ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.

Registered No litigation declared Residential / Group Housing project

PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.

By ARJUNSINGH BHOORSINGH RATHORE

RG-MH-03337 · RERA P51800021193 · Last updated on MahaRERA portal: 19 Aug 2026

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 48 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 48 months from the original
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 60%
28 of 31Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 85 documents Report an error

PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. is a Residential / Group Housing project by ARJUNSINGH BHOORSINGH RATHORE in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800021193 on 14 Jun 2019. Possession is promised by 30 Jun 2027. The completion date has moved by 48 months from the original filing. 3 of the 31 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NamePRIYA CO-OPERATIVE HOUSING SOCIETY LTD.
  • TypeResidential / Group Housing
  • Location
    • JUHU CROSS LANE ROAD
    • VILE PARLE WEST
    • Andheri
    • Mumbai Suburban
    • 400058
  • Pincode400058
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800021193
  • ReraGenie IDRG-MH-03337

Builder

  • NameARJUNSINGH BHOORSINGH RATHORE
  • Entity typeIndividual

Key dates

this monthRegisteredJun 2019First promiseJun 2023Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on14 Jun 2019
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2023)
  • Buildings1 building record
  • Documents filed85 files

Current status

10%3 of 31 units booked
50.0%Work done, per cost certificate

Figures as on 19 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PRIYA CO-OPERATIVE HOUSING SOCIETY LIMITEDNA5528331

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 60%.

PRIYA CO-OPERATIVE HOUSING SOCIETY LIMITED: 34% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed33

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots33
Closed/Covered1
Open Space32

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area678 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityBRIHANMUMBAI MUNICIPAL CORPORATION
Permissible FSI677.9
Proposed, not sanctioned678 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAHURA CENTRE GROUND FLOOR MAHAKALI CAVES ROAD ANDHERI WEST MUMBAI 400093
Estimated costRs 9.45 cr
Cost incurredRs 4.72 cr
Work done50.0%
BuildingWingEstimatedIncurred
PRIYA CO-OPERATIVE HOUSING SOCIETY LIMITEDNARs 9.45 crRs 4.72 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKALPESH JAIN
EngineerHARESH S PATEL
Chartered AccountantRAHUL AGRAWAL
Chartered AccountantARPAJ AND ASSOCIATES
PartnerRole in project
ARJUNSINGH BHOORSINGH RATHORE-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800016863Jun 2023 → Jun 2024

Reason as filed by the promoterDue to the Covid-19 Pandemic Situation in the Country We could not completed our Work on time, Therefore request you to kindly consider our attached extension letter

EXT51800024171Jun 2023 → Jun 2026

Reason as filed by the promoterThe primary reasons for the delay, as we understand, include arch 1. Road Winding Issues in D P 2034 There have been challenges with road construction due to changes in planning regulations and technical issues, which have directly impacted the project's timeline 2 Ongoing Court Cases Legal disputes between the society and certain members of the project have contributed to the overall delay These issues are currently resolved. 3 Other Legal Litigations and Regulatory Delays. In addition to the above, there have been other legal and regulatory challenges, including delays in obtaining the neces

EA19082622231Jun 2023 → Jun 2027

Reason as filed by the promoterI, Arjun Singh Rathore, Proprietor of M/s. Rasal Builders & Developers, is the promoters of the real estate project known as "PRIYA CO-OPERATIVE HOUSING SOCIETY LIMITED" bearing Maha RERA Registration No. P51800021193. The primary reasons for the delay, as we understand, include: 1. Road Winding Issues in D P 2034: There have been challenges with road construction due to changes in planning regulations and technical issues, which have directly impacted the project's timeline. 2. Ongoing Court Cases: Legal disputes between the society and certain members of the project have contributed to the o

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000209927Gerald Michael MisquittaArjun Singh Rathod Prop of Rasal Builders and Developers07/02/2022
CC12604567Rachna Rajiv JainARJUNSINGH BHOORSINGH RATHORE21/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 May 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 May 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Jun 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Jun 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed85

