Home / Browse projects / Ahmednagar, Maharashtra / PREMIUM ICON

Registered No litigation declared Residential / Group Housing project

PREMIUM ICON

By PREMIUM BUILDERS & DEVELOPERS

RG-MH-14047 · RERA P52200030905 · Last updated on MahaRERA portal: 7 Feb 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Ahmednagar registration emailed to you, free during the pilot beta.
Aug 2027Possession promisedno revision filed
11 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 50%
0Complaints at MahaRERAon this registration
Jump to the 91 documents Report an error

PREMIUM ICON is a Residential / Group Housing project by PREMIUM BUILDERS & DEVELOPERS in Ahmednagar, Maharashtra, registered with MahaRERA as P52200030905 on 29 Sep 2021. Possession is promised by 31 Aug 2027.

At a glance

Project

  • NamePREMIUM ICON
  • TypeResidential / Group Housing
  • Location
    • MAHARASHTRA
    • NAELGAON
    • Ahmadnagar (M Corp.)
    • Nagar
    • Ahmednagar
    • 414001
  • Pincode414001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52200030905
  • ReraGenie IDRG-MH-14047

Builder

  • NamePREMIUM BUILDERS & DEVELOPERS
  • Entity typePartnership
  • PartnersSHIVAJI MACHINDRA SHINDE, INDUBAI ARVIND NAGAWADE, ANUP LALCHANDRA HARAL, SARLA BABASAHEB WAKALE

Key dates

this monthRegisteredSep 2021PromisedAug 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Sep 2021
  • Promised completion31 Aug 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed91 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING WING ANA90000
BUILDING WING BNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 7 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 50%.

BUILDING WING A91%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING WING B23%
ActivityProgress
Excavation100%
Basement (if any)50%
Podiums (if any)50%
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 7 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes50%

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Open Space2
BuildingOpen SpaceTotal
BUILDING WING A11
BUILDING WING B11

Land and ownership4

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,059 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on18 Aug 2025
LandownerVillageDistrict
ABHAY KRUSHNARAO RAJEAhmadnagar (M Corp.)Ahmednagar
SHARDUL KRUSHNRAO RAJEAhmadnagar (M Corp.)Ahmednagar
SHARAYU AVINASH MANGALKARPune (M Corp.)Pune
KRUSHNAJI MARUTI RAJEPune (M Corp.)Pune

Approvals and building plan

Sanctioning authoritytown planning
Permissible FSI6165.74
Proposed, not sanctioned6,166 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAPMC MARKET YARD FIRST FLOOR AHMEDNAGAR

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMAYUR KOTHARI
EngineerBHALCHANDRA B SONAWANE
Chartered AccountantKIRAN P BHANDARI popatlal bhandari
PartnerRole in project
PREMIUM BUILDERS & DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Sep 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Aug 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Sep 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Aug 2027

