Home / Browse projects / Raigarh, Maharashtra / Plot No. 39 Sector-14 Kharghar Bus Depot

Registered No litigation declared Others project

Plot No. 39 Sector-14 Kharghar Bus Depot

By CITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED

RG-MH-29174 · RERA P52000028196 · Last updated on MahaRERA portal: 24 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 34 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Apr 2028Possession promisedmoved 34 months from the original
52 of 121Construction stages doneacross 11 buildings; furthest along: Slabs of Super Structure, 95%
0Complaints at MahaRERAon this registration
Jump to the 102 documents Report an error

Plot No. 39 Sector-14 Kharghar Bus Depot is a Others project by CITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED in Raigarh, Maharashtra, registered with MahaRERA as P52000028196 on 10 Feb 2021. Possession is promised by 30 Apr 2028. The completion date has moved by 34 months from the original filing.

At a glance

Project

  • NamePlot No. 39 Sector-14 Kharghar Bus Depot
  • TypeOthers
  • Location
    • Sector -14
    • Kharghar
    • Panvel
    • Raigarh
    • 410210
  • Pincode410210
  • RERA no.P52000028196
  • ReraGenie IDRG-MH-29174

Builder

  • NameCITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED
  • Entity typeCompany
  • Other registrations21 more →
  • Completed7 of 22
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects7 →

Key dates

this monthRegisteredFeb 2021First promiseJun 2025Revised toApr 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 Feb 2021
  • Promised completion30 Apr 2028
  • Revised completionRevised to 30 Apr 2028 (originally 30 Jun 2025)
  • Buildings11 building records
  • Documents filed102 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
E-B-01NA270000
E-B-02NA270000
E-B-03NA270000
E-B-04NA270000
E-B-05NA270000
E-B-06NA270000
E-B-07NA270000
E-B-08NA270000
E-B-09NA270000
E-B-10NA270000
CommercialNA10000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building11

As on 24 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

52 of 121 construction stages are filed complete across 11 buildings. The stage furthest along is Slabs of Super Structure, at 95%.

E-B-0146%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure3%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
E-B-0232%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)50%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
E-B-0329%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)15%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
E-B-0448%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure27%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises1%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
E-B-0549%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure32%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises1%
Sanitary Fittings within the flats / premises1%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
E-B-0656%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure91%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises23%
Sanitary Fittings within the flats / premises3%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
E-B-0757%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises3%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
E-B-0858%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises32%
Sanitary Fittings within the flats / premises4%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
E-B-0958%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises37%
Sanitary Fittings within the flats / premises4%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
E-B-1059%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises39%
Sanitary Fittings within the flats / premises5%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Commercial27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed446

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots446
Closed/Covered446
BuildingClosed/CoveredTotal
E-B-014343
E-B-024343
E-B-034343
E-B-044343
E-B-054343
E-B-064343
E-B-074343
E-B-084343
E-B-094343
E-B-104343
Commercial1616

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area27,217 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI57775.93
Proposed, not sanctioned57,776 sq m
Buildings approved11
Buildings sanctioned11

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCIDCO BHAWAN, GROUND FLOOR, CBD BELAPUR, NAVI MUMBAI 400614

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Chartered AccountantN B Sayed & Associates
PartnerRole in project
CITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000027553Jun 2025 → Apr 2028

Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 30/04/2028 to complete the project and fulfil all regulatory requirements.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Dec 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Jan 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Jan 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Jan 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2028

Documents filed102

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 102 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 - Kharghar Bus Depot as on March 2026.pdf24 Jun 2026
Form 2File: Form 2 - Kharghar Bus Depot as on March 2026.pdf24 Jun 2026
Form 3File: Form 3 Kharghar Bus Depot as on 31-12-2025.pdf24 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Kharghar Bus Depot as on Dec 2025.pdf24 Jun 2026
Form 5 (FY 2024-2025)File: Final Form 5 of Kharghar Bus Depot as on 31-03-2025.pdf8 Jun 2026
Form 1File: Form 1 Kharghar Bus Depot as on Dec 2025.pdf17 Feb 2026
Form 2File: Form 2 - Kharghar Bus Depot as on Dec 2025.pdf17 Feb 2026
Form 3File: Form 3 Kharghar Bus Depot as on 31-12-2025.pdf17 Feb 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Kharghar Bus Depot as on Dec 2025.pdf17 Feb 2026
Form 1File: Form 1 Kharghar Bus Depot as on 30-09-2025.pdf17 Feb 2026
Form 2File: Form 2 - Kharghar Bus Depot as on Sep 2025.pdf17 Feb 2026
Form 3File: Form 3 Kharghar Bus Depot as on 30-09-2025 Final.pdf17 Feb 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Kharghar Bus Depot as on Sep 2025.pdf17 Feb 2026
Form 1File: Form 1 - Kharghar Bus Depot as on June 2025 (Signed).PDF3 Jan 2026
Form 2File: Form 2 - Kharghar Bus Depot as on June 2025 (Signed).PDF3 Jan 2026
Form 3File: Form 3 - Kharghar Bus Depot as on June 2025 (Signed)_compressed.pdf3 Jan 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Kharghar Bus Depot as on Sep 2025.pdf3 Jan 2026
Form 1File: Form 1 Kharghar Bus Depot as on 30-09-2025.pdf3 Jan 2026
Form 2File: Form 2 - Kharghar Bus Depot as on Sep 2025.pdf3 Jan 2026
Form 3File: Form 3 Kharghar Bus Depot as on 30-09-2025 Final_compressed.pdf3 Jan 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Kharghar Bus Depot as on Sep 2025.pdf3 Jan 2026
Disclosure of sold/ booked inventoryFile: KHBD.pdf23 Jun 2025
Disclosure of sold/ booked inventoryFile: Circular 29_11zon (1).pdf23 Jun 2025
Disclosure of sold/ booked inventoryFile: 3 Disclosure of sold_ booked inventory (3) (1)_11zon.pdf23 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Kharghar Bus Depot as on 31-03-2025.pdf20 Jun 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 of Kharghar Bus Depot as on FY 2023-24.pdf19 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kharghar Bus Depot as on March 2025.pdf14 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Kharghar Bus Depot as on March 2025.pdf16 May 2025
Disclosure of sold/ booked inventoryFile: Circular 29 KBD_11zon.pdf11 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Kharghar Bus Depot as on 31-12-2024.pdf20 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Kharghar Bus Depot as on 30-09-2024.pdf20 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Kharghar Bus Depot as on 30-06-2024.pdf20 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Kharghar Bus Depot as on 31-03-2024 Final.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kharghar Bus Depot as on March 2024.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kharghar Bus Depot as on June 2024.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kharghar Bus Depot as on Sep 2024.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kharghar Bus Depot as on Dec 2024.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kharghar Bus Depot - Sep 23.pdf15 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kharghar Bus Depot - Dec 23.pdf15 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kharghar Bus Depot - Mar 24.pdf15 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kharghar Bus Depot - June 24.pdf15 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kharghar Bus Depot - Sep 24.pdf15 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kharghar Bus Depot - Dec 24.pdf15 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KHBD DEC2023_compressed.pdf13 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KHBD SEPT2023_compressed.pdf13 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KHBD JUN2023_compressed.pdf13 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KHBD MAR2023_compressed.pdf13 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kharghar Bus Depot Sec-14 30623.pdf10 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kharghar Bus Depot Sec-14 30923.pdf10 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kharghar Bus Depot Sec-14 301223.pdf10 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kharghar Bus Depot Sec-14 30323.pdf10 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dec 2023 KHBD.pdf10 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Jun 2023 Form-II KHBD.pdf10 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: March 2023 Form-II KHBD.pdf10 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sept 2023 KHBD.pdf10 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sec 14 Kharghar Bus Depot Dec 23_compressed.pdf3 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sec 14 Kharghar Bus Depot Sept 23_compressed.pdf3 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sec 14 Kharghar Bus Depot June 23_compressed.pdf3 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sec 14 Kharghar Bus Depot Mar 23_compressed.pdf3 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Kharghar BD June 23.pdf3 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Kharghar Bus Depot FY 20-21.pdf19 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Kharghar Bus Depot FY 22-23.pdf19 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Kharghar Bus Depot FY 21-22.pdf19 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form- 2A-Plot 39 Kharghar.pdf13 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate.pdf24 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer’s Certificate on Cost Incurred on Project.pdf7 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer’s Certificate on Cost Incurred on Project.pdf7 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect’s Certificate of Percentage of Completion of Work.pdf3 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineers Certificate on Quality Assurance.pdf3 Jun 2023
Declaration about Commencement CertificateFile: Format D- Kharghar Bus Depot.pdf1 Jun 2023
Disclosure of sold/ booked inventoryFile: Circular 29- Kharghar Bus Depot_compressed.pdf1 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A- Kharghar bus Depot- Dec 21.pdf3 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A- Kharghar bus Depot- Mar 22.pdf3 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A- Kharghar bus Depot - Jun 22.pdf3 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A- Kharghar bus Depot- Sept 22.pdf3 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A- Kharghar bus Depot- Dec 22.pdf3 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Dec 2021 Kharghar Bus Depot_11zon.pdf29 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Mar 2022 Kharghar Bus Depot_11zon.pdf29 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Jun 2022 Kharghar Bus Depot_11zon.pdf29 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sept 2022 Kharghar Bus Depot_11zon.pdf29 Mar 2023

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
SWAPNAPOORTI HOUSING SCHEMEPlot No -2 Sector -36 Kharghar Navi Mumbai3,590CompletedMay 2015Late, Jun 2016
VALLEY SHILP HOUSING SCHEMEPlot No -3 Sector 36 Kharghar Navi Mumbai1,224CompletedMay 2014Late, May 2015

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 34 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Plot No. 39 Sector-14 Kharghar Bus Depot on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kharghar5,900+ in Raigarh

Builder: CITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED

CITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED has 22 registrations on MahaRERA, including SECTOR 21 TALOJA and SECTOR 22, TALOJA. Its filings disclose 7 earlier MahaRERA projects: declares 0 of 7 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Plot No. 39 Sector-14 Kharghar Bus Depot is delayed beyond 30 Apr 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Plot No. 39 Sector-14 Kharghar Bus Depot?

The registered promoter entity is CITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Plot No. 39 Sector-14 Kharghar Bus Depot?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Plot No. 39 Sector-14 Kharghar Bus Depot?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Plot No. 39 Sector-14 Kharghar Bus Depot?

The professionals named in the filing: Chartered Accountant: N B Sayed & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Plot No. 39 Sector-14 Kharghar Bus Depot?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Plot No. 39 Sector-14 Kharghar Bus Depot. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Plot No. 39 Sector-14 Kharghar Bus Depot to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.