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A 25-26.pdf19 Aug 2026
Withdrawal Update Form 1File: form 1.pdf14 Aug 2026
Withdrawal Update Form 2File: form 2.pdf14 Aug 2026
Withdrawal Update Form 3File: form 3.pdf14 Aug 2026
Withdrawal Update Form 1File: FORM 1_JAN TO MAR26.pdf12 Aug 2026
Withdrawal Update Form 1File: FORM 1_JAN TO MAR26.pdf12 Aug 2026
Withdrawal Update Form 2File: FORM 2_JAN TO MAR26.pdf12 Aug 2026
Withdrawal Update Form 2File: FORM 2_JAN TO MAR26.pdf12 Aug 2026
Withdrawal Update Form 3File: form 3.pdf12 Aug 2026
Withdrawal Update Form 3File: form 3.pdf12 Aug 2026
Withdrawal Update Form 1File: FORM 1_JAN TO MAR26.pdf10 Aug 2026
Withdrawal Update Form 2File: FORM 2_JAN TO MAR26.pdf10 Aug 2026
Withdrawal Update Form 3File: FORM 3_JAN TO MAR26.pdf10 Aug 2026
Withdrawal Update Form 1File: FORM 1 July to Sept2025.pdf7 Aug 2026
Withdrawal Update Form 1File: FORM 1_Oct to Dec2025.pdf7 Aug 2026
Withdrawal Update Form 2File: revised form 2.pdf7 Aug 2026
Withdrawal Update Form 2File: form 2.pdf7 Aug 2026
Withdrawal Update Form 3File: form 3.pdf7 Aug 2026
Withdrawal Update Form 3File: FORM 3_Oct to Dec2025.pdf7 Aug 2026
Withdrawal Update Form 1File: FORM 1_April to June2025.pdf6 Aug 2026
Withdrawal Update Form 2File: FORM 2 _April to June 2025.pdf6 Aug 2026
Withdrawal Update Form 3File: FORM 3 _April to June 2025.pdf6 Aug 2026
Declaration in FORM BFile: FORM B_.pdf23 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1_ARCHITECT CERTIFICATE.pdf23 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 _ ENGINEER CERTIFICATE.pdf23 Jun 2025
Commencement Certificates / NA Order for plotted developmentFile: 2469387_FurtherCC_signed.pdf23 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A_ QUALITY ASSURANCE.pdf23 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT CERTIFICATE.pdf4 Jun 2025
Certificates of CA (Form 3)File: FORM 3.pdf4 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEER CERTIFICATE.pdf4 Jun 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold as on 31_03_2025.pdf4 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FROM 2A QUALITY ASSURANCE.pdf4 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1.pdf17 May 2025
Certificates of CA (Form 3)File: form 3 - CA certificate - July to Sept 2024_compressed.pdf17 May 2025
Certificates of CA (Form 3)File: Form 3 - CA certificate - Oct to Dec 2024_compressed.pdf17 May 2025
Certificates of CA (Form 3)File: Form 3 Priya CHS 31-03-2025.pdf17 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 1 Architect Apr to Jun 2024.pdf17 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf17 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - Architect - Apr to Jun 2023.pdf9 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - Architect - Jul to Sept 2023.pdf9 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - Architect - Oct to Dec 2023.pdf9 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - Architect - Jan to Mar 2024.pdf9 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A-23-24.pdf9 Jul 2024
Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD - UNSOLD.pdf9 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5-23-24-SIGNED.pdf9 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 -2021-22 (1).pdf29 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 - 2022-23 (1).pdf29 Jun 2023
Details of encumbrances concerned to FinanceFile: DETAILS OF LEGAL.pdf27 Jun 2023
Details of encumbrances concerned to LegalFile: DETAILS OF LEGAL.pdf27 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE FORM 1.pdf27 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf27 Jun 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD.pdf27 Jun 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: INTEREST IN OTHER.pdf27 Jun 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: SEPERATE BANK AC DETAILS.pdf27 Jun 2023
Deviation Report with respect to Allotment letterFile: DEVIATION ALLOTMENT LETTER.pdf27 Jun 2023
Deviation Report with respect to model copy of AgreementFile: DEVIATION AGREEMENT FOR SALE.pdf27 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Certificate - RBD.pdf6 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM5-FY 2019-20.pdf6 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM5-FY 2020-21.pdf6 Jun 2022
Building plan approvalFile: IOD (2).pdf4 Jun 2022
Building plan approvalFile: IOD PLAN.pdf4 Jun 2022
Building Plan Approval (IOD)File: IOD (2).pdf4 Jun 2022
Building Plan Approval (IOD)File: IOD PLAN.pdf4 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: C C _FirstCC.pdf4 Jun 2022
Declaration about Commencement CertificateFile: Declaraton about C C.pdf27 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera 1.pdf27 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineer Certificate_compressed.pdf27 Apr 2022
Disclosure of sold/ booked inventoryFile: Disclosure for Sold.pdf27 Apr 2022
Certificates of CA (Form 3)File: Form 3_ CA_compressed.pdf27 Apr 2022
Commencement Certificates / NA Order for plotted developmentFile: Textile Committee Order Copy1.pdf31 May 2019
Commencement Certificates / NA Order for plotted developmentFile: Redevlopment Proposal approved by Members1.pdf31 May 2019
Commencement Certificates / NA Order for plotted developmentFile: MX-M356N_20190529_132741.pdf31 May 2019
Certificates of CA (Form 3)File: CA Certificate.PDF16 May 2019
Layout approvalFile: LAYOUT PLAN RASAL.PDF15 May 2019
PAN CardFile: Pan Card Copy.pdf15 May 2019
Copy of the legal title reportFile: Title Certificate Priya CHS Ltd.pdf15 May 2019
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN RASAL.PDF15 May 2019
Commencement Certificates / NA Order for plotted developmentFile: Declaration cum Confirmation commencement certificate.pdf15 May 2019
Proforma of Allotment letterFile: allotment letter.pdf15 May 2019
Building plan approvalFile: I O D.pdf14 May 2019

How this compares with Mumbai Suburban

10%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 48 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VILE PARLE WEST6,700+ in Mumbai Suburban

2 kmPRIYA CO-OPERATIVE HOUSICompleted 43Lapsed / revoked 14Other 16Dot size: filed unitsN

Filed coordinates, straight-line distance. 73 registered projects within 2 km.

Builder: ARJUNSINGH BHOORSINGH RATHORE

ARJUNSINGH BHOORSINGH RATHORE has 1 registration on MahaRERA, including PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.?

The registered promoter entity is ARJUNSINGH BHOORSINGH RATHORE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.?

The professionals named in the filing: Architect: KALPESH JAIN; Engineer: HARESH S PATEL; Chartered Accountant: RAHUL AGRAWAL; Chartered Accountant: ARPAJ AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PRIYA CO-OPERATIVE HOUSING SOCIETY LTD. to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.