Documents filed91

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 91 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1 Q 2 2025-26_0001.pdf7 Feb 2026
Form 2File: FORM 2 Q 2 2025-26_0001.pdf7 Feb 2026
Disclosure of Sold and Booked InventoryFile: INVENTORY.pdf7 Feb 2026
Form 3File: FORM 3.pdf7 Feb 2026
Building plan approval or NA orderFile: NA ORDER.pdf3 Sep 2025
Form 1File: FORM 1 Q1 2022-23_0001.pdf18 Aug 2025
Form 2File: FORM 2 Q1 2022-23_0001.pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY Q1 2022-23_0001.pdf18 Aug 2025
Form 3File: FORM 3.pdf18 Aug 2025
Form 1File: FORM 1 Q1 2023-24_0001.pdf18 Aug 2025
Form 2File: FORM 2 Q 1 2023-24_0001.pdf18 Aug 2025
Form 3File: FORM 3.pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY Q 1 2023-24_0001.pdf18 Aug 2025
Form 1File: FORM 1 Q1 2024-25_0001.pdf18 Aug 2025
Form 2File: FORM 2 Q1 2024-25_0001.pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY Q 1 2024-25_0001.pdf18 Aug 2025
Form 3File: FORM 3.pdf18 Aug 2025
Form 1File: FORM 1 Q1 2025-26_0001.pdf18 Aug 2025
Form 2File: FORM 2 Q 1 2025-26_0001.pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY Q 1 2025-26_0001.pdf18 Aug 2025
Form 3File: FORM 3.pdf18 Aug 2025
Form 1File: FORM 1 Q2 2021-22_0001.pdf18 Aug 2025
Form 2File: FORM Q 2 2021-22_0001.pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY Q 2 2021-22_0001.pdf18 Aug 2025
Form 3File: FORM 3.pdf18 Aug 2025
Form 1File: FORM 1 Q2 2022-23_0001.pdf18 Aug 2025
Form 2File: FORM 2 Q2 2022-23_0001.pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY Q 2 2022-23_0001.pdf18 Aug 2025
Form 3File: FORM 3.pdf18 Aug 2025
Form 1File: FORM1 Q2 2023-24_0001.pdf18 Aug 2025
Form 2File: FORM 2 Q 2 2023-24_0001.pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY Q 2 2023-24_0001.pdf18 Aug 2025
Form 3File: FORM 3.pdf18 Aug 2025
Form 1File: FORM 1 Q2 2024-25_0001.pdf18 Aug 2025
Form 2File: FORM 2 Q2 2024-25_0001.pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY Q 2 2024-25_0001.pdf18 Aug 2025
Form 3File: FORM 3.pdf18 Aug 2025
Form 1File: FORM 1 Q3 2021-22_0001.pdf18 Aug 2025
Form 2File: FORM 2 Q3 2021-22_0001.pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY Q 3 2021-22_0001.pdf18 Aug 2025
Form 3File: FORM 3.pdf18 Aug 2025
Form 1File: FORM 1 Q3 2022-23_0001.pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY Q 3 2022-23_0001.pdf18 Aug 2025
Form 2File: FORM 2 Q3 2022-23_0001.pdf18 Aug 2025
Form 3File: FORM 3.pdf18 Aug 2025
Form 1File: FORM 1 Q3 2023-24_0001.pdf18 Aug 2025
Form 2File: FORM 2 Q 3 2023-24_0001.pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY Q 3 2023-24_0001.pdf18 Aug 2025
Form 3File: FORM 3.pdf18 Aug 2025
Form 1File: FORM 1 Q3 2024-25_0001.pdf18 Aug 2025
Form 2File: FORM 2 Q3 2024-25_0001.pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY Q 3 2024-25_0001.pdf18 Aug 2025
Form 3File: FORM 3.pdf18 Aug 2025
Form 1File: FORM 1 Q4 2022-23_0001.pdf18 Aug 2025
Form 2File: FORM 2 Q 4 2022-23_0001.pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY Q 4 2022-23_0001.pdf18 Aug 2025
Form 3File: FORM 3.pdf18 Aug 2025
Form 1File: FORM 1 Q4 2023-24_0001.pdf18 Aug 2025
Form 2File: FORM 2 Q4 2023-24_0001.pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY Q 4 2023-24_0001.pdf18 Aug 2025
Form 3File: FORM 3.pdf18 Aug 2025
Form 1File: FORM 1 Q4 2024-25_0001.pdf18 Aug 2025
Form 2File: FORM 2 Q4 2024-25_0001.pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY Q 4 2024-25_0001.pdf18 Aug 2025
Form 3File: FORM 3.pdf18 Aug 2025
Form 3File: FORM 3.pdf12 Aug 2025
Form 1File: mayur Kothari.pdf12 Aug 2025
Form 2File: ENGINEER'S CERTIFICATE.pdf12 Aug 2025
Disclosure of Sold and Booked InventoryFile: form b.pdf12 Aug 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: primuim buldres n developer.pdf2 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Premium Builders RERA.pdf20 Feb 2023
Copy of the legal title reportFile: legal title finallllll.pdf23 Sep 2021
OtherFile: leagal title latest.pdf21 Sep 2021
Declaration in FORM BFile: form b.pdf6 Sep 2021
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf2 Sep 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: mayur Kothari.pdf2 Sep 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE.pdf2 Sep 2021
Details of encumbrancesFile: self declaration certificate.pdf27 Aug 2021
Commencement Certificates / NA Order for plotted developmentFile: NA COMMENCEMENT CERTIFICATE.pdf27 Aug 2021
OtherFile: NA COMMENCEMENT CERTIFICATE.pdf27 Aug 2021

How this compares with Ahmednagar

7%of Ahmednagar projects moved their completion datethis one has not
28%of Ahmednagar registrations have lapsed or been cancelledthis one is on the register

Computed across the 490+ Ahmednagar projects on ReraGenie, from their own filings.

Keep PREMIUM ICON on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NAELGAON490+ in Ahmednagar

2 kmPREMIUM ICONCompleted 5Lapsed / revoked 3Other 4Dot size: filed unitsN

Filed coordinates, straight-line distance. 12 registered projects within 2 km.

Builder: PREMIUM BUILDERS & DEVELOPERS

PREMIUM BUILDERS & DEVELOPERS has 1 registration on MahaRERA, including PREMIUM ICON. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Ahmednagar district page.

Frequently asked questions

What are my rights if PREMIUM ICON is delayed beyond 31 Aug 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PREMIUM ICON?

The registered promoter entity is PREMIUM BUILDERS & DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PREMIUM ICON?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PREMIUM ICON?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PREMIUM ICON?

The professionals named in the filing: Architect: MAYUR KOTHARI; Engineer: BHALCHANDRA B SONAWANE; Chartered Accountant: KIRAN P BHANDARI popatlal bhandari. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PREMIUM ICON?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PREMIUM ICON. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PREMIUM ICON to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.