ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / PRIDE OF UTTAN

Registration lapsed No litigation declared Residential / Group Housing project

PRIDE OF UTTAN

By BRICKSCITY DEVELOPERS PRIVATE LIMITED

RG-MH-55959 · RERA P51700030690 · Last updated on MahaRERA portal: 31 May 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 43 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
1 of 11Construction stages donefurthest along: Basement (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 15 documents Report an error

PRIDE OF UTTAN is a Residential / Group Housing project by BRICKSCITY DEVELOPERS PRIVATE LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700030690 on 8 Sep 2021. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 43 months from the original filing.

At a glance

Project

  • NamePRIDE OF UTTAN
  • TypeResidential / Group Housing
  • Location
    • SURVEY NO 117 HISSA NO 3
    • UTTAN
    • Mira-Bhayandar (M Corp.)
    • Thane
    • 401106
  • Pincode401106
  • RERA no.P51700030690
  • ReraGenie IDRG-MH-55959

Builder

  • NameBRICKSCITY DEVELOPERS PRIVATE LIMITED
  • Entity typeCompany
  • ChairpersonANKIT ASHOK OSTWAL
  • DirectorsASHOK PRITHVIRAJ OSTWAL, MADHU ASHOK OSTWAL
  • Other registrations2 more →
  • No longer live3 lapsed, de-registered or revoked

Key dates

10 months past promisethis monthRegisteredSep 2021First promiseMay 2022Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on8 Sep 2021
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 27 May 2022)
  • Buildings1 building record
  • Documents filed15 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PRIDE OF UTTANNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 31 May 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

PRIDE OF UTTAN: 9% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 31 May 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed4

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots4
Closed/Covered4

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area960 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
DINESH SINGHMira-Bhayandar (M Corp.)Thane

Approvals and building plan

Permissible FSI460.0
Proposed, not sanctioned460 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJESAL PARK, BHAYANDER EAST

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMARIO ECORREA
EngineerMARIO ECORREA
Chartered AccountantABHISHEK SURANA
PartnerRole in project
BRICKSCITY DEVELOPERS PRIVATE LIMITED-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700011933May 2022 → May 2023

Reason as filed by the promoterDRASTICALLY INCREASE IN PRICE OF MATERIALS.

EXT51700025404May 2022 → Dec 2025

Reason as filed by the promoterAs the Project is in Remote Are Due To internal and financial issue, The Construction work of the Project is Delayed

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Aug 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Aug 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Aug 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed15

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: CIR 29.pdf31 May 2022
CERSAI detailsFile: CERSAI_Search_Report_200238378531_For_Asset_Based_Search_28_05_2022_20_16_18_944.pdf28 May 2022
Layout approvalFile: PLAN COPY UTTAN.pdf25 Aug 2021
Building plan approvalFile: PLAN COPY UTTAN.pdf25 Aug 2021
Copy of Layout Approval (in case of layout)File: PLAN COPY UTTAN.pdf25 Aug 2021
Building Plan Approval / NA Order for plotted developmentFile: PLAN COPY UTTAN.pdf25 Aug 2021
Copy of the legal title reportFile: New Legal Title.pdf18 Aug 2021
PAN CardFile: BrickscityDevelopers PAN Card.pdf11 Aug 2021
Declaration about Commencement CertificateFile: CC declaration.pdf11 Aug 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Pride of Uttan.pdf11 Aug 2021
Details of encumbrancesFile: Encumbrance Ankit.pdf10 Aug 2021
Commencement Certificates / NA Order for plotted developmentFile: CC - ANKIT.pdf10 Aug 2021
Declaration in FORM BFile: Form B Ankit.pdf10 Aug 2021
Proforma of Allotment letterFile: Agreement ANKIT.pdf10 Aug 2021
Proforma of Allotment letterFile: Allotment Letter Ankit.pdf10 Aug 2021

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 43 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PRIDE OF UTTAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near UTTAN7,600+ in Thane

Builder: BRICKSCITY DEVELOPERS PRIVATE LIMITED

BRICKSCITY DEVELOPERS PRIVATE LIMITED has 3 registrations on MahaRERA, including BRICKS SABURI and PRIDE OF UTTAN. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that PRIDE OF UTTAN shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PRIDE OF UTTAN is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PRIDE OF UTTAN?

The registered promoter entity is BRICKSCITY DEVELOPERS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PRIDE OF UTTAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PRIDE OF UTTAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PRIDE OF UTTAN?

The professionals named in the filing: Architect: MARIO ECORREA; Engineer: MARIO ECORREA; Chartered Accountant: ABHISHEK SURANA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PRIDE OF UTTAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PRIDE OF UTTAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PRIDE OF UTTAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.