Red flags
- No red flags in this filing
Clear
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
PRAMUR ESTONIA is a Residential/Group Housing project by PRAMUR CONSTRUCTIONS PVT LTD in Mysore, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1268/378/PR/171015/000707 on 15 Oct 2017. Possession is promised by 10 Dec 2017.
At a glance
Project
- NamePRAMUR ESTONIA
- TypeResidential/Group Housing
- Location
- MYSORE
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1268/378/PR/171015/000707
- ReraGenie IDRG-KA-60911
Builder
- NamePRAMUR CONSTRUCTIONS PVT LTD
- Entity typeCompany
- CINU45203KA1991PTC012210
- Authorized SignatorySRINIVAS MURTHY PRAKASH
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on15 Oct 2017
- Promised completion10 Dec 2017
- Revised completionNone
- Buildings1 building record
- Documents filed42 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Pramur Estonia | - | - | - | 9 | 0 | 9 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RACHANE... the build art |
| Engineer | YASHAS CONSULTANTS |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed42
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1268/378/PR/171015/000707 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: CER_ROC.jpg | - |
| Commencement Certificate | - |
| Estonia | - |
| Estonia | - |
| SALE DEED-DRAFT | - |
| AGREEMENT_FOR_SALE_DRAFT | - |
| Property Papers | - |
| Estonia | - |
| Estonia | - |
| Booking_Form | - |
| Estonia brochure | - |
| FORM OF SANCTION | - |
| Estonia brochure | - |
| Estonia - EC_1964-2017 | - |
| katha-rakesh | - |
| DEVELOPMENT AGREEMENT | - |
| ESTONIA_legal paper | - |
| Balance Sheet 2015 - 2016File: BALANCE SHEET-2016.pdf | - |
| Balance Sheet 2014 - 2015File: BS-2014-15.pdf | - |
| Balance Sheet 2013 - 2014File: BS-2014.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: P & L-2016.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: PL-2014-15.pdf | - |
| Audited Profit and Loss Statement 2013 - 2014File: PL-2014.pdf | - |
| Director's Report 2015 - 2016File: directors reporit201516.pdf | - |
| Director's Report 2014 - 2015File: directors report201415.pdf | - |
| Director's Report 2013 - 2014File: DIRECTRORS REPORT.pdf | - |
| Cash Flow Statement 2015 - 2016File: Cashflow201516_rev.pdf | - |
| Cash Flow Statement 2014 - 2015File: Cashflow201415_rev.pdf | - |
| Auditor's Report 2015 - 2016File: auditorsreoport201516 (2).pdf | - |
| Auditor's Report 2014 - 2015File: Auditors_report2015.pdf | - |
| Auditor's Report 2013 - 2014File: Auditors_report2014(1).pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: IT RETURNS _ 2015-16.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: ITR 201415.pdf | - |
| Income Tax Return Acknowledgement 2013 - 2014File: ITR201314.pdf | - |
| FORMB | - |
| Prospectus/BrochureFile: Estonia Brochure.pdf | - |
| Advertisement Copy 1File: Estonia Brochure.pdf | - |
| Tower Excel SheetFile: PRM-KA-RERA-1268-378-PR-171015-000707.xlsx | - |
| Occupancy CertificateFile: Application for CR.pdf | - |
| Completion certificateFile: Application for CR.pdf | - |
| Registered Agreement of SaleFile: AGREEMENT FOR SALE-compressed.pdf | - |
| Registered conveyance deed for an individual unitFile: DEEDOFSALE_C1_reduce.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mysore
Computed across the 700+ Mysore projects on ReraGenie, from their own filings.
Keep PRAMUR ESTONIA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mysore700+ in Mysore
Filed coordinates, straight-line distance. 15 registered projects within 2 km.
Construction of 2446 Dus at Mandakalli Mysore
MCC
Construction of 1440 houses at lalithadripura
City Corporation Myuru
Construction of 843 G+2 Houses
Chief Officer
JAL VAYU TOWERS
AIR FORCE NAVAL HOUSING BOARD
Sanaklp Temple Tree
Sankalp Constructions private limited
SANKALP CROWN PHASE 1
SANKALP CONSTRUCTIONS PRIVATE LIMITED
See every Mysore project, with the district possession charts
Builder: PRAMUR CONSTRUCTIONS PVT LTD
PRAMUR CONSTRUCTIONS PVT LTD has 1 registration on RERA Karnataka, including PRAMUR ESTONIA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Mysore district page.
Frequently asked questions
What are my rights if PRAMUR ESTONIA is delayed beyond 10 Dec 2017?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of PRAMUR ESTONIA?
The registered promoter entity is PRAMUR CONSTRUCTIONS PVT LTD, a company as per the filing. Its CIN U45203KA1991PTC012210 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in PRAMUR ESTONIA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at PRAMUR ESTONIA?
The professionals named in the filing: Architect: RACHANE... the build art; Engineer: YASHAS CONSULTANTS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PRAMUR ESTONIA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback