Home / Browse projects / Thane, Maharashtra / Pool City Lakshadweep Villa
Pool City Lakshadweep Villa
By Meravilla Infra Private Limited
RG-MH-32210 · RERA PR1330002500101 · Last updated on MahaRERA portal: 1 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 1 complaint at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Pool City Lakshadweep Villa is a Residential / Group Housing project by Meravilla Infra Private Limited in Thane, Maharashtra, registered with MahaRERA as PR1330002500101 on 23 Jun 2025. Possession is promised by 31 Dec 2028. 0 of the 81 units on this registration are recorded sold or booked, and 55 of 730 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NamePool City Lakshadweep Villa
- TypeResidential / Group Housing
- Location
- -
- Vafe
- Shahapur
- Vafe
- Shahapur
- Thane
- 421601
- Pincode421601
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR1330002500101
- ReraGenie IDRG-MH-32210
Builder
- NameMeravilla Infra Private Limited
- Entity typeCompany
- CINU70109MH2020PTC339769
- DirectorsPratik Hitesh Shah, Sagar Rashmikant Chheda
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on23 Jun 2025
- Promised completion31 Dec 2028
- Revised completionNone
- Buildings81 building records
- Documents filed19 files
Current status
Figures as on 1 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| RH - 1 | 1 | 1 | 1 | 1 | 0 | 1 |
| RH - 1 | 2 | 1 | 1 | 1 | 0 | 1 |
| RH - 1 | 3 | 1 | 1 | 1 | 0 | 1 |
| RH - 1 | 4 | 1 | 1 | 1 | 0 | 1 |
| RH - 1 | 5 | 1 | 1 | 1 | 0 | 1 |
| RH - 1 | 6 | 1 | 1 | 1 | 0 | 1 |
| RH - 1 | 7 | 1 | 1 | 1 | 0 | 1 |
| RH - 1 | 8 | 1 | 1 | 1 | 0 | 1 |
| RH - 1 | 9 | 1 | 1 | 1 | 0 | 1 |
| RH - 1 | 10 | 1 | 1 | 1 | 0 | 1 |
| RH - 1 | 11 | 1 | 1 | 1 | 0 | 1 |
| RH - 1 | 12 | 1 | 1 | 1 | 0 | 1 |
| RH - 2 | 13 | 1 | 1 | 1 | 0 | 1 |
| RH - 2 | 14 | 1 | 1 | 1 | 0 | 1 |
| RH - 2 | 15 | 1 | 1 | 1 | 0 | 1 |
| RH - 2 | 16 | 1 | 1 | 1 | 0 | 1 |
| RH - 2 | 17 | 1 | 1 | 1 | 0 | 1 |
| RH - 2 | 18 | 1 | 1 | 1 | 0 | 1 |
| RH - 2 | 19 | 1 | 1 | 1 | 0 | 1 |
| RH - 2 | 20 | 1 | 1 | 1 | 0 | 1 |
| RH - 2 | 21 | 1 | 1 | 1 | 0 | 1 |
| RH - 2 | 22 | 1 | 1 | 1 | 0 | 1 |
| RH - 2 | 23 | 1 | 1 | 1 | 0 | 1 |
| RH - 2 | 24 | 1 | 1 | 1 | 0 | 1 |
| RH - 3 | 25 | 1 | 1 | 1 | 0 | 1 |
| RH - 3 | 26 | 1 | 1 | 1 | 0 | 1 |
| RH - 3 | 27 | 1 | 1 | 1 | 0 | 1 |
| RH - 3 | 28 | 1 | 1 | 1 | 0 | 1 |
| RH - 3 | 29 | 1 | 1 | 1 | 0 | 1 |
| RH - 3 | 30 | 1 | 1 | 1 | 0 | 1 |
| RH - 3 | 31 | 1 | 1 | 1 | 0 | 1 |
| RH - 3 | 32 | 1 | 1 | 1 | 0 | 1 |
| RH - 3 | 33 | 1 | 1 | 1 | 0 | 1 |
| RH - 3 | 34 | 1 | 1 | 1 | 0 | 1 |
| RH - 3 | 35 | 1 | 1 | 1 | 0 | 1 |
| RH - 3 | 36 | 1 | 1 | 1 | 0 | 1 |
| RH - 4 | 37 | 1 | 1 | 1 | 0 | 1 |
| RH - 4 | 38 | 1 | 1 | 1 | 0 | 1 |
| RH - 4 | 39 | 1 | 1 | 1 | 0 | 1 |
| RH - 4 | 40 | 1 | 1 | 1 | 0 | 1 |
| RH - 5 | 41 | 1 | 1 | 1 | 0 | 1 |
| RH - 5 | 42 | 1 | 1 | 1 | 0 | 1 |
| RH - 5 | 43 | 1 | 1 | 1 | 0 | 1 |
| RH - 5 | 44 | 1 | 1 | 1 | 0 | 1 |
| RH - 5 | 45 | 1 | 1 | 1 | 0 | 1 |
| RH - 6 | 46 | 1 | 1 | 1 | 0 | 1 |
| RH - 6 | 47 | 1 | 1 | 1 | 0 | 1 |
| RH - 6 | 48 | 1 | 1 | 1 | 0 | 1 |
| RH - 6 | 49 | 1 | 1 | 1 | 0 | 1 |
| RH - 6 | 50 | 1 | 1 | 1 | 0 | 1 |
| RH - 6 | 51 | 1 | 1 | 1 | 0 | 1 |
| RH - 6 | 52 | 1 | 1 | 1 | 0 | 1 |
| RH - 6 | 53 | 1 | 1 | 1 | 0 | 1 |
| RH - 6 | 54 | 1 | 1 | 1 | 0 | 1 |
| RH - 6 | 55 | 1 | 1 | 1 | 0 | 1 |
| RH - 6 | 56 | 1 | 1 | 1 | 0 | 1 |
| RH - 6 | 57 | 1 | 1 | 1 | 0 | 1 |
| RH - 7 | 58 | 1 | 1 | 1 | 0 | 1 |
| RH - 7 | 59 | 1 | 1 | 1 | 0 | 1 |
| RH - 7 | 60 | 1 | 1 | 1 | 0 | 1 |
| RH - 7 | 61 | 1 | 1 | 1 | 0 | 1 |
| RH - 7 | 62 | 1 | 1 | 1 | 0 | 1 |
| RH - 7 | 63 | 1 | 1 | 1 | 0 | 1 |
| RH - 7 | 64 | 1 | 1 | 1 | 0 | 1 |
| RH - 7 | 65 | 1 | 1 | 1 | 0 | 1 |
| RH - 7 | 66 | 1 | 1 | 1 | 0 | 1 |
| RH - 7 | 67 | 1 | 1 | 1 | 0 | 1 |
| RH - 7 | 68 | 1 | 1 | 1 | 0 | 1 |
| RH - 7 | 69 | 1 | 1 | 1 | 0 | 1 |
| RH - 8 | 70 | 1 | 1 | 1 | 0 | 1 |
| RH - 8 | 71 | 1 | 1 | 1 | 0 | 1 |
| RH - 8 | 72 | 1 | 1 | 1 | 0 | 1 |
| RH - 8 | 73 | 1 | 1 | 1 | 0 | 1 |
| RH - 8 | 74 | 1 | 1 | 1 | 0 | 1 |
| RH - 8 | 75 | 1 | 1 | 1 | 0 | 1 |
| RH - 8 | 76 | 1 | 1 | 1 | 0 | 1 |
| RH - 8 | 77 | 1 | 1 | 1 | 0 | 1 |
| RH - 8 | 78 | 1 | 1 | 1 | 0 | 1 |
| RH - 8 | 79 | 1 | 1 | 1 | 0 | 1 |
| RH - 8 | 80 | 1 | 1 | 1 | 0 | 1 |
| RH - 8 | 81 | 1 | 1 | 1 | 0 | 1 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 1 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 81 buildings; the table lists the first 20.
55 of 730 construction stages are filed complete across 81 buildings. The stage furthest along is Slabs of Super Structure, at 75%.
RH - 1 · wing 10%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RH - 1 · wing 20%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RH - 1 · wing 311%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RH - 1 · wing 411%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RH - 1 · wing 511%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RH - 1 · wing 611%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RH - 1 · wing 711%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RH - 1 · wing 811%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RH - 1 · wing 911%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RH - 1 · wing 1011%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RH - 1 · wing 1111%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RH - 1 · wing 1211%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RH - 2 · wing 1311%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RH - 2 · wing 1411%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RH - 2 · wing 1511%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RH - 2 · wing 1611%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RH - 2 · wing 1711%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RH - 2 · wing 1811%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RH - 2 · wing 1911%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RH - 2 · wing 200%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 1 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | 0% |
| Water Supply | No | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | 0% |
| Storm Water Drains | No | 0% |
| Landscaping & Tree Planting | No | 0% |
| Street Lighting | No | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed81
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Stilt / Ground | Total |
|---|---|---|
| RH - 1 1 | 1 | 1 |
| RH - 1 2 | 1 | 1 |
| RH - 1 3 | 1 | 1 |
| RH - 1 4 | 1 | 1 |
| RH - 1 5 | 1 | 1 |
| RH - 1 6 | 1 | 1 |
| RH - 1 7 | 1 | 1 |
| RH - 1 8 | 1 | 1 |
| RH - 1 9 | 1 | 1 |
| RH - 1 10 | 1 | 1 |
| RH - 1 11 | 1 | 1 |
| RH - 1 12 | 1 | 1 |
| RH - 2 13 | 1 | 1 |
| RH - 2 14 | 1 | 1 |
| RH - 2 15 | 1 | 1 |
| RH - 2 16 | 1 | 1 |
| RH - 2 17 | 1 | 1 |
| RH - 2 18 | 1 | 1 |
| RH - 2 19 | 1 | 1 |
| RH - 2 20 | 1 | 1 |
| RH - 2 21 | 1 | 1 |
| RH - 2 22 | 1 | 1 |
| RH - 2 23 | 1 | 1 |
| RH - 2 24 | 1 | 1 |
| RH - 3 25 | 1 | 1 |
| RH - 3 26 | 1 | 1 |
| RH - 3 27 | 1 | 1 |
| RH - 3 28 | 1 | 1 |
| RH - 3 29 | 1 | 1 |
| RH - 3 30 | 1 | 1 |
| RH - 3 31 | 1 | 1 |
| RH - 3 32 | 1 | 1 |
| RH - 3 33 | 1 | 1 |
| RH - 3 34 | 1 | 1 |
| RH - 3 35 | 1 | 1 |
| RH - 3 36 | 1 | 1 |
| RH - 4 37 | 1 | 1 |
| RH - 4 38 | 1 | 1 |
| RH - 4 39 | 1 | 1 |
| RH - 4 40 | 1 | 1 |
| RH - 5 41 | 1 | 1 |
| RH - 5 42 | 1 | 1 |
| RH - 5 43 | 1 | 1 |
| RH - 5 44 | 1 | 1 |
| RH - 5 45 | 1 | 1 |
| RH - 6 46 | 1 | 1 |
| RH - 6 47 | 1 | 1 |
| RH - 6 48 | 1 | 1 |
| RH - 6 49 | 1 | 1 |
| RH - 6 50 | 1 | 1 |
| RH - 6 51 | 1 | 1 |
| RH - 6 52 | 1 | 1 |
| RH - 6 53 | 1 | 1 |
| RH - 6 54 | 1 | 1 |
| RH - 6 55 | 1 | 1 |
| RH - 6 56 | 1 | 1 |
| RH - 6 57 | 1 | 1 |
| RH - 7 58 | 1 | 1 |
| RH - 7 59 | 1 | 1 |
| RH - 7 60 | 1 | 1 |
| RH - 7 61 | 1 | 1 |
| RH - 7 62 | 1 | 1 |
| RH - 7 63 | 1 | 1 |
| RH - 7 64 | 1 | 1 |
| RH - 7 65 | 1 | 1 |
| RH - 7 66 | 1 | 1 |
| RH - 7 67 | 1 | 1 |
| RH - 7 68 | 1 | 1 |
| RH - 7 69 | 1 | 1 |
| RH - 8 70 | 1 | 1 |
| RH - 8 71 | 1 | 1 |
| RH - 8 72 | 1 | 1 |
| RH - 8 73 | 1 | 1 |
| RH - 8 74 | 1 | 1 |
| RH - 8 75 | 1 | 1 |
| RH - 8 76 | 1 | 1 |
| RH - 8 77 | 1 | 1 |
| RH - 8 78 | 1 | 1 |
| RH - 8 79 | 1 | 1 |
| RH - 8 80 | 1 | 1 |
| RH - 8 81 | 1 | 1 |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Ravindra Manilal Sanghvi | Greater Mumbai (M Corp.) (Part) (802794) | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 1.34 cr | - |
| RH - 1 | 1 | Rs 33.11 lakh | Rs 3.54 lakh |
| RH - 1 | 2 | Rs 33.11 lakh | Rs 3.54 lakh |
| RH - 1 | 3 | Rs 33.11 lakh | Rs 3.54 lakh |
| RH - 1 | 4 | Rs 33.11 lakh | Rs 3.54 lakh |
| RH - 1 | 5 | Rs 33.11 lakh | Rs 3.54 lakh |
| RH - 1 | 6 | Rs 33.11 lakh | Rs 3.54 lakh |
| RH - 1 | 7 | Rs 33.11 lakh | Rs 3.54 lakh |
| RH - 1 | 8 | Rs 33.11 lakh | Rs 3.54 lakh |
| RH - 1 | 9 | Rs 33.11 lakh | Rs 3.54 lakh |
| RH - 1 | 10 | Rs 33.11 lakh | Rs 3.54 lakh |
| RH - 1 | 11 | Rs 33.11 lakh | Rs 3.54 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Amit Ananta Patil |
| Engineer | S K Consultants & Engineers |
| Engineer | NEXUS Consultants & Engineers |
| Chartered Accountant | Pranav Bhaskaran & Associates |
| Partner | Role in project |
|---|---|
| Meravilla Infra Private Limited | - |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12602568 | Parag Dilip Singh Bhadoria | Meravilla Infra Private Limited | 02/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportNot on the file
A lawyer's report on who owns the land and what is registered against it.
- Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 May 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 May 2025 - Commencement CertificateNot on the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
- Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2028
Documents filed19
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 - Pool City Lakshadweep Villa as on Dec 2025_signed.pdf | 1 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 - Pool City Lakshadweep Villa as on March 2026_signed.pdf | 1 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 - Pool City Lakshadweep Villa as on Dec 2025.pdf | 1 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 - Pool City Lakshadweep Villa March 2026.pdf | 1 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 - Pool City Lakshadweep Villa as on Dec 2025.pdf | 1 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 - Pool City Lakshadweep Villa March 2026.pdf | 1 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 - Pool City Lakshadweep Villa as on June 2025_signed.pdf | 21 May 2026 |
| Withdrawal Update Form 1File: Form 1 - Pool City Lakshadweep Villa as on Sep 2025_signed.pdf | 21 May 2026 |
| Withdrawal Update Form 2File: Form 2 - Pool City Lakshadweep Villa as on June 2025.pdf | 21 May 2026 |
| Withdrawal Update Form 2File: Form 2 - Pool city Lakshadweep Villa as on Sept 2025.pdf | 21 May 2026 |
| Withdrawal Update Form 3File: Form 3 - Pool City Lakshadweep Villa as on June 2025.pdf | 21 May 2026 |
| Withdrawal Update Form 3File: Form 3 - Pool city Lakshadweep Villa - Sept 2025.pdf | 21 May 2026 |
| Layout approvalFile: plot 12 to 27 - page 1.pdf | 27 May 2025 |
| Building plan approvalFile: plot 12 to 27 - page 2.pdf | 27 May 2025 |
| Building plan approvalFile: plot 12 to 27 - page 3.pdf | 27 May 2025 |
| Building plan approvalFile: plot 12 to 27 - page 4.pdf | 27 May 2025 |
| Building plan approvalFile: plot 12 to 27 - page 5.pdf | 27 May 2025 |
| Building plan approvalFile: plot 12 to 27 - page 6.pdf | 27 May 2025 |
| Declaration and undertaking (Annexure A)File: Annexure A - Order No 50.pdf | 26 May 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 19 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Pool City Lakshadweep Villa on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Vafe, Shahapur7,600+ in Thane
Filed coordinates, straight-line distance. 23 registered projects within 2 km.
BELLA VISTA PHASE 8
INDO ASIAN BUILDCON PVT LTD
RUSTOMJEE BELLE VUE
KEYSTONE REALTORS LIMITED
THE VENISCAPE
MIVAAN BUILDCON PRIVATE LIMITED
VISION SKY WORLD
M/S VISION SKY WORLD
Sunteck FORESTWorld 1
SUNTECK REALTY HOLDINGS PVT LTD
Sunteck FORESTWorld 2
SUNTECK REALTY HOLDINGS PVT LTD
See every Thane project, with the district possession charts
Builder: Meravilla Infra Private Limited
Meravilla Infra Private Limited has 1 registration on MahaRERA, including Pool City Lakshadweep Villa. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if Pool City Lakshadweep Villa is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Pool City Lakshadweep Villa?
The registered promoter entity is Meravilla Infra Private Limited, a company as per the filing. Its CIN U70109MH2020PTC339769 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Pool City Lakshadweep Villa?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Pool City Lakshadweep Villa?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Pool City Lakshadweep Villa?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Pool City Lakshadweep Villa?
The professionals named in the filing: Architect: Amit Ananta Patil; Engineer: S K Consultants & Engineers; Engineer: NEXUS Consultants & Engineers; Chartered Accountant: Pranav Bhaskaran & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Pool City Lakshadweep Villa?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback