ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / PRASANNA PARADISE

Registered No litigation declared Residential / Group Housing project

PRASANNA PARADISE

By PARAS PROPERTIES

RG-MH-74922 · RERA P52100048666 · Last updated on MahaRERA portal: 16 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 4 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jan 2027Possession promisedmoved 4 months from the original
8 of 11Construction stages donefurthest along: Basement (if any), 0%
14 of 42Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 63 documents Report an error

PRASANNA PARADISE is a Residential / Group Housing project by PARAS PROPERTIES in Pune, Maharashtra, registered with MahaRERA as P52100048666 on 12 Jan 2023. Possession is promised by 30 Jan 2027. The completion date has moved by 4 months from the original filing. 28 of the 42 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NamePRASANNA PARADISE
  • TypeResidential / Group Housing
  • Location
    • SANE CHOWK MORE WASTI
    • CHIKHLI
    • Chikhali
    • Haveli
    • Pune
    • 412114
  • Pincode412114
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100048666
  • ReraGenie IDRG-MH-74922

Builder

  • NamePARAS PROPERTIES
  • Entity typePartnership
  • PartnersRAMBHAU KAHNDU PANDHARKAR, KARTIK RAMBHAU PANDHARKAR
  • Other registrations1 more →

Key dates

this monthRegisteredJan 2023First promiseSep 2026Revised toJan 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on12 Jan 2023
  • Promised completion30 Jan 2027
  • Revised completionRevised to 30 Jan 2027 (originally 30 Sep 2026)
  • Buildings1 building record
  • Documents filed63 files

Current status

67%28 of 42 units booked
96.5%Work done, per cost certificate

Figures as on 16 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PRASANNA PARADISENA6642042

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

PRASANNA PARADISE: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 16 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed71

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots71
Closed/Covered21
Open Space50

Land and ownership9

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area922 sq m
Land owned byThe promoter, with other names on the file
Named landowners9
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on3 Jul 2025
LandownerVillageDistrict
KUNDLIK GENBA MOREChikhaliPune
MANDA KUNDLIK MOREChikhaliPune
SOMNATH KUNDLIK MOREChikhaliPune
SHARDDHA SOMNATH MOREChikhaliPune
SUNITA GOPAL NAKAHTEChikhaliPune
SUBHDARA RAMBHAU PANDHARKARChikhaliPune
ASHA SUNIL BHONDVERavetPune
SUSHMA NAVNATH WASWADAMBEGAON BkPune
SARIKA ANIL GADHAVEThane (M Corp.)Thane

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI2211.24
Proposed, not sanctioned2,211 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShetty Complex, Thermax Chowk, Pune
Estimated costRs 4.80 cr
Cost incurredRs 4.63 cr
Work done96.54%
BuildingWingEstimatedIncurred
PRASANNA PARADISENARs 4.50 crRs 4.40 cr
-NARs 30.00 lakhRs 23.07 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectROHAN S LUNAWAT
EngineerANIL B MAHADIK
Chartered AccountantCA Vivek Nandkishor Lahoti
Chartered AccountantGanesh Sunil Mandlecha
PartnerRole in project
PARAS PROPERTIES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P52100048666/WarSep 2026 → Jan 2027

Reason as filed by the promoterNA

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Oct 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Oct 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Oct 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Oct 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jan 2027

Documents filed63

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A 25-26.pdf16 Sep 2026
Form 2A (FY 2024-2025)File: Form 2A 24-25.pdf16 Sep 2026
Withdrawal Update Form 1File: form 1 Q3.pdf15 Sep 2026
Withdrawal Update Form 1File: Form 1 Q1.pdf15 Sep 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate Q4.pdf15 Sep 2026
Withdrawal Update Form 2File: Form 2 Q1.pdf15 Sep 2026
Withdrawal Update Form 3File: Form 3 CA certificate.pdf15 Sep 2026
Withdrawal Update Form 3File: Form 3 CA Certificate Q1_compressed.pdf15 Sep 2026
Withdrawal Update Form 1File: form 1.pdf4 Feb 2026
Withdrawal Update Form 2File: Form 2 q3.pdf4 Feb 2026
Withdrawal Update Form 3File: form 3 singh_1_11zon.pdf4 Feb 2026
Withdrawal Update Form 1File: Form 1.pdf28 Jan 2026
Withdrawal Update Form 1File: Form 1.pdf28 Jan 2026
Withdrawal Update Form 2File: Form 2.pdf28 Jan 2026
Withdrawal Update Form 2File: Form 2 q2.pdf28 Jan 2026
Withdrawal Update Form 3File: form 3 with sign_1_11zon.pdf28 Jan 2026
Withdrawal Update Form 3File: form 3 with sign_2_11zon.pdf28 Jan 2026
Form 5 (FY 2022-2023)File: Form 5.pdf30 Sep 2025
Form 5 (FY 2024-2025)File: form 5 24-25 with sign.pdf29 Sep 2025
Form 5 (FY 2023-2024)File: Form 5.pdf29 Sep 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf5 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf5 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf5 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 3rd 2024.pdf29 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 3rd 2024.pdf29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 3rd 2024.pdf29 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf14 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form 1 Q1.pdf20 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer’s Certificate Form 2 Q1.pdf20 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form 1 Q1.pdf17 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate 2.pdf17 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q1.pdf17 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: PARAS Form 3 Q4_compressed.pdf26 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q3_compressed.pdf18 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf6 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf6 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q1_compressed.pdf13 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q2_compressed.pdf13 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 compressed.pdf30 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf22 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf22 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 25042023 Form 3 Prasana Paradise_compressed.pdf22 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Prasanna Paradise.pdf6 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Rambhau Pandharkar.pdf6 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Kartik Rambhau Pandharkar.pdf6 Jan 2023
Proforma of Agreement for saleFile: RERA Draft 20221229.pdf29 Dec 2022
Deviation Report with respect to model copy of AgreementFile: Detailed deviation report - Agreement.pdf26 Dec 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank declaration.pdf20 Dec 2022
Building plan approvalFile: Sanction plan merged.pdf18 Oct 2022
Layout approvalFile: Sanction plan merged.pdf18 Oct 2022
Copy of the legal title reportFile: Search Report.pdf18 Oct 2022
Details of encumbrances concerned to FinanceFile: Legal Encumbrances.pdf18 Oct 2022
Details of encumbrances concerned to LegalFile: Legal Encumbrances.pdf18 Oct 2022
Copy of Layout Approval (in case of layout)File: Sanction plan merged.pdf18 Oct 2022
Building Plan Approval / NA Order for plotted developmentFile: Sanction plan merged.pdf18 Oct 2022
Declaration about Commencement CertificateFile: Decrlaration about commencement certificate.pdf18 Oct 2022
Declaration in FORM BFile: Affidavit Developer.pdf18 Oct 2022
CERSAI detailsFile: undertaking no security deposit cersai.pdf18 Oct 2022
Deviation Report with respect to Allotment letterFile: Deviation sheet.pdf18 Oct 2022
PAN CardFile: PAN - PARAS PROPERTIES.pdf15 Oct 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf15 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect’s Certificate.pdf15 Oct 2022
Proforma of Allotment letterFile: model form allotment letter - Copy.pdf15 Oct 2022

How this compares with Pune

67%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 4 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PRASANNA PARADISE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHIKHLI13,700+ in Pune

2 kmPRASANNA PARADISECompleted 46Lapsed / revoked 20Other 20Dot size: filed unitsN

Filed coordinates, straight-line distance. 86 registered projects within 2 km.

Builder: PARAS PROPERTIES

PARAS PROPERTIES has 2 registrations on MahaRERA, including PRASANNA PARADISE and PARAS SHAGUN. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if PRASANNA PARADISE is delayed beyond 30 Jan 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PRASANNA PARADISE?

The registered promoter entity is PARAS PROPERTIES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PRASANNA PARADISE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PRASANNA PARADISE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PRASANNA PARADISE?

The professionals named in the filing: Architect: ROHAN S LUNAWAT; Engineer: ANIL B MAHADIK; Chartered Accountant: CA Vivek Nandkishor Lahoti; Chartered Accountant: Ganesh Sunil Mandlecha. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PRASANNA PARADISE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PRASANNA PARADISE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PRASANNA PARADISE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.