordinates, straight-line distance. 402 registered projects within 2 km.
SHREE RAM DELTA
Shreenathji Enterprises
Brillante
Callista Realty Limited
SAI SUNCITY PHASE 3
Chariot Properties LLP
ANANDAM PHASE - II
TODAY GLOBAL HOMES
Maximus Residency Phase-I
Superb Maa Developers LLP
Sai Vrindavan Dham
KT & LK SWEET HOMES
See every Raigarh project, with the district possession charts
Builder: SHIVKRUPA BUILDERS AND DEVELOPERS
SHIVKRUPA BUILDERS AND DEVELOPERS has 1 registration on MahaRERA, including PRIYANSHI RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What does it mean that PRIYANSHI RESIDENCY shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if PRIYANSHI RESIDENCY is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PRIYANSHI RESIDENCY?
The registered promoter entity is SHIVKRUPA BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PRIYANSHI RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against PRIYANSHI RESIDENCY?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for PRIYANSHI RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PRIYANSHI RESIDENCY?
The professionals named in the filing: Architect: SANDEEP SHINDE; Chartered Accountant: KEYUR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PRIYANSHI RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback