Home / Browse projects / Raigarh, Maharashtra / Prime Ruby

Registered No litigation declared Others project

Prime Ruby

By Prime Abhishek Buildcon

RG-MH-91528 · RERA P52000046197 · Last updated on MahaRERA portal: 4 Aug 2026

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 24 months from the original
6 of 11Construction stages donefurthest along: Internal walls, 90%
2 of 38Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 77 documents Report an error

Prime Ruby is a Others project by Prime Abhishek Buildcon in Raigarh, Maharashtra, registered with MahaRERA as P52000046197 on 20 Jun 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 36 of the 38 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NamePrime Ruby
  • TypeOthers
  • Location
    • Sector 3
    • Pushpak
    • Dapoli
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000046197
  • ReraGenie IDRG-MH-91528

Builder

  • NamePrime Abhishek Buildcon
  • Entity typePartnership
  • PartnersMangesh Vasant Warule, Avinash Dagdu Jagdale
  • Other registrations3 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredJun 2022First promiseDec 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on20 Jun 2022
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed77 files

Current status

95%36 of 38 units booked
65.2%Work done, per cost certificate

Figures as on 4 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Prime RubyNA7734438

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

Prime Ruby: 63% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 4 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed5

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots5
Closed/Covered5

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area470 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on21 Jul 2026
LandownerVillageDistrict
Chanchaldas SDG Reality LLPjaysingpurKolhapur

Approvals and building plan

Sanctioning authorityCity And Industrial Development Corporation
Permissible FSI1550.47
Proposed, not sanctioned1,147 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHARDA TERRACES, PLOT NO 65,SECTOR-11,CBD BELAPUR
Estimated costRs 3.17 cr
Cost incurredRs 2.07 cr
Work done65.18%
BuildingWingEstimatedIncurred
Prime RubyNARs 2.96 crRs 2.00 cr
-NARs 20.85 lakhRs 6.66 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVastuyog Architects
EngineerSK Consultants & Engineers
EngineerStrucon Consulting Engineers
EngineerMangesh Warle
Chartered AccountantNB Sayed & Associates
Chartered AccountantMulani and Associates
PartnerRole in project
Prime Abhishek Buildcon-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA22072621829Dec 2024 → Dec 2026

Reason as filed by the promoterThe project completion timeline has been impacted due to ongoing coordination with various statutory authorities and the time involved in obtaining requisite approvals and compliances. Further, certain minor finishing and allied works are presently in progress, and the Occupancy Certificate (OC) from the competent authority is awaited. In view of the above, additional time is required to complete the remaining works and fulfill all regulatory formalities. Given the circumstances, we kindly request an extension until 31-12-2026, to complete the project and fulfill all regulatory requirements.

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000480004Karishma Karunakar ShettyPRIME ABHISHEK BUILDCON04/05/2024
CC12503537Surbhi AroraPrime Abhishek Buildcon04/10/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Jun 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Feb 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Feb 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed77

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 (June 2026) Ruby.pdf4 Aug 2026
Withdrawal Update Form 1File: Form 1 (June 2026) Ruby.pdf4 Aug 2026
Withdrawal Update Form 1File: Form 1 (June 2026) Ruby.pdf4 Aug 2026
Withdrawal Update Form 1File: Form 1 (June 2026) Ruby.pdf4 Aug 2026
Withdrawal Update Form 1File: Form 1 (June 2026) Ruby.pdf4 Aug 2026
Withdrawal Update Form 1File: Form 1 (June 2026) Ruby.pdf4 Aug 2026
Withdrawal Update Form 1File: Form 1 (June 2026) Ruby.pdf4 Aug 2026
Withdrawal Update Form 2File: Form 2 - Prime Ruby March 24.pdf4 Aug 2026
Withdrawal Update Form 2File: Form 2 (June 2026) Ruby.pdf4 Aug 2026
Withdrawal Update Form 2File: Form 2 (June 2026) Ruby.pdf4 Aug 2026
Withdrawal Update Form 2File: Form 2 (June 2026) Ruby.pdf4 Aug 2026
Withdrawal Update Form 2File: Form 2 (June 2026) Ruby.pdf4 Aug 2026
Withdrawal Update Form 2File: Form 2 (June 2026) Ruby.pdf4 Aug 2026
Withdrawal Update Form 2File: Form 2 (June 2026) Ruby.pdf4 Aug 2026
Withdrawal Update Form 3File: Form 3 (June 2026) Ruby.pdf4 Aug 2026
Withdrawal Update Form 3File: Form 3 (June 2026) Ruby.pdf4 Aug 2026
Withdrawal Update Form 3File: Form 3 (June 2026) Ruby.pdf4 Aug 2026
Withdrawal Update Form 3File: Form 3 (June 2026) Ruby.pdf4 Aug 2026
Withdrawal Update Form 3File: Form 3 (June 2026) Ruby.pdf4 Aug 2026
Withdrawal Update Form 3File: Form 3 (June 2026) Ruby.pdf4 Aug 2026
Withdrawal Update Form 3File: Form 3 (June 2026) Ruby.pdf4 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A 25-26 Ruby.pdf4 Aug 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8 Architect’s Certificate of Percentage of Completion of Work (Form 1) (1).pdf15 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 11 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf15 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf15 Feb 2025
Other - TechnicalFile: img20250211_12155366.pdf12 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Prime Ruby as on Sep 2024.pdf29 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Prime Ruby as on Sep 2024.pdf29 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 PRIME RUBY as on Sep 2024.pdf30 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Prime Ruby June 24.pdf15 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Prime Ruby as on 30-06-2024.pdf14 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Prime Ruby March 24.pdf12 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Prime Ruby as on 31-03-2024.pdf12 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Prime Ruby form SAMPLE pl267.pdf5 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Prime Ruby Dec 23.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Prime Ruby as on 31-12-2023.pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Prime Ruby as on Dec 2023.pdf9 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Prime Ruby as on 30-09-2023.pdf26 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Prime Ruby Jun 23 - Form 2.pdf26 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Prime Ruby Sept 23 - Form 2.pdf26 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Prime Ruby as on 30-06-2023.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Prime Ruby as on 30-09-2023.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Prime Ruby June 22 - Form 2.pdf12 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Prime Ruby September 22 - Form 2.pdf12 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Prime Ruby as on March 23.pdf12 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Prime Ruby as on 30-06-2022.pdf12 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Prime Ruby as on 30-09-2022.pdf12 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Prime Ruby as on 31-03-2023.pdf12 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Prime Ruby Dec 22 - Form 2.pdf29 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Prime Ruby as on December 2022.pdf29 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RUBY Form 1.pdf13 Apr 2023
Layout approvalFile: Layout Plan_compressed-1.pdf3 Feb 2023
Building plan approvalFile: Layout Plan_compressed-1.pdf3 Feb 2023
Building plan approvalFile: Layout Plan_compressed-2.pdf3 Feb 2023
Building plan approvalFile: Layout Plan_compressed-3.pdf3 Feb 2023
Copy of Layout Approval (in case of layout)File: Layout Plan_compressed-1.pdf3 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: Layout Plan_compressed-1.pdf3 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: Layout Plan_compressed-2.pdf3 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: Layout Plan_compressed-3.pdf3 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf3 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Prime Ruby (1).pdf24 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Prime Ruby (2).pdf24 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Prime Ruby (3).pdf24 Jan 2023
Copy of the legal title reportFile: Title_Scan.pdf10 Jun 2022
Proforma of Allotment letterFile: Agreement for Sale_Prime Ruby.pdf10 Jun 2022
Proforma of Allotment letterFile: Allotment Letter_Prime Landmark.pdf10 Jun 2022
CERSAI detailsFile: CERSAI_Search_Report_200239373749_For_Asset_Based_Search_09_06_2022_15_55_04_024.pdf9 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Prime Ruby Form 3_merged_compressed.pdf9 Jun 2022
Details of encumbrancesFile: Encumbrance Letter.pdf7 Jun 2022
Declaration about Commencement CertificateFile: Format D (32).pdf7 Jun 2022
Declaration in FORM BFile: Form B (Promoter).pdf7 Jun 2022
Layout approvalFile: Plan 267.pdf6 Jun 2022
Building plan approvalFile: Plan 267.pdf6 Jun 2022
PAN CardFile: PAB pan card.pdf6 Jun 2022
Copy of Layout Approval (in case of layout)File: Plan 267.pdf6 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan 267.pdf6 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: CC -267.pdf6 Jun 2022

How this compares with Raigarh

95%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 24 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Prime Ruby on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pushpak5,900+ in Raigarh

Builder: Prime Abhishek Buildcon

Prime Abhishek Buildcon has 4 registrations on MahaRERA, including Prime Ruby and Prime Pearl. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Prime Ruby is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Prime Ruby?

The registered promoter entity is Prime Abhishek Buildcon, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Prime Ruby?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Prime Ruby?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Prime Ruby?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Prime Ruby?

The professionals named in the filing: Architect: Vastuyog Architects; Engineer: SK Consultants & Engineers; Engineer: Strucon Consulting Engineers; Engineer: Mangesh Warle; Chartered Accountant: NB Sayed & Associates; Chartered Accountant: Mulani and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Prime Ruby?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Prime Ruby. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Prime Ruby to